CTR064363_Pricing.xlsx
XLSX spreadsheet 407 KB Posted
- Attached to
- Master Agreement AZ|CTR064363
- Contract number
- CTR064363
- Issued by
- Arizona
About this file
This document is a comprehensive pricing sheet for ITS (Intelligent Transportation Systems) Installation, Repair and Replacement Services submitted by CS Construction, Inc. The pricing document appears to be part of a state or local government contract, though the specific jurisdiction is not explicitly named in the provided excerpt.
The pricing sheet details labor rates, equipment rates, and subcontractor pricing for various technical services. Labor classifications include electricians, signal technicians, crane operators, and project managers, with hourly rates ranging from $67 to $140. Equipment pricing covers utility trucks, boom trucks, cranes, and specialized vehicles with hourly rates between $25 and $250. The contractor offers a consistent 15% cost-plus markup for materials, traffic control services, and subcontractor work. Additional pricing components include a daily per diem rate of $150 for locations 60 miles outside Phoenix and various traffic control equipment rentals. The document provides a comprehensive rate structure for infrastructure and transportation-related installation and repair services, suggesting a detailed government contract for technical infrastructure work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Labor Rates and Classifications
| PRICING SHEET |
| ITS Installation, Repair and Replacement Services |
OFFEROR: CS Construction, Inc.
Labor Rates
Instructions: Labor Classifications: The Contractor shall provide labor rates for any labor levels that may be applicable to the service being offered.The labor rates listed below will be used for evaluation purposes. The Contractor must use additional lines to fill in any other classifications that are being offered. Below indicate labor rates as required in paragraph 4.6.3.1 in the scope of work.
| Labor Classificiation | Hourly Rate | Notes |
| Electrician | $105.00 | Port to Port |
| Crew Lead (Foreman) | $105.00 | Port to Port |
| Signal & Lighting Technician | $78.00 | Port to Port |
| Boom Truck Operator | $88.00 | Port to Port |
| Backhoe Operator | $85.00 | Port to Port |
| Project Manager | $125.00 | Port to Port |
| Crane Operator (up to 50 TN) | $140.00 | Port to Port |
| Dump Truck Driver | $75.00 | Port to Port |
| Laborer | $67.00 | Port to Port |
| Superintendent | $130.00 | Port to Port |
| Hydrovac Truck Operator | $82.00 | Port to Port |
| Fiber Optic Technician | $95.00 | Port to Port |
| Per Diem / Subsistence | $150.00 | Daily Rate per Person (Locations 60 miles outside of Phoenix) |
Materials Pricing
| PRICING SHEET |
| ITS Installation, Repair and Replacement Services |
OFFEROR: CS Construciton, Inc.
Materials Pricing
Instructions: Materials Pricing: The Contractor shall provide a Cost-Plus-Fixed Percentage for any Material classifications that may be applicable to the service being offered. The Contractor must use additional lines to fill in any classifications that are being offered. Below indicate fixed percentage as required in paragraph 4.11.1 in the scope of work.
| Material Classifications | Cost-Plus-Fixed Percentage (%) | Notes |
| All Material Categories | 15% |
Equipment Pricing
| PRICING SHEET |
| ITS Installation, Repair and Replacement Services |
OFFEROR: CS Construction, Inc.
Equipment Pricing
Instructions: Equipment Pricing: The Contractor shall provide a Hourly Rate for any Equipment that may be applicable to the service being offered.The Equipment Classifications listed below will be used for evaluation purposes. The Contractor must use additional lines to fill in any other classifications that are being offered. Below indicate equipment daily rate as required in paragraph 4.12 in the scope of work.
| Equipment Classification | Hourly Rate | Notes |
| Utility/ Pickup Truck | $26.00 | Port to Port |
| Boom/ Bucket Truck | $65.00 | Port to Port |
| Air Compressor | $26.00 | Port to Port |
| Skip Loader | $35.00 | Port to Port |
| Backhoe | $50.00 | Port to Port |
| Crane (up to 50 TN) | $210.00 | Port to Port |
| 10 Wheeler Dump Truck | $250.00 | Port to Port |
| Transport Truck | $65.00 | Port to Port |
| Hydrovac Truck | $135.00 | Port to Port |
| Fiber Van / Trailer | $45.00 | Port to Port |
| Fiber Fusion Splicer | $25.00 | In-Use |
| OTDR Fiber Tester | $40.00 | In-Use |
Traffic Control Labor Pricing
| PRICING SHEET |
| ITS Installation, Repair and Replacement Services |
OFFEROR: CS Construction, Inc.
Traffic Control Labor Pricing (Sub-Contractor)
Instructions: Traffic Control Labor Pricing (Sub-Contractor): The Contractor shall provide a Cost-Plus-Fixed Percentage for any Traffic Control for Subcontractor classifications that may be applicable to the service being offered.The Traffic Control for Subcontractor Classifications listed below will be used for evaluation purposes. The Contractor must use additional lines to fill in any other classifications that are being offered. Below indicate fixed percentage as required in paragraph 4.13.4 in the Specifications.
| Traffic Control (Sub-Contractor) Classifications | Cost-Plus-Fixed Percentage | Notes |
| Uniformed Officer | 15% | |
| Traffic Control Lead | 15% | |
| Laborer | 15% | |
| Traffic Control Device Rental | 15% | |
| Traffic Control Plans | 15% |
Traffic Control Materials
| PRICING SHEET |
| ITS Installation, Repair and Replacement Services |
OFFEROR: CS Construction, Inc.
Traffic Control Materials
Instructions: Traffic Control Materials (Contractor owned/supplied): The Contractor shall provide a daily rate for any Traffic Control Materials for Contractor Owned/supplied classifications that may be applicable to the service being offered.The Traffic Control for Contractor Owned/supplied materials listed below will be used for evaluation purposes. The Contractor must use additional lines to fill in any other classifications that are being offered. Below indicate fixed percentage as required in paragraph 4.13.7 in the Specifications.
| Traffic Control Materials (Contractor owned/supplied) Classifications | Daily Rate | Notes |
| Variable Message Signs | N/A | Do not own |
| Arrow Boards | $60.00 | |
| Type I, Vertical Panel | $1.00 | |
| Type II, Vertical Panel, Tubular Marker Barricade | $1.00 | |
| Type III, High Level Flag Trees Barricade | N/A | Do not own |
| Rigid Portable Sign Stands | $1.00 | |
| Spring Portable Sign Stands | $1.00 | |
| Type A Warning Lights | $0.50 | |
| Type C Warning Lights | $0.50 | |
| Truck Mounted Attenuator | $500.00 | Without Driver |
| Temporary Sign Less Than 10 SQ.FT. | $1.00 | |
| Temporary Sign 10 SQFT or More | $1.00 |
Subcontractor Work Pricing
| PRICING SHEET |
| ITS Installation, Repair and Replacement Services |
OFFEROR: CS Construction, Inc.
Subcontractor Work Pricing
Instructions: Subcontractor Work Pricing: The Contractor shall provide a Cost-Plus-Fixed Percentage for any Subcontractor work classification that may be applicable to the service being offered.The Subcontractor Classifications listed below will be used for evaluation purposes. The Contractor must use additional lines to fill in any other classifications that are being offered. Below indicate fixed percentage as required in paragraph 4.30 in the Specifications.
| Subcontractor Classifications | Cost-Plus-Fixed Percentage (%) | Notes |
| Equipment Operator | 15% | |
| Labor Services | 15% | |
| Equipment materials | 15% | |
| Drilling Subcontractor | 15% | |
| Horizontal Directional Drilling Subcontractor | 15% | |
| Hydrovac Subcontractor | 15% | |
| Crane (35TN to 110TN) | 15% |