Corrected Final - Design Specifications.pdf
PDF 2 MB Posted
- Attached to
- F-35 Jet Blast Deflectors Federal contract opportunity
- Solicitation number
- FA667524R0003
About this file
This document contains the project specifications and drawings for the F-35 Jet Blast Deflector (JBD) improvements at NAS Fort Worth JRB. The work includes demolishing existing F-16 jet blast deflectors and constructing new F-35 jet blast deflectors in accordance with the provided architectural and engineering specifications. The project is being solicited under Solicitation Number FA667524R0003. A pre-proposal conference and site visit will be held on 30 July 2024, and Requests for Information (RFIs) are due by 2 August 2024. The project will be awarded and administered by the Department of the Air Force Reserve Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ADDENDUM 1 - RFI and Coring Change R2.pdf | ||
| Solicitation Amendment FA667524R00030001 SF 30.pdf | ||
| ADDENDUM 1 - RFI and Coring Change.pdf | ||
| Solicitation - FA667524R0003.pdf | ||
| DOL Wage Determination 2015-5231 Rev 2023.pdf | ||
| Corrected Final - Drawings.pdf | ||
| Corrected Final - Design Narrative.pdf | ||
| RFI -RFC FORM.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAS FORT WORTH JRB
F-35 JET BLAST DEFLECTOR (JBD)
IMPROVEMENTS
Contract #FA664318D0010
Delivery Order/Call #:
FA667523F0012
PROJECT SPECIFICATIONS
LEO A DALY Project No. 092-10066-011
CORRECTED FINAL DESIGN
April 05, 2024
4-5-2024
PROJECT SPECIFICATIONS TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 LIST OF DRAWINGS
00 22 13.00 20 SUPPLEMENTARY INSTRUCTIONS TO OFFERORS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
01 32 01.00 10 PROJECT SCHEDULE
01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 11.51 PAINT REMOVAL FROM AIRFIELD PAVEMENTS
32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT
32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY
PAVEMENTS
32 17 23 PAVEMENT MARKINGS
DIVISION 34 – JET BLAST DEFLECTORS
34 73 19 JET BLAST BARRIER/DEFLECTOR FOR HIGH
TAXI/BREAKAWAY VELOCITIES
-- End of Project Table of Contents --
F-35 Jet Blast Deflector (JBD)improvements, NAS Ft Worth JRB
April 05-2024
Document 00 01 15 Page 1
CUI
DOCUMENT 00 01 15
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause
"DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING NO. TITLE
GI001 COVER
GI002 SITE LOCATION MAP WITH HAUL ROUTE & VICINITY MAP
VS101 OVERALL SITE SURVEY
CD101 DEMOLITION PLAN NORTH BLAST DEFLECTOR
CD102 DEMOLITION PLAN EAST BLAST DEFLECTOR
CS101 SITE LAYOUT NORTH BLAST DEFLECTOR
CS102 SITE LAYOUT EAST BLAST DEFLECTOR
CG101 GRADING AND JOINTING NORTH BLAST DEFLECTOR
CG102 GRADING AND JOINTING EAST BLAST DEFLECTOR
CI101 PHASING
M101 BLAST DEFLECTOR DETAILS
C501 DETAILS
C502 DETAILS
C503 DETAILS
April 05-2024
Document 00 01 15 Page 2
1.3 SUPPLEMENTARY DRAWINGS
These supplementary drawings may not be a part of the contract but are included with the drawings for information.
1.3.1 Boring Logs
The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made. Subsurface data, not specified or indicated, have been obtained by the Government at this station. The data are available for examination by prospective bidders in the office of the Contracting Officer.
1.3.2 Subsurface Data
Subsurface data, not specified or indicated, have been obtained by the
Government at the station. The data are available for examination by prospective bidders at the office of the Contracting Officer.
-- End of Document --
Document 00 22 13.00 20 Page 1
DOCUMENT 00 22 13.00 20
SUPPLEMENTARY INSTRUCTIONS TO OFFERORS
1.1 CONTRACT LINE ITEMS
The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.
Provide the Contract Line Item (CLIN) lump sum price for the following items:
CLIN 0001 – F-35 Jet Blast Deflector (JBD)improvements Base Price
1. Remove Apron Edge Marking from Doolittle Gate south to its termination point just south of Burke Avenue as shown on Sheet CD101.
The total price for CLIN 0001 shall include all materials, labor, taxes, contractor's overhead and profit, and any other incidentals for the completion of the item.
CLIN 0002 – F-35 Jet Blast Deflector (JBD) improvements Base Price
1. Do not remove Existing Apron under the new JBD along the east side. See
Sheet CS-102 for the extent and limits of existing apron to remain.
The total cost deduction price for CLIN 0002 shall include all materials, labor, taxes, contractor's overhead and profit, and any other incidentals for the completion of the item.
1.2 GENERAL BID NOTES
a. The award will be made on the total sum of Contract Line Items unit prices and extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an
Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.
1.3 CONTRACT LINE ITEM AWARD
Award of CLIN 0001 or CLIN 0002 will be at the discretion of the Government and will be determined within 60 days from the receipt of bids.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Document 00 22 13.00 20 Page 2
-- End of Document --
APRIL 05, 2024
Section 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government
SD-01 Preconstruction Submittals
Schedule; G
Dig Permits; G
Personnel Vetting Documents; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes all work indicated on the Contract Documents including the drawings and specifications known as, F-35 Jet Blast Deflector
(JBD)improvements.
1.2.2 Location
The work is located at the JRB Ft. Worth, Texas. The exact location is as shown on the Contract Documents.
1.3 WORK RESCHEDULING
Allow for a maximum of 30 calendar days in the construction schedule where construction activity is prohibited due to flight operations. Where other construction activities are permitted impose a further allowance for 30 calendar days in the schedule, of excavation and subsurface activity abeyance. The government will provide 24-hour notification each time the restrictions are invoked.
Normal duty hours for work are from 6:00 a.m. to 6:00 p.m., Monday through
Friday. Requests for additional work requires written approval from the
Contracting Officer 7 days in advance of the proposed work period.
1.4 OCCUPANCY OF PREMISES
Adjacent buildings will be occupied during performance of work under this
Contract.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of existing apron, and location of staging area.
Section 01 11 00 Page 2
At no time will access be blocked to Building 1643 or Building 1637.
Contractor is advised that other contractors may be working in the same area at the time of this project.
1.5 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. The Contractor shall provide temporary construction facilities for the
Contractor as well as other small contractors working in the same area.
This includes material storage/staging areas, contractor trailer locations, and parking for construction personnel. Company (identified) vehicle parking will be allowed in the construction free zone when installed. Personally owned vehicle parking will not be allowed in the construction free zone but will use the main parking lot B1654 or
B1650. Multiple Contractors will be responsible for other phases of the project. The Contractor shall be required to coordinate with the other contractors and the base staff for use of the construction areas.
1.6 ON-SITE PERMITS
1.6.1 Utility Outage Requests and Utility Connection Requests
Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, schedule outside the regular working hours or on weekends, as approved by the
Contracting Officer. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.
Submit requests for utility outages and connections in writing to the
Contracting Officer for approval at least 14 calendar days in advance of the time required. In each request, state the system involved, area involved, approximate duration of outage, and the nature of work involved.
1.6.2 Excavation Permits
ACTIVITY SUBMISSION DATE SUBMISSION FORM
Dig Permits 30 calendar days prior to work
To be supplied by
Contracting
Officer
Post permits at a conspicuous location in the construction area.
Burning of trash or rubbish is not permitted.
Section 01 11 00 Page 3
1.7 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation and comply with
Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar
(GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered.
Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.7.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
1.8 SALVAGE MATERIAL AND EQUIPMENT
No items shall be salvaged for this project.
-- End of Section --
Section 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
1.1 SUBMITTALS
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Contractor Regulations; G, RO
Transportation of Personnel, Materials, and Equipment; G, RO
List of Contact Personnel; G, RO
Personnel List; G, RO
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. The temporary fence must be ready as approved by Contracting Officer before work is started on the flight line which would interfere with normal operation.
b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
c. The flight line will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
d. Permission to interrupt any Activity roads or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
e. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials must be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to
Section 01 14 00 Page 2
CUI
do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Additional Personnel Requirements
1.3.1.2.1 General Construction
General construction of the secure area must be performed by U.S. firms using U.S. citizens. General construction includes all construction activities.
1.3.1.3 Installation Access
Obtain access to Navy installations through participation in the Defense
Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy
Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html. No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.3.1.3.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html. Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF
1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html.
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
https://www.cnic.navy.mil/om/dbids.html
Section 01 14 00 Page 3
1.3.1.3.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification. The
Government is the final authority.
1.3.1.3.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the
Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting
Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.3.1.3.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.3.1.4 NCACS Identification Badges and Installation Access
Application for and use of badges will be as directed. Obtain access to the installation by participating in the Navy Commercial Access Control System
(NCACS), or by obtaining passes each day from the Base Pass and
Identification Office. Costs for obtaining passes through the NCACS are the responsibility of the Contractor. One-day passes, issued through the Base
Pass and Identification Office, will be furnished without charge. Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment
Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.
a. NCACS Program: NCACS is a voluntary program in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to one year, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. The
Government performs background screening and credentialing. Throughout the year the Contractor employee must continue to meet background http://www.uscis.gov/portal/site/uscis
Section 01 14 00 Page 4
CUI
screening standards. Periodic background screenings are conducted to verify continued NCACS participation and installation access privileges. Under the NCACS program, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an elevation of Force Protection Conditions (FPCON).
Information on costs and requirements to participate and enroll in
NCACS is available at http://www.rapidgate.com or by calling 1-877-727-
4342. Contractors should be aware that the costs incurred to obtain
NCACS credentials, or costs related to any means of access to a Navy
Installation, are not reimbursable. Any time invested, or price(s) paid, for obtaining NCACS credentials will not be compensated in any way or approved as a direct cost of any contract with the Department of the Navy.
b. One-Day Passes: Participation in the NCACS is not mandatory, and if the Contractor chooses to not participate, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The
Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the NCACS.
1.3.1.5 No Smoking Policy
Smoking is prohibited on the construction site.
1.3.2 Working Hours
Regular working hours must consist of a 10 hour period approved by the
Contracting Officer, between 8:00 a.m. and 5:00 p.m., Monday through Friday, and 7 a.m. to 11 p.m. on Saturday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the
Contracting Officer may approve work outside regular hours.
1.3.4 Occupied and Existing Buildings
The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the
Not Used http://www.rapidgate.com/
Section 01 20 00.00 20 Page 1
SECTION 01 20 00.00 20
PRICE AND PAYMENT PROCEDURES
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2016) Construction Equipment Ownership and
Operating Expense Schedule
1.2 SUBMITTALS
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Schedule of Prices; G, RO
1.3 SCHEDULE OF PRICES
1.3.1 Data Required
Within 30 calendar days of notice of award, prepare and deliver to the
Contracting Officer a Schedule of Prices as directed by the Contracting
Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized, and totals provided for each construction category.
1.3.2 Schedule Instructions
Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer. Identify the cost for site work and include incidental work.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification
Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP 1110-1-8.
Section 01 20 00.00 20 Page 2
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract
Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR
52.232-5 Payments Under Fixed-Price Construction Contracts. The requests for payment shall include the documents listed below.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the
Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 shall include certification by
Contractor and Quality Control (QC) Manager.
b. The Estimate for Voucher/ Contract Performance Statement on NAVFAC Form
4330/54 furnished by the Government, showing in detail: the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use NAVFAC
Form 43300/54 on NAVFAC contracts when a Monthly Estimate for Voucher is required.
c. Updated Project Schedule and reports required by the contract.
d. Contractor Safety Self Evaluation Checklist.
e. Other supporting documents as requested.
f. Updated copy of submittal register.
g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
1.5.2 Final Invoice
a. A final invoice shall be accompanied by the certification required by
DFARS 252.247.7023 Transportation of Supplies by Sea, and the
Contractor's Final Release. If the Contractor is incorporated, the
Final Release shall contain the corporate seal. An officer of the corporation shall sign, and the corporate secretary shall certify the
Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's
Final Release Form and required certification of Transportation of
Supplies by Sea must be provided directly to the respective Contracting
Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of
Transportation of Supplies by Sea has been confirmed by the Contracting
Officer, the Contractor shall then submit final invoice and attach a copy of the Final Release Form and required certification of
Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
Section 01 20 00.00 20 Page 3
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting
Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR
32.503-6 Suspension or Reduction of Payments:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current as stated in
Contract Clause "FAC 5252.236-9310, Record Drawings."
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment shall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this contract.
Requests for progress payment consideration for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price
Construction Contracts have been met.
d. Materials are adequately insured and protected from theft and exposure.
Section 01 20 00.00 20 Page 4
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation shall be stored either in Hawaii, Guam, Puerto Rico, or the Continental
United States. Other locations are subject to written approval by the
Section 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
EM 385-1-1 (2014) Safety and Health Requirements Manual will review the submittal for the Government
View Location Map
Progress and Completion Pictures
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in
PDF file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc
(CD) or data versatile disc (DVD), cumulative of all photos to date.
Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Photographs provided are for unrestricted use by the Government.
Section 01 30 00 Page 2
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
1.6 SUPERVISION
1.6.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years’ experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For projects where the superintendent is permitted to also serve as the
Quality Control (QC) Manager as established in Section 01 45 00.00 20
QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.6.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the jobsite at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.6.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion. Furthermore, the
Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
file:///P:/000/SPECSINTACT/Jobs/09210066006PKG1/prntdata/Word/01%2045%2000.00%2020.docx
Section 01 30 00 Page 3
1.7 PRECONSTRUCTION MEETING
Immediately after award and/or upon completion of design and design acceptance by the government, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the
Preconstruction Meeting. The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. The contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.7.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site
Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.8 PARTNERING
1.8.1 Team-Led (Informal) Partnering
a. The Contracting Officer will coordinate the initial Team-Led (Informal)
Partnering Session with key personnel of the project team, including
Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project
Manager.
b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the
Contractor.
c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer.
d. The Partners will determine the frequency of the follow-on sessions.
e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.
1.9 MOBILIZATION
Contractor shall mobilize to the jobsite within 60 calendar days of contract award. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.
Section 01 30 00 Page 4
Section 01 31 23.13 20 Page 1
SECTION 01 31 23.13 20
ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
1.1 CONTRACT ADMINISTRATION
Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic
Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable, non-functional, or specifically requested in addition to electronic submission. Contact the Contracting Officer's Representative (COR) regarding availability of eCMS training and reference materials.
1.2 USER PRIVILEGES
The Contractor will be provided access to eCMS. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.
1.3 SUBMITTALS
List of Contractor's Personnel; G, RO
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
The eCMS requires a web-browser and Internet connection. Obtain from an approved vendor an External Certification Authority (ECA), Primary Key
Infrastructure (PKI) certificate, or other similar digital identification to support two-factor authentication and access to eCMS. Provide and maintain computer hardware and software for the eCMS access throughout the duration of the contract for all Contractor-designated users. Provide connectivity, speed, bandwidth, and access to the Internet to ensure adequate functionality. Neither upgrading of the Contractor's computer system nor delays associated from the usage of the eCMS will be justification or grounds for a time extension or cost adjustment to the Contract.
1.4.2 Contractor Personnel List
Section 01 31 23.13 20 Page 2
CUI
Within 20 calendar days of contract award, provide to the Contracting
Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of technical submittals and documents and will require access to the eCMS. Project personnel roles to be filled in the eCMS include the Contractor's Project Manager, Superintendent, Quality Control (QC) Manager, and Site Safety and Health
Officer (SSHO). Personnel must be capable of electronic document management. Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users. Provide the following information:
First Name
Last Name
E-mail Address
Office Address
Project Role (e.g., Project Manager, QC Manager, Superintendent)
1.4.3 Field Administration
Within 30 days of Contract Award, provide a tablet computer with a Common
Access Card (CAC) reader at the job site for Government use only. The tablet computer must have a web-browser, built-in camera, and cellular data connectivity. Provide tablet computer with a rugged case suitable for use in a construction environment. The tablet computer must be fully charged and made available at all times for Government use to facilitate the input of construction data at the job site. The tablet will be given back to the contractor prior to leaving the jobsite for charging, maintaining and securing. After completion of the work, reset the tablet computer to factory default settings. The tablet computer remains the property of the
Contractor and must be removed from the site. There are restrictions on the use of WIFI on military bases. Cellular data connectivity and availability, and use of WIFI requires coordination with and approval by the Contracting
Officer.
1.5 SECURITY CLASSIFICATION
In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.
The eCMS and tablet computer must only be used for the transaction of unclassified information associated with construction projects. In conformance with the Freedom of Information Act (FOIA), Department of
Defense Manual 5200.01-V4: DoD Information Security Program: Controlled
Unclassified Information (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U -
UNCLASSIFIED" (U) or "CUI - CONTROLLED UNCLASSIFIED INFORMATION (CUI)".
1.6 ECMS UTILIZATION
Establish, maintain, and update data and documentation in the eCMS throughout the duration of the contract.
Personally Identifiable Information (PII) transmittal is not permitted in the eCMS.
Section 01 31 23.13 20 Page 3
1.6.1 Information Security Classification/Identification
The eCMS must be used for the transmittal of the following documents. This requirement supersedes conflicting requirements in other sections, however, submittal review times in Section 01 33 00 SUBMITTAL PROCEDURES remain applicable. Table 1 - Project Documentation Types provides the appropriate
U and CUI designations for various types of project documents. Construction documents requiring CUI status must be marked accordingly. Apply the appropriate markings before any document is uploaded into eCMS. Markings are not required on U documents.
Table 1 also identifies which eCMS application is to be used in the transmittal of data (these are subject to change based on the latest software configuration). If a designated application is not functional within 4 hours of initial attempt, defer to the Submittal application and submit the required data as an uploaded portable document (e.g., PDF), word processor, spreadsheet, drawing, or other appropriate format. Hard copy or e-mail submission of these items is acceptable only if eCMS is documented to be not available or not functional. After uploading documents to the
Submittal application, transmit the submittals and attachments to the COR via the Transmittal application. For Submittals, select the following:
Preparation by = Contractor personnel assigned to prepare the submittal
Approval by = Contracting Officer Representative (COR)
Returned by = Design Lead/Manager
Forwarded to = Contractor project manager
Table 1 - Project Documentation Types
SUBJECT/NAME CLASS REMARKS ECMS APPLICATION
As-Built Drawings U Locations of sensitive areas must be labeled as either "Controlled
Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site
Security Manager
Submittals and
Transmittals
Construction
Permits
U Refer to rules of the issuing activity, state, or jurisdiction
Submittals and
Transmittals
Construction
Schedules
(Activities and
Milestones)
U After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and
Scheduling App
Construction
Schedules (3-Week
Lookahead)
U Import the schedule file into the scheduling application, and select
"Approve" to establish a new schedule baseline
Scheduling App file:///P:/000/SPECSINTACT/Jobs/09210066006PKG1/prntdata/Word/01%2033%2000.docx
Section 01 31 23.13 20 Page 4
CUI
SUBJECT/NAME CLASS REMARKS ECMS APPLICATION
Daily Production
Reports
CUI Provide weather conditions, crew size, man-hours, equipment, and materials information
Daily Report
Daily Quality
Control (QC)
Reports
CUI Provide QC Phase, Definable
Features of Work Identify visitors
Daily Report
Environmental
Notice of Violation
(NOV), Corrective
Action Plan
U Refer to rules of the issuing activity, state, or jurisdiction
Submittals and
Transmittals
Environmental
Protection Plan
(EPP)
CUI Submittals and
Transmittals
Invoice (Supporting
Documentation)
CUI Applies to supporting documentation only. Invoices are submitted in Wide-Area Workflow
(WAWF)
Submittals and
Transmittals
Jobsite
Documentation, Bulletin Board, Labor Laws, SDS
U Submittals and
Transmittals
Meeting Minutes CUI Meeting Minutes
Operations &
Maintenance Support
Information
(OMSI/eOMSI), Facility Data
Worksheet
U 1. Locations of sensitive areas must be labeled as either
"Controlled Area" or "Restricted
Area" and may be shown on unclassified documents with the approval from Site Security
Manager2. Design reviews will be performed in existing "Dr Checks"
Submittals and
Transmittals
Photographs U Subject to base/installation restrictions
Submittals and
Transmittals
QCM Initial Phase
Checklists
CUI Checklists (Site
Management)
QCM Preparatory
Phase Checklists
CUI Checklists (Site
Management)
Section 01 31 23.13 20 Page 5
CUI
SUBJECT/NAME CLASS REMARKS ECMS APPLICATION
Quality Control
Plans
CUI Submittals and
Transmittals
QC Certifications U Submittals and
Transmittals
QC Punch List U Punch Lists
(Testing Logs)
Red-Zone Checklist U Checklists (Site
Management)
Rework Items List CUI Punch Lists
(Testing Logs)
Request for
Information (RFI)
Post-Award
CUI RFIs
Safety Plan CUI Daily Report
Safety - Activity
Hazard Analyses
(AHA)
CUI Daily Report
Safety - Mishap
Reports
CUI Daily Report
SCIF/SAPF
Accreditation
Support Documents
CUI Note: Some Construction Security plans may be classified as Secret.
Classified information must not be uploaded into eCMS. Refer to the
Site Security Manager, as applicable.
Submittals and
Transmittals
Shop Drawings U Locations of sensitive areas must be labeled as either "Controlled
Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site
Security Manager
Submittals and
Transmittals
Storm Water
Pollution
Prevention (Notice of Intent - Notice of Termination)
U Refer to rules of the issuing activity, state, or jurisdiction
Submittals and
Transmittals
Section 01 31 23.13 20 Page 6
CUI
SUBJECT/NAME CLASS REMARKS ECMS APPLICATION
Submittals and
Submittal Log
U Submittals and
Transmittals
Testing Plans, Logs, and Reports
CUI Submittals and
Transmittals
Quality Assurance
Reports
CUI Checklists
(Government initiated)
Non-Compliance
Notices
CUI Non-Compliance
Notices
(Government initiated)
Other Government-prepared documents
CUI GOV ONLY
All O there
Documents
CUI Refer to FOIA guidelines and contact the FOIA official to determine whether exemptions exist
As applicable
1.6.2 Markings on CUI documents
a. Only CUI documents being electronically uploaded into the eCMS (.docx, .xlsx, .pptx, .pdf, .jpg, .zip, and others as appropriate), and associated paper documents described in the paragraph CONTRACT
ADMINISTRATION require CUI markings as indicated in the subparagraphs below.
b. CUI documents that are originally created within the eCMS application using the web-based forms (RFIs, Daily Reports, and others as appropriate) will be automatically watermarked by the eCMS software, and these do not require additional markings.
c. CUI documents must be marked "UNCLASSIFIED//FOR OFFICIAL USE ONLY" at the bottom of the outside of the front cover (if there is one), the title page, the first page, and the outside of the back cover (if there is one).
d. CUI documents must be marked on the internal pages of the document as
"UNCLASSIFIED/FOR OFFICIAL USE ONLY"' at top and bottom.
e. Where Installations require digital photographs to be designated CUI, place the markings on the face of the photograph.
f. For visual documentation, other than photographs and audio documentation, mark with either visual or audio statements as appropriate at both the beginning and end of the file.
1.7 QUALITY ASSURANCE
Section 01 31 23.13 20 Page 7
CUI
Requested Government response dates on Transmittals and Submittals must be in accordance with the terms and conditions of the Contract. Requesting response dates earlier than the required review and response time, without concurrence by the Government COR, may be cause for rejection.
Incomplete submittals will be rejected without further review and must be resubmitted. Required Government response dates for resubmittals must reflect the date of resubmittal, not the original submittal date.
Not Used.
Not Used.
Section 01 32 01.00 10 Page 1
SECTION 01 32 01.00 10
PROJECT SCHEDULE
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in
Construction
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
Preliminary Project Schedule; G
Initial Project Schedule; G
Periodic Schedule Update; G
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Government Default Software
The Government intends to use Primavera P6.
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support
Section 01 32 01.00 10 Page 2
CUI
agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Primavera
If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.
2.1.2.2 Other Than Primavera
If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to
FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project
Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial, or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay
Section 01 32 01.00 10 Page 3
CUI
request amount from each payment period until such revisions to the project schedule have been made.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original
Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review, and acceptance of SD-01 Preconstruction Submittals
(individu…