This is a Contract Amendment Summary from the Arizona Department of Transportation (ADOT), located in Phoenix, AZ, involving American Road Maintenance, Inc. as the contractor. The document is Amendment No. Two (2) for a project involving the Airport Pavement Management System (APMS) Construction at nine different airports.
The amendment adjusts the contract line item costs for three specific airports: St. Johns Industrial Airpark (increased from $197,659.50 to $219,431.40), Wickenburg Municipal Airport (increased from $248,113.00 to $328,021.60), and Winslow-Lindberg Regional Airport (decreased from $123,361.50 to $109,269.00). These changes are based on technical specifications and drawings, with corresponding Change Orders (COs) attached. All other terms, conditions, and provisions of the original contract remain unchanged. The amendment is dated for revision in 11/2024 and follows the Uniform Terms and Conditions, Section 5, regarding Contract Changes.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARIZONA DEPARTMENT OF TRANSPORTATION
1655 W. Jackson Street, MD 100P
Phoenix, AZ 85007
Contract Amendment Summary CONTRACTOR: American Road Maintenance, Inc. AMENDMENT NO.: Two (2)
DESCRIPTION: Airport Pavement Management System (APMS) Construction at 9 Airports
Rev. 11/2024
Pursuant to the Uniform Terms and Conditions, Section 5, Contract Changes, the above referenced contract is amended. Summary of changes is as follows:
1. Line item CTR069182-8 St. Johns Industrial Airpark per the technical specifications & drawings increased from $197,659.50 to $219,431.40 total cost. See attached CO.
2. Line item CTR069182-9 Wickenburg Municipal Airport per the technical specifications & drawings increased from $248,113.00 to $328,021.60 total cost. See attached CO.
3. Line item CTR069182-10 Winslow-Lindberg Regional Airport per the technical specifications & drawings decreased from $123,361.50 to $109,269.00 total cost. See attached CO.
4. All other terms, conditions and provisions of this contract remain unchanged.