This is a Solicitation Information Sheet issued by the University of Connecticut for an Open Invitation to Bid (ITB) for the North Campus Painting project located at 82 North Eagleville Road, Storrs, Connecticut. The project entails painting student rooms and hallways in North Campus, requiring surface preparation, patching, installation of surfacing materials following ceiling plaster abatement, application of one primer coat and two finish coats to each student room. The ITB was released on February 11, 2026, with a pre-bid conference scheduled for February 18, 2026 at 10:00 AM at the Bid Room, Procurement Services, 3 Discovery Drive, Storrs, Connecticut. The deadline for Requests for Information is February 25, 2026 at 2:00 PM, with bids due on March 10, 2026 at 2:00 PM, followed by a virtual bid opening at 2:15 PM via Microsoft Teams. A scope review meeting with the lowest qualified bidder is scheduled for March 12, 2026 at 2:00 PM. The anticipated contract issuance and Notice to Proceed is April 30, 2026, with construction planned to start May 31, 2026 and substantial completion targeted for July 31, 2026.
Bidders must submit cost proposals using the University's prescribed form and provide documentation demonstrating previous relevant experience on comparable interior painting projects with a recommended construction value of $350,000 completed within the past ten years, along with resumes for proposed key personnel including project superintendent and project manager. Bid security is required if the total bid amount exceeds $50,000, in the form of a bid bond, certified check, or letter of credit equal to ten percent of the bid amount (or twenty-five percent for bids exceeding $100,000). The project is subject to a $1 million cap, with liquidated damages assessed at $500 per calendar day for failure to achieve substantial completion on schedule. Bidders must demonstrate bonding capacity equal to the total bid amount and financial ability to complete a minimum $550,000 construction project. The contract includes a ten percent self-performance requirement and spending allocation goals requiring thirty percent of the contract price be awarded to Connecticut-certified Small Business Enterprises (SBEs) and ten percent to Minority Business Enterprises (MBEs). Connecticut prevailing wage requirements apply if the total contract value is $100,000 or more. The University encourages participation by SBE, MBE, Woman-Owned (WBE), and disability-owned (DisBE) businesses certified by Connecticut's Department of Administrative Services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CPFP Construction GC/Trade Open ITB, July 2025 Page 1 of 5
SOLICITATION INFORMATION SHEET
CONSTRUCTION - GENERAL CONTRACTOR/TRADE CONTRACTOR
OPEN INVITATION TO BID
The University of Connecticut is accepting sealed Bids for:
ITB RELEASE DATE: 2/11/2026
PROJECT NUMBER: CP012926
PROJECT NAME: North Campus Painting
PROJECT LOCATION: 82 North Eagleville Road, Storrs, CT 06269
PROCUREMENT AGENT: Chris Peters, chris.peters@uconn.edu, 860-486-6324
INTENT OF THIS SOLICITATION: The purpose of this Open Invitation to Bid (“ITB”) is to solicit bids for the North Campus Painting project.
LOCATION OF THIS SOLICITATION: Submit a Bid for this solicitation through the HuskyBuy Portal:
https://bids.sciquest.com/apps/Router/PublicEvent?CustomerOrg=UConnFullSuite.
SBE/MBE PARTICIPATION: The University of Connecticut is committed to providing a professionally inclusive environment within which small and minority businesses are encouraged to participate in the procurement experience. As such, we encourage participation by Small (SBE) businesses, Minority-Owned (MBE) businesses, Woman-Owned (WBE) businesses, and businesses owned by persons with a disability (DisBE), certified as such by the Connecticut’s Department of Administrative Services Supplier Diversity Division. For further information, visit: https://portal.ct.gov/DAS/Services/Licensing-Certification- Permitting-and-Codes/Small-Minority-Business-Center. To learn about the University of Connecticut’s Supplier Diversity Program, visit: https://supplierdiversity.ubs.uconn.edu. Additionally, the University encourages Connecticut-based businesses to participate in this public solicitation process.
CRITICAL DATES:
Pre-Bid Conference Date and Time 2/18/2026 10:00 AM Pre-Bid Conference Location Bid Room, Procurement Services, 3 Discovery Drive, Storrs, CT 06269 Q&A (RFI) Due Date and Time 2/25/2026 2:00 PM mailto:chris.peters@uconn.edu https://bids.sciquest.com/apps/Router/PublicEvent?CustomerOrg=UConnFullSuite https://portal.ct.gov/DAS/Services/Licensing-Certification-Permitting-and-Codes/Small-Minority-Business-Center https://portal.ct.gov/DAS/Services/Licensing-Certification-Permitting-and-Codes/Small-Minority-Business-Center https://supplierdiversity.ubs.uconn.edu/
CPFP Construction GC/Trade Open ITB, July 2025 Page 2 of 5
Bid Due Date and Time Bid Opening
3/10/2026 2:00 PM
Microsoft Teams Link 2:15 PM
Scope Review Meeting (with lowest qualified Bidder)
3/12/2026 2:00 PM
PRE-BID CONFERENCE: During the Pre-Bid Conference, the ITB and Scope of Work will be discussed. There also will be an opportunity to view existing conditions (if applicable). The Pre-Bid Conference is not mandatory, however, interested Bidders are strongly encouraged to attend.
There are limited short-term and PayByPhone parking spaces around the University Business Services building. The North Parking Garage is recommended to all vendors as parking on campus is at your own risk. The North Garage parking is paid via online app (PaybyPhone or Flowbird) or at a kiosk and is required when parking vehicle and not when exiting the garage.
REQUEST FOR INFORMATION QUESTIONS: All Requests for Information (“RFI”) questions are to be posted under the Q&A Board Tab in the HuskyBuy sourcing event for this Solicitation. No phone calls or RFI questions emailed directly to the Procurement Agent will be accepted.
CLARIFICATIONS, ADDENDA, and INTERPRETATIONS: Bidders shall promptly notify the University of any ambiguity, inconsistency, or error which they may discover upon examination of the plans, specifications, and contract documents.
Any and all interpretations of the drawings, specifications, RFI Responses, contract documents, and supplemental instructions, will be in the form of a clarification/addendum, and posted as part of the HuskyBuy sourcing event. Failure of a Bidder to receive any such clarification/addendum or interpretation shall not release a Bidder from the obligations under its Bid as submitted.
BID OPENING: Bid openings are conducted via virtual conference at 2:15 p.m. on the due date. It is the responsibility of the Bidder to request access to the bid opening prior to the bid due date and time via email to the Procurement Agent listed for this solicitation.
CONSIDERATION OF BIDS: Cost Proposals received in response to this ITB are opened during a public opening. To ensure the integrity of the bidding process, the Total Bid Amount and prices for any Alternates are read at the bid opening. After the bid opening and before the contract award, the lowest responsible Bidder is determined by adding together the Total Bid Amount plus any Alternates (additive or deductive) accepted by the University. The University reserves the right to elect to implement some, all, or none of the Alternates (if applicable) set forth in this Bid, as may be in the best interest of the University. Prices for Alternates are not negotiable since they are a component in determining the lowest responsible Bidder.
The lowest responsible Bidder shall also demonstrate, to the satisfaction of the University, that they possess the proven financial ability, managerial ability, technical ability, and the integrity, necessary to perform the Scope of Work faithfully and efficiently for this Project, without conflict of interest. Bids shall be evaluated utilizing the objective technical criteria listed within the ITB, as well as any additional information obtained from persons or other sources identified in the Bid.
https://teams.microsoft.com/meet/25461387140073?p=hVWPcuLXgqVtpO950t
CPFP Construction GC/Trade Open ITB, July 2025 Page 3 of 5
THIS SOLICITATION IS FOR PROJECTS LESS THAN $1M. BIDS OVER $1M (INCLUDING ALL ALTERNATES)
CANNOT BE CONSIDERED BY THE UNIVERSITY.
PROJECT SCHEDULE/DURATION:
• Anticipated Contract Issuance/Notice to Proceed: April 30, 2026
• Construction is planned to start: May 31, 2026
• Substantial Completion: July 31, 2026
LIQUIDATED DAMAGES: Liquidated Damages of Five Hundred Dollars and 00/100 ($500.00) per calendar day shall be assessed if the Contractor fails to achieve Substantial Completion or causes delay to the Substantial Completion of any portion of the work within the Contract Time.
WAGE RATES: Wages are required for this Project if the total cost of all work to be performed by the Contractor and Subcontractors is $100,000.00 or more and subject to Connecticut General Statutes §31- 53, §31-54, and §31-55: https://www.cga.ct.gov/current/pub/chap_557.htm#sec_31-53.
PROJECT DESCRIPTION/SCOPE OF WORK: This project entails the painting of student rooms and hallways in North Campus. The painting will require patching and installation of surfacing materials following ceiling plaster abatement. Each student room entails preparation of painting surfaces to receive paint and application of one primer coat and two coats of finish paint.
COST PROPOSAL: Submit a Cost Proposal utilizing the Form provided. No substitution of the Form is permitted.
FINANCIAL ABILITY: The lowest responsible Bidder will be required to submit their Company’s financial documents within 5 business days of notification from the University. The financial documents must demonstrate the Company’s ability to complete a construction project with a minimum value of at least $550,000. See the Financial Ability Prequalification Requirements Document for further information.
Failure of the lowest responsible Bidder to submit financial documents during the specified timeframe or failure to pass the University’s financial requirements will result in a non-responsive Bid.
Note: Financial documents are not required to be submitted with your Company’s bid submission.
QUALIFICATIONS OF BIDDER: In addition to submitting a Cost Proposal, all Bidders must provide information/documentation with their submission that demonstrates the following:
- PREVIOUS RELEVANT EXPERIENCE: Describe the overall qualifications of the Bidder, including background in this field and the services that it provides. Utilize the Previous Relevant Experience Form, Const-Open ITB provided with this ITB.
a. It is recommended that the Proposer provide three (3) examples of projects that are in progress or completed within the past ten (10) years, comparable in size, scope, and similar environment to this Project, with an emphasis on interior painting.
b. It is recommended that the examples have a construction value of $350,000.
c. A detailed description of the work performed and how it relates to the scope of work outlined in the ITB shall be included.
d. Projects with any information on the Form stated as “confidential” may not be considered.
https://www.cga.ct.gov/current/pub/chap_557.htm#sec_31-53
CPFP Construction GC/Trade Open ITB, July 2025 Page 4 of 5
- PROPOSED TEAM QUALIFICATIONS: The Bidder must demonstrate the ability to staff the project with high quality, experienced personnel. Describe the qualifications and responsibilities of the key personnel who will be assigned to the Project including their experience on similar assignments and their specific responsibilities for the proposed Project. Utilize the Resume for Proposed Key Personnel, Const-Open ITB provided with this RFQ.
a. It is recommended that the Proposer provide Resumes for the following positions: Project
Superintendent and Project Manager. Only provide Resumes for the key project team; do not include Resumes for personnel not assigned to the team.
MISCELLANEOUS REQUIRED DOCUMENTS: The Bid shall include the following documents:
1. SEEC Form 10: Review the SEEC Form 10: Notice to Executive Branch State Contractors and Prospective
State Contractors of Campaign Contribution and Solicitation Limitations (acknowledgment of receipt of the explanation of prohibitions) and upload the executed Form where applicable. The Form can be found at: https://seec.ct.gov/Portal/data/forms/ContrForms/seec_form_10_final.pdf.
2. Bidder Contract Compliance Monitoring Report: Review the Commission on Human Rights and Opportunities Bidder Contract Compliance Regulations Notification to Bidders and upload the completed Report where applicable. The Form can be found at: https://portal.ct.gov/- /media/chro/cc-documents/notificationtobidders.
3. Supplier Diversity Certificate: If certified, provide your Company’s current Supplier Diversity Certificate issued by the Connecticut Department of Administrative Services.
4. Bid Security: A bid security in the form of a bid bond, certified check or a treasurer’s or cashier’s check issued by a responsible bank or trust company, payable to the University of Connecticut (reference the attached bid bond form) must accompany all bids if the Total Bid Amount is over $50,000.00. Bid bonds must be issued by a surety licensed in Connecticut and listed on the Department of Treasury’s Listing of Approved Sureties with an underwriting limitation of no less than the full amount of the bid.
The bid security shall be in the amount equal to TEN PERCENT (10%) of the amount of the bid. In lieu of a bid bond or certified check, a letter of credit that shall be in the amount of TEN PERCENT (10%) of the total bid amount for a bid valued less than $100,000 and in the amount of twenty-five percent (25%) of the bid amount for any bid value that exceeds $100,000 may be submitted
5. Bonding Capacity: Provide a letter from your bonding company or representative confirming bonding capacity and include if they have ever had to complete or finance work on your behalf. Bonding capacity shall be for, at a minimum, the Total Bid Amount submitted for this Project.
CONTRACT: A draft of the contract has been provided with the solicitation documents. The University reserves the right to modify the contract or waive any informality as it deems to be in the best interest of the University. By submitting a Bid, your Company accepts the contract and any modifications that the University deems necessary to it without exception. Bidders will be notified of any modifications to the contract made by the University. Any exceptions to the contract submitted by the Bidder will not be considered.
SELF-PERFORMANCE REQUIREMENT: If awarded this contract, the Contractor shall be required to perform not less than ten percent (10%) of the Total Contract Price with its own forces.
GOOD FAITH EFFORTS PLAN: The Spending Allocation Goal for this Project is that (1) not less than thirty percent (30%) of the Total Contract Price be awarded to subcontractors who are certified by the Connecticut Department of Administrative Services as “Small Business Enterprises” (“SBEs”) and (2) not less than ten percent (10%) of the Total Contract Price be awarded to subcontractors who are certified by the Connecticut Department of Administrative Services as “Minority Business Enterprises” (“MBEs”) (the https://seec.ct.gov/Portal/data/forms/ContrForms/seec_form_10_final.pdf https://portal.ct.gov/-/media/chro/cc-documents/notificationtobidderspdf.pdf?rev=63ae9bf7406c4ef8b686464466ab8493&hash=1A95FCD08D0688CFDB09A70B61F68C9A https://portal.ct.gov/-/media/chro/cc-documents/notificationtobidderspdf.pdf?rev=63ae9bf7406c4ef8b686464466ab8493&hash=1A95FCD08D0688CFDB09A70B61F68C9A
CPFP Construction GC/Trade Open ITB, July 2025 Page 5 of 5
10% Spending Allocation Goal for MBEs may be included in the 30% Spending Allocation Goal for SBEs).
If the Contractor is an S/MBE, then any self-performed work may be included in the Spending Allocation Goal, however, self-performing MBE’s must still demonstrate good faith efforts to employ other MBEs as subcontractors and supplier of materials. The Contractor is responsible for ensuring that they, and the S/MBEs they have selected, are eligible Connecticut-certified S/MBE contractors. Failure to make good faith efforts will be subject to enforcement that may lead to withholding of contract payments, disqualification from future bidding, and/or civil penalties and legal action by CHRO. For further information see: CHRO's Contract Compliance Program.
Listed below is a sample of suggested categories (if applicable) and possibilities for the breakout of the schedule of values for inclusion of S/MBE participation:
01 – General Conditions: temporary electric and wiring; cleaning
02 – Existing Conditions: demolition and salvage; abatement
03 – Concrete: sidewalks and flatwork
05 - Metals: metal stairs and railings; miscellaneous metals; decorative metal
06- Woods Plastics and Composites: rough carpentry and blocking
07 – Thermal and Moisture Protection: insulation; sealers and waterproofing
08 – Openings: door hardware
09 – Finishes: tile installation; acoustic ceilings; flooring installations; painting and coatings;
firestopping
10 – Specialties: signage
12 – Furnishings: window treatments
14 – Conveying Equipment: lifts
23 – HVAC (Heating, Ventilating, Air Conditioning): HVAC duct insulation
27 – Communications: low voltage cabling
28 – Electronic Safety & Security: fire alarm and security wiring
32 – Exterior Improvements: retaining walls; paving; fencing and gates; landscaping
44 – Pollution and Waste Control Equipment: trucking
End of Solicitation Information Sheet https://portal.ct.gov/chro/contract-compliance/contract-compliance/contract-compliance-forms-and-reports