The document appears to be a work schedule spreadsheet (CTR078665) for a demolition project involving right of way parcels 7-12414 and 7-12373, detailing a specific construction/demolition timeline. While specific state or agency details are not fully evident, the work schedule indicates a structured demolition plan with precise daily activities and timing.
The demolition work is scheduled from 9/23/25 to 10/17/25, involving two separate parcels with distinct demolition phases. The work will occur Monday through Friday from 6:00am to 4:00pm, with specific activities including mobilization, structure demolition, debris removal to landfill, site stabilization, and demobilization. The project includes NESHAP (National Emission Standards for Hazardous Air Pollutants) compliance, and follows a sequential process for each parcel: mobilization, demolition and debris removal, and final demobilization. Each parcel (7-12414 and 7-12373) has a slightly different timeline but follows a similar operational workflow.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Demolition of Right of Way Parcels | |
| 7-12414 & 7-12373 | Start |
Date:
| 9/23/25 | Duration | 10/17/25 | 10/6/25 | 10/7/25 | 10/8/25 | 10/9/25 | 10/10/25 | 10/13/25 | 10/14/25 | 10/15/25 | 10/16/25 | 10/17/25 | |||||||
| Activity | Start | Duration | End | M | T | W | Th | F | M | T | W | Th | F | M | T | W | Th | F | |
| File NESHAP | 9/23/25 | 10 | 10/3/25 | ||||||||||||||||
| 7-12414 | |||||||||||||||||||
| Mobilize, begin demo of structure | 10/6/25 | 1 | 10/6/25 | ||||||||||||||||
| Demo, load out debris to landfill, berm and stabilize | 10/7/25 | 3 | 10/9/25 | ||||||||||||||||
| Demob | 10/10/25 | 1 | 10/10/25 |
| 7-12373 | |||
| Mobilize, begin demo of structure | 10/13/25 | 1 | 10/13/25 |
| Demo, load out debris to landfill, berm and stabilize | 10/14/25 | 3 | 10/16/25 |
| Demob | 10/17/25 | 1 | 10/17/25 |
Work will occur Monday - Friday 6:00am to 4:00pm image1.png