CTR078665_Contract_Amendment_One.pdf
PDF 700 KB Posted
- Attached to
- Master Agreement AZ|CTR078665
- Contract number
- CTR078665
- Issued by
- Arizona
About this file
The document is a Contract Amendment Summary from the Arizona Department of Transportation (ADOT) involving MP Environmental Services as the contractor. The amendment pertains to the demolition of Parcels 7-12414 and 7-12373, specifically modifying an existing contract through Amendment No. One (1).
The amendment adds a new requirement for the contractor to remove approximately 25 feet of piping and excavate a 4-foot wide by 4-foot deep trench to expose existing Salt River Project (SRP) electrical wiring. A corresponding line item, CTR078665-5 for Removal of Piping and Excavation for SRP Electrical Work, has been added to the Arizona Procurement Portal with a cost of $2,440.00. The detailed cost breakdown includes labor (operators, technicians, project manager), equipment (roll-off truck, excavator, skid steer), and other expenses like profile fees and disposal costs. The work is located at 7209 W. Wier and involves transite pipe removal and disposal, with a project estimated completion date of October 17, 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CTR078665 Post Award Agenda.docx | DOCX document | |
| CTR078665 Work Schedule - BPM007066.xlsx | XLSX spreadsheet | |
| CTR078665 Key Personnel.pdf | ||
| CTR078665 Post Award Meeting Sign-In Sheet.pdf | ||
| CTR078665 Site Specific Health and Safety Plan.pdf | ||
| CTR078665 - Payment Bond.pdf | ||
| CTR078665_ACCEPTED_ANY_ALL_GL_AL_WC_10.01.24-01.01.26.pdf | ||
| CTR078665_Contract_Documents.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARIZONA DEPARTMENT OF TRANSPORTATION
1655 W. Jackson Street, MD 100P
Phoenix, AZ 85007
Contract Amendment Summary CONTRACTOR: MP Environmental Services AMENDMENT NO.: One (1) DESCRIPTION: Demolition of Parcels 7-12414 and 7-12373
Rev. 03/2025
Pursuant to the Uniform Terms and Conditions, Section 5, Contract Changes, the above referenced contract is amended. Summary of changes is as follows:
1. Contract Requirements, Section 4 Specific Requirements, Section 4.1.5 Demolition and Site
Clearance Section 4.1.5.1.7. has been added to read as follows:
• The Contractor shall remove approximately twenty-five (25) feet of piping and excavate a trench approximately four (4) feet wide by four (4) feet deep to expose existing SRP electrical wiring. The Contractor shall backfill the four (4) foot wide by four (4) feet deep trench once SRP or the applicable utility has completed all electrical work. The Contractor shall adhere to the specified backfilling requirements in Section 4.1.6. – Excavation and Backfilling.
2. Contract Pricing The following line item has been added in the Arizona Procurement Portal (APP), Pricing Tab.
• CTR078665-5 Removal of Piping and Excavation for SRP Electrical Work $2,440.00.
3. All other terms, conditions and provisions of this contract remain unchanged.
Quantity Rate Total
Operator (Asbestos worker) 6 Hour 65.00$ 390.00$
Technician (Asbestos worker) 3 Hour 50.00$ 150.00$
Project Manager 1 Hour 85.00$ 85.00$
Subtotal 625.00$
Equipment Quantity Rate Total
Roll off Truck and bin 6 Day 140.00$ 840.00$ excavator Day n/c
Skid steer 1 Each 300.00$ 300.00$
Crew truck and trailer 1 each 250.00$ 250.00$
Subtotal 1,390.00$
Other Quantity Rate Total
Profile Fee 1 75.00$ 75.00$
Disposal (Minimum) 1 Each 350.00$ 350.00$
FSC (Fuel Surcharge) Included
Subtotal 425.00$
Total Estimated Cost 2,440.00$ https://www.eia.gov/petroleum/gasdiesel/Fuel Surcharge (FSC) - changes weekly based of EIA calculation :
MP Environmental Services, Inc.
3045 South 51st Avenue
Phoenix, AZ 85043
602-278-6233 Office
Project Manager: Brendan Mills
Customer: ADOT
Description of work: Transite pipe removal and disposal; SRP dig & backfill Location: 7209 W. Wier Contact: Amy. MacGregor Date: Oct 17 2025
Labor
Type of Quote:
**This is not a contract for work; Estimate only.
*Demurrage rate will be applied to load rate after 1 hour load/offload at $90.00per hour charged in 1/4 hour increments https://www.eia.gov/petroleum/gasdiesel/