Construction Manager-General Contractor (CM-GC) for the Weld County Justice Center.pdf
PDF 550 KB Posted
- Solicitation number
- B2600077
- Issued by
- Weld County, Colorado
About this file
Weld County Justice Center CM/GC RFP Summary
This is a Request for Proposal (RFP) issued by Weld County, Colorado for Construction Manager/General Contractor (CM/GC) services for the Weld County Justice Center project in Greeley, Colorado. The project encompasses construction of a new 6-story, approximately 282,000 square-foot Justice Center with 24 courtrooms and an adjacent 5-story parking structure of approximately 202,000 square feet. The Justice Center will feature five fully built-out levels and one conditioned, unfinished shell level for future build-out, organized into three distinct circulation zones (secure, restricted, and public) and including judges' chambers, courtrooms, jury assembly, detention areas, and associated support spaces. Parking Structure construction is anticipated to commence in November 2026, with Justice Center construction beginning in June 2027. The Letter of Interest with executed Bidder Non-Disclosure Agreement is due July 14, 2026, by 2:00 PM MT to bids@weld.gov. A mandatory Pre-Bid Conference is scheduled for July 16, 2026, with time and location provided upon receipt of the Letter of Interest and Non-Disclosure Agreement. Technical questions are due July 30, 2026, with responses posted August 4, 2026. Proposals are due August 18, 2026, by 10:00 AM MT via email (preferred) or hand delivery. Interviews are anticipated August 25, 2026, with a Notice of Award anticipated September 2, 2026, and contract execution anticipated September 16, 2026. The contract will be based on the AIA A133-2019 agreement with a two-phase structure: preconstruction services on a cost-reimbursement basis up to a fixed fee, followed by construction services under a Guaranteed Maximum Price (GMP) model.
The CM/GC must provide a lump sum or not-to-exceed preconstruction fee with staffing assumptions and reimbursable expenses, plus a proposed construction phase fee as a percentage of the Cost of the Work. Additionally, proposers must submit fees for general conditions, project insurance, bonding, and builders risk insurance as percentages of the Cost of the Work. Proposers are required to competitively select and secure a written commitment from a precast concrete trade partner prior to Notice of Award and identify other critical trade partners (structural steel, mechanical, electrical, plumbing) with commitments upon Notice of Award. RFP responses are limited to 80 pages maximum and will be evaluated on firm qualifications and experience (3.0 weighting factor), staff qualifications (2.0), location and workload capacity (1.0), safety and claims history (2.0), project approach (4.0), schedule (3.0), fee proposal (4.0), and cost model (1.0). Finalists will participate in interviews before the Board of County Commissioners, evaluated on work approach, team qualifications, preconstruction and cost control approach, schedule strategy, presentation quality, question and answer responses, and overall confidence in project delivery. Weld County provides preference to resident Weld County proposers and Colorado suppliers where proposals are competitive in price and quality. The County reserves the right to reject any or all proposals, waive informalities, award to multiple vendors, or award based on written responses alone without conducting interviews.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Weld County Finance Department Purchasing Division
1301 North 17th Avenue Greeley, Colorado 80631
Solicitation # B2600077 Page 1
Construction – Request for Proposal (RFP) Cover Sheet
Solicitation Number: B2600077
Title: Construction Manager/General Contractor (CM/GC) For the Weld
County Justice Center
Advertisement Date: July 2, 2026
Letter of Interest Due: July 14, 2026, by 2:00 PM MT
Letter of Interest Email: bids@weld.gov
Pre-Bid Conference: July 16, 2026, time provided upon receipt of Letter of Interest and
Bidder Non-Disclosure Agreement
Pre-Bid Location: Location provided upon receipt of Letter of Interest and Bidder Non-
Disclosure Agreement
Questions Due: July 30, 2026, by 2:00 pm
Questions Posted: August 4, 2026, by 2:00 pm
Questions email: bids@weld.gov
Bid Due Date: August 18, 2026, by 10:00 am, Purchasing’s Clock
Bid Delivery: Preferred email to bids@weld.gov or option to hand delivery to 1301
North 17th Avenue, Greeley, CO 80631
For additional information: bids@weld.gov
Documents Included in this Proposal Package
RFP Schedules Schedule A: Proposal Instructions Schedule B: Scope of Work Schedule C: Project Schedule Schedule D: RFP Response - Criteria Schedule E: Proposal Form Schedule F: Insurance & Bonds Schedule G: Weld County Contract
RFP Attachments Attachment A – Letter of Interest Attachment B – Bidder Non-Disclosure Agreement mailto:bids@weld.gov mailto:bids@weld.gov mailto:bids@weld.gov
Table of Contents Construction – Request for Proposal (RFP) Cover Sheet
Documents Included in this Proposal Package
RFP Schedules
RFP Attachments
Table of Contents
Schedule A - Proposal Instructions
Purpose/Background
Proposal Advertisement
Letter of Interest, Pre-Bid Conference, and Access to Project Drawings
Proposal Submission
Introductory Information
Cooperative Purchasing
Schedule B - Scope of Work
Project Overview
Method of Procurement
Delivery Method
Pricing Method
Specific Requirements and Responsibilities
Schedule C - Procurement Schedule
Schedule D – RFP Response Criteria
RFP Response Submittal
Response Format
Grading Criteria
Schedule E - Proposal Response Form
Proposal Submittal Instructions
Fees
Attestation
Schedule F – Insurance and Bonds
Insurance
Bonds
Insurance Mailing Information
Schedule G - Weld County Contract
Contractual Obligations
Weld County Standard Contract
Solicitation # B2600077 Page 3
Schedule A - Proposal Instructions
Purpose/Background The Board of County Commissioners of Weld County, Colorado, by and through its Purchasing Office (collectively referred to herein as, “Weld County”), wishes to purchase the following:
Construction Manager/General Contractor (CM/GC) for the Weld County Justice Center
A Mandatory pre-bid conference will be held on July 16, 2026. The time and location of the pre-bid conference will be provided to each Proposer that submits Attachment A (Letter of Interest) and an executed Attachment B (Bidder Non-Disclosure Agreement). Bidders must participate and record their presence at the pre-bid conference to be eligible to submit bids.
Bids will be received until: August 18, 2026 at 10:00 am (Weld County Purchasing Time Clock).
The submitted bids will be read over a Microsoft Teams Conference Call on August 18, 2026 at 2:00 pm. To join, call the phone number and enter the Conference ID provided below or you are invited to attend the bid opening in person at the Weld County Purchasing Conference Room, 1301 N. 17 th Avenue, Greeley, CO 80631.
Microsoft Teams By Phone
Join: TEAMS Meeting
Meeting ID: 224 757 927 401 358 Passcode: Bi2gE9EJ
+1 720-439-5261,,795954677#
United States, Denver Phone conference ID: 795 954 677#
Proposal Advertisement
You can find information concerning this request on the BidNet Direct website at https://www.bidnetdirect.com/ Weld County Government is a member of BidNet Direct. BidNet Direct is an on-line notification system which is being utilized by multiple non-profit and governmental entities. Participating entities post their Proposals, quotes, proposals, addendums, and awards on this one centralized system.
Letter of Interest, Pre-Bid Conference, and Access to Project Drawings The Weld County Justice Center is a combined judicial and detention facility. Because the project drawings contain security-sensitive content, the pre-bid conference logistics and project drawings are not publicly distributed with this RFP. To receive them, a firm must submit Attachment A (Letter of Interest) and an executed Attachment B (Bidder Non-Disclosure Agreement) together to bids@weld.gov by the deadline in Schedule C. Upon receipt of both, the County will provide the pre-bid conference time and location and release the Project Documents (Attachments C and D to this RFP).
A firm that has not submitted both documents by the Schedule C deadline will not be admitted to the pre-bid conference and will not be eligible to submit a Proposal. The Project Documents (Attachments C and D to this RFP) are to be used solely to prepare a Proposal for this solicitation and are subject to the confidentiality terms of Attachment B.
https://teams.microsoft.com/meet/224757927401358?p=ykzdJxwuT6v9HwsoYl https://www.bidnetdirect.com/
Solicitation # B2600077 Page 4
Proposal Submission
1. PREFERRED: email Proposals to bids@weld.gov If your Proposal exceeds 25MB please upload your Proposal to https://www.bidnetdirect.com. The maximum file size to upload to BidNet Direct is 500 MB. If vendor does not desire email submission, sealed Proposals will be received at the Office of the Weld County Purchasing in the Weld County Building located at 1301 North 17th Avenue, Greeley, CO 80631 by the Proposal due date and time.
2. PDF format is required. Emailed Proposals must include the following statement on the email:
“I hereby waive my right to a sealed Proposal”. An email confirmation will be sent when your Proposal has been received. Please call Purchasing at 970-400-4222 or 4223 with any questions.
Introductory Information
1. Proposals shall be typewritten or ink on forms prepared by the Weld County Purchasing Division. Each Proposal must give the full business address of Proposer and be signed by authorized person. Proposals by partnerships must furnish the full names of all partners and must be signed with the partnership name by one of the members of the partnership or by an authorized representative, followed by the signature and title of the person signing. Proposals by corporations must be signed with the legal name of the corporation, followed by the name of the state of the incorporation and by the signature and title of the president, secretary, or other person authorized to bind it in the matter. The name of each person signing shall also be typed or printed below the signature. A Proposal by a person who affixes to his signature the word "president," "secretary," "agent," or other title without disclosing his principal, may be held to be the Proposal of the individual signing. When requested by the Weld County Procurement Manager satisfactory evidence of the authority of the officer signing on behalf of a corporation shall be furnished. A power of attorney must accompany the signature of anyone not otherwise authorized to bind the Proposer. All corrections or erasures shall be initialed by the person signing the Proposal. All Proposers shall agree to comply with all of the conditions, requirements, specifications, and/or instructions of this Proposal as stated or implied herein. All designations and prices shall be fully and clearly set forth. All blank spaces in the Proposal forms shall be suitably filled in. Proposers are required to use the Proposal Forms which are included in this package and on the basis indicated in the Proposal Forms. The Proposal must be filled out completely, in detail, and signed by the Proposer.
2. Late or unsigned Proposals shall not be accepted or considered. It is the responsibility of the
Proposer to ensure that the Proposal arrives in the Weld County Purchasing Division on or prior to the time indicated in Section 1, entitled, "Notice to Proposers." Hard copy Proposals received prior to the time of opening will be kept unopened in a secure place. No responsibility will attach to the Weld County Procurement Manager for the premature opening of a Proposal not properly addressed and identified. Proposals may be withdrawn upon written request to and approval of the Weld County Procurement Manager; said request being received from the withdrawing Proposer prior to the time fixed for award. Negligence on the part of a Proposer in preparing the Proposal confers no right for the withdrawal of the Proposal after it has been awarded.
Proposers are expected to examine the conditions, specifications, and all instructions contained herein, failure to do so will be at the Proposers’ risk.
3. In accordance with Section 14-9(3) of the Weld County Home Rule Charter, Weld County will https://www.bidnetdirect.com/
Solicitation # B2600077 Page 5 give preference to resident Weld County Proposers in all cases where said Proposals are competitive in price and quality. It is also understood that Weld County will give preference to suppliers from the State of Colorado, in accordance with C.R.S. § 30-11-110 (when it is accepting Proposals for the purchase of any books, stationery, records, printing, lithographing or other supplies for any officer of Weld County). Weld County reserves the right to reject any and all Proposals, to waive any informality in the Proposals, to award the Proposal to multiple vendors, and to accept the Proposal that, in the opinion of the Board of County Commissioners, is to the best interests of Weld County. The Proposal(s) may be awarded to more than one vendor.
Cooperative Purchasing Weld County encourages cooperative purchasing in an effort to assist other agencies to reduce their cost of soliciting and to make better use of taxpayer dollars through volume purchasing. Vendor(s) may, at their discretion, agree to extend the prices and/or terms of the resulting award to other state or local government agencies, school districts, or political subdivisions in the event they would have a need for the same product/service. Usage by any entity shall not have a negative impact on Weld County in the current term or in any future terms.
Solicitation # B2600077 Page 6
Schedule B - Scope of Work
Project Overview
Weld County is moving forward with design and construction of a new Justice Center to serve the growing needs of its community. Through this RFP, Weld County is seeking proposals from qualified Construction Manager / General Contractor (CM/GC) firms to provide Preconstruction and Construction services for the Weld County Justice Center Project, located in Greeley, Colorado.
While final scope will be refined during design and preconstruction, for purposes of proposal evaluation and comparison, the County has established the following program baselines to generally describe potential scale, organization, and functional components of the Justice Center project. These baselines are provided solely for evaluation purposes and are subject to modification and refinement based on design evolution, stakeholder input, funding strategy, and direction from the Board of County Commissioners.
Weld County Justice Center This project encompasses the complete construction of the Weld County Justice Center and associated parking structure.
Current Program Baseline:
• Located at West Block / Block 66 in Greeley, CO
• 6-story, 24-courtroom Justice Center (approximately 282,000 SF) and an adjacent 5-story ~600-stall Parking Structure (approximately 202,000 SF)
• Levels 1, 2, 4, 5, and 6 (approximately 42,000 SF each) fully built out and finished; Level 3 (approximately 42,000 SF) delivered as a conditioned, unfinished shell with core/circulation extended for future courtroom build-out
• Justice Center will be organized into 3-distinct circulation zones (secure, restricted, and public), and will include, but not limited to, the following spaces:
o Judges' Chambers o Courtrooms o Jury Assembly o Clerk of Court o District Attorney o Probation o Justice Services o Court Administration o Sheriff / Court Security and Holding o Public Lobby o Vehicular Sallyport o BOH Service Yard
Anticipated Construction Commencement:
• Parking Structure – November 2026
• Justice Center – June 2027
Method of Procurement Best Value: Best Value refers to a project procurement method where price and other key factors, such as quality and expertise, are considered in the evaluation and selection process. Best Value is typically achieved through a two-step process using a Request for Qualifications (RFQ) and Request for Proposal (RFP) to evaluate proposers.
Solicitation # B2600077 Page 7
Delivery Method
Construction Manager/General Contractor (CM/GC): A Construction Manager/General Contractor (CM/GC) is a construction project delivery method in which the county enters into separate contracts with the designer and the builder, often at or about the same time. During design, the CM/GC advises the owner and designer on constructability, value engineering, cost estimating, schedule, sequencing, selection of components and materials, and other matters.
When the design is completed, the CM/GC using defined or negotiated fees becomes the builder or general contractor for the work and may use subcontractors and/or self-perform the work. The CM/GC does not become a Construction Manager; instead the county supplies construction management through its own staff or a consultant.
Pricing Method
Guaranteed Maximum Price (GMP): Guaranteed Maximum Price (GMP) (also known as not-to-exceed price) is a variance of the Cost-Plus pricing method where the contractor guarantees the county will pay no more than the maximum price established for the completion of the work. GMP fees may include but are not limited to the costs of work, management fees, and a contingency fee to cover risk. GMP for vertical construction contracts are typically executed in two (2) parts. The first contract is for preconstruction services and is usually a lump sum or hourly fee. The second contract is for actual construction based on the design, which establishes the GMP. GMP fees may include but are not limited to Design, Pre-Construction Services, General Conditions, specifications, Construction Management, Bonds, Contingency, and Insurance and Cost of Work.
GMP contracts are cost-type contracts (also known as an open book-contract).
Specific Requirements and Responsibilities
Scope of Preconstruction Services All preconstruction services will be provided on a cost-reimbursement basis up to the stated preconstruction fixed fee as defined in Schedule E.
The CM/GC shall provide professional Preconstruction Services during the design phase to support Weld County and the Design Team. The CM/GC shall be engaged during the Design Development phase for the Justice Center and the Construction Documents for the Parking Structure.
In general, Preconstruction Services are expected to include but not be limited to the following:
• Serve as a partner to the design team and provide preconstruction guidance.
• Secure production capacity and schedule availability with early trade partners, managing long lead procurement timelines in coordination with the design team.
• Competitively select and hold under written commitment a precast concrete trade partner prior to Notice of Award, such that the selected precast firm is able to begin meaningful work immediately and hold production timelines upon Notice of Award with no delay to the project schedule.
• Develop and update schedules, estimates, and action plans as required.
• Guide decisions regarding phasing of the project to optimize quality, schedule, and budget.
Solicitation # B2600077 Page 8
• Strategically approach the sub-contractor market with a focus on providing quality, schedule, and budget value to the County.
• Provide information, estimates, and schemes regarding construction materials, methods, systems, phasing, sustainability, and costs and participate in decisions regarding same.
• Provide design team with collaborative input on design decisions that impact construction schedule.
• Provide guidance and strategy developing early work packages to support procurement and construction.
• Provide design team with collaborative input on design decisions that impact construction budget.
• Provide input on current market climate and economic conditions.
• Develop detailed and well-organized bid packages in coordination with the design team and County.
• Advertise, manage, and obtain bids per Weld County requirements.
Scope of Construction Services It is anticipated that the GMP will be established during the final stages of the Construction Documents phase and prior to buy-out of/bidding on most or all the bid packages. The GMP may be established after completion of the Construction Documents and subsequent to the bidding phase at the County’s sole discretion.
The established GMP will be the maximum amount paid for the construction of the respective facilities, unless scope changes are requested by the County. County’s acceptance (if accepted) of the GMP by contract amendment will constitute completion of the Preconstruction Services for the applicable Project, and that GMP Amendment will initiate the Construction period for the applicable Project where the CM/GC will take the role as Construction Manager and General Contractor.
At the time of execution of the GMP Amendment, the CM/GC will be required to submit a 100% Performance and 100% Labor & Materials bond for the completion of the specified Project. Failure of the CM/GC to obtain the applicable bonding will result in termination of the applicable GMP Amendment.
The County shall not be obligated to enter into a GMP Amendment with the CM/GC. The County retains the option to cancel the Construction Services; to start a new selection process for the Construction Services of the Project; to terminate the contract and negotiate a replacement contract with the next highest rated Proposer from this solicitation.
Solicitation # B2600077 Page 9
Schedule C - Procurement Schedule
Below is the anticipated schedule for procurement of this solicitation:
Advertisement Date July 2, 2026
Letter of Interest Due (Attachments A and B) July 14, 2026, by 2:00 PM MT
Letter of Interest email bids@weld.gov
Pre-Bid Conference Mandatory July 16, 2026, time and location provided upon receipt of Letter of Interest and Bidder Non-Disclosure Agreement (Attachments A and B)
Technical Questions Due July 30, 2026, by 2:00 PM
Technical Questions email bids@weld.gov
Questions Answered via Addendum August 4, 2026
Proposals Are Due August 18, 2026, by 10:00 am MT Purchasing’s Clock
Interviews (Anticipated) August 25, 2026
Solicitation Notice of Award (Anticipated) September 2, 2026
Contract Execution (Anticipated) September 16, 2026
Solicitation # B2600077 Page 10
Schedule D – RFP Response Criteria
RFP Response Submittal
Weld County is seeking the proposer with the best value for the County. To aid in the determination, contractor shall address the following items in the RFP response submittal, The RFP Response should be arranged in order of the evaluation criteria shown in the RFP Review Scoring Table below.
The response items include:
1. Firm Overview and Qualifications
a) Provide a description of the history and capabilities of your firm. Describe the types of projects or services the firm normally performs and the relative dollar value for each. Provide the firm’s bonding capacity and state the ability of the firm to bond this project.
b) Provide five (5) successfully completed projects where the basis of compensation was a guaranteed maximum price for either public or private customers; profiles should include at least three (3) projects that demonstrate similar complexity, size, scope, logistics in downtown/close building proximity and critical delivery regardless of delivery method.
c) Provide a summary of your firm’s experience in negotiating critical subcontracts early in the design process and describe how you successfully integrated these firms into the project improving project delivery while maintaining price competition.
d) Provide at least three references that can speak to the proposer’s experience with projects of this scale/scope as well as the proposer’s manner of business.
e) Describe any judgements, claims, or suits pending or outstanding against the proposer’s company.
2. Staff Qualifications
a) Provide an organizational chart and narrative staffing plan showing proposed staff, reporting relationships and key responsibilities for each staff member. Describe roles and responsibilities for pre-construction and construction phase services.
b) Provide detailed resumes for each proposed staff member, including the last 5 relevant projects, employment history, education and personal references.
3 Location & Workload
a) Describe the typical geographic range of your firm’s work. If Greeley is outside of that typical geographic range, how do you plan on managing this work to the benefit of Weld County, including pre-construction meeting attendance and management during construction?
b) Provide a summary of your firm’s recent, current and project workload in addition to this project. What has been your annual volume of work (in dollars) for each of the past (10) years. What is your anticipated volume of work (in dollars) for the current year, and what is your plan for the next three (3) years?
Solicitation # B2600077 Page 11
4. Safety & Claims
a) Provide a summary of your team’s accident prevention program and submit your team’s EMR and OSHA Lost Time Accident Rate for each of the past five (5) years.
b) Provide a record of claims, litigation, or arbitration matters initiated by your firm or against your firm (in which you were a named part) for each of the last five years. List the names of the project, the date of litigation, the amount of the settlement or judgement, and identify your involvement, i.e. defendant or plaintiff.
c) Provide a record of complaints filed against your firm by regulatory agencies (e.g., OSHA, County regulators, etc.) for each of the last five years. List the name of the project, the date of complaint, the amount of the settlement and identify your involvement, i.e., defendant or plaintiff.
5. Project Approach
a) Describe the preconstruction process in which your firm will achieve this effort and be successful. Outline your preconstruction team, experience, expertise at early scope definition and development with design team. Include discussion about determining and assessing constructability issues, proposing value engineering, assessing alternative construction options, products and engineering systems for cost savings and life cycle cost design considerations.
b) Identify the precast concrete trade partner your team has competitively selected for this Project. Describe the competitive process used to solicit and evaluate precast subcontractor bids, including the number of firms solicited and the basis of selection.
Provide a signed letter of commitment from the selected precast firm confirming its availability and ability to begin meaningful work immediately and hold production timelines upon Notice of Award.
c) Describe how your team will identify, engage, and commit other critical trade partners (structural steel, mechanical, electrical, plumbing, etc.) upon Notice of Award, demonstrating that schedule sensitive scopes have qualified trade partners in place with no delay to the project.
d) Discuss your firm’s approach to completing the project. Describe how you will support Weld County’s goals to deliver a high-quality functional project with a conservative budget and most efficient schedule.
e) Describe your firm’s cost tracking and budget forecasting approach when working as a project team member during early design and on-going through the project. Describe the proposed project team’s experience in actively interfacing with the project team to provide continuous, real-time cost and budget tracking feedback.
f) Provide your firm’s approach to quality control during design and construction including coordination of subcontract work and commissioning building systems.
g) Explain how the proposer is familiar with Weld County’s project specifications and policies.
h) Provide a description of critical issues that the proposer considers to be of importance for the project and how those issues will be solved.
6. Schedule
Solicitation # B2600077 Page 12
a) Include a preliminary construction schedule showing major milestones by phase associated with this project and how the proposer would complete the project within the contract time.
7. Fee Proposal
a) Provide a Lump Sum or Not-to-Exceed Preconstruction Fee, including staffing assumptions and any reimbursable expenses.
b) Provide the proposed Construction Phase Fee as a percentage of the Cost of the Work, clearly identifying overhead and profit.
8. Cost Model
a. Provide a preliminary cost model for the Weld County Justice Center project based on Attachments C and D.
b. Given that the Parking Structure is currently in the Design Development phase and the Justice Center is currently in the Schematic Design phase, this cost model is not intended to represent a definitive or guaranteed project cost. Instead, the intent is to understand each CM/GC team’s approach to developing early-stage estimates, including the assumptions, methodologies, and level of effort applied. Respondents are expected to rely on relevant historical data, benchmarking, and professional judgment as appropriate.
Response Format
The following defines the response format:
1. Limit the total length of RFP Response to a maximum of 80 pages.
a. The County will reject RFP responses received that are longer than 80 pages in length.
b. The front and back cover will not count as pages.
c. Section dividers do not count as pages.
d. The Proposal document forms and Addendum forms included in this request which are mandatory to submit with your Proposal will not be included in the page count for your proposal.
2. RFP Responses shall be mainly made up of 8 ½” x 11” paper.
a. 11” x 17” paper can only be used for presenting construction schedules, or example plan sheets.
b. Text sizes shall be 10 point or larger.
3. Failure to follow these instructions may result in the RFP Response being rejected.
Grading Criteria
RFP Responses will be evaluated in accordance with the criteria set forth in Table 1. Each RFP Response will be independently evaluated by an evaluation committee selected by the Board of County Commissioners, with committee members scoring responses using the established rating
Solicitation # B2600077 Page 13 scale.
Following completion of the initial evaluation, the evaluation committee will identify the highest-rated proposers as finalists and recommend that the Board interview those finalists. Finalists will be invited to participate in interviews before the Board.
Finalists will be evaluated at the Board’s sole discretion based on the interview criteria identified in Table 2. Interview evaluations will be used to determine final rankings.
The Board of County Commissioners reserves the right to award a contract based on the written RFP Responses alone, to conduct interviews as part of the evaluation process, or to take any other action deemed to be in the best interest of the County.
NOTE: The proposer determined to represent the best value to the County may not be the proposer submitting the lowest overall cost.
Solicitation # B2600077 Page 14
Table 1 - RFP Response Scoring Criteria
Evaluation Criteria
Evaluation Standard Scoring Weighting Factors
Scoring % Range
Firm Overview & Qualifications
Demonstrates relevant project experience, bonding capacity, successful negotiated projects, MEP integration experience, strong references, and acceptable claims history.
1 to 5
3.0
3% - 15%
Staff Qualifications
Proposed team demonstrates appropriate experience, clear roles, strong organizational structure, and relevant project history.
2.0
2% - 10%
Location & Workload
Demonstrates capacity to manage project location effectively, and maintain sufficient workload capacity.
1.0
1% - 5%
Safety & Claims History
Demonstrates strong safety performance (EMR/OSHA), minimal claims history, and regulatory compliance.
2.0
2% - 10%
Project Approach
Demonstrates clear preconstruction strategy, cost control, constructability review, quality control, value engineering, alignment with County goals, and a competitively selected precast concrete trade partner under written commitment and ready to mobilize at Notice of Award.
4.0
4% - 20%
Schedule
Provides a realistic, detailed schedule demonstrating ability to meet contract time.
3.0
3% - 15%
Fee Proposal
Fees are competitive, transparent, and clearly structured; demonstrates sound GMP development and cost control approach.
4.0
4% - 20%
Cost Model
Provides a Cost Model for Project #1 as depicted in Attachments C and D.
1.0
1%-5%
Total
20 to 100
Solicitation # B2600077 Page 15
Table 2 - Interview Scoring Criteria
Evaluation Criteria
Evaluation Standard Scoring Weighting Factors
Scoring % Range
Work Approach The team clearly describes its approach to delivering the project, including integration of scope, schedule, budget, risk identification and mitigation, and stakeholder coordination.
Demonstrates understanding of project constraints and provides practical, implementable strategies.
3% to 15%
Team Qualifications
Demonstrates relevant experience on similar size/complexity projects, strong leadership, and effective communication skills. Shows a proven track record of successful project delivery.
2% to 10%
Preconstruction & Cost Control Approach
Demonstrates a clear and credible approach to cost estimating, budgeting, value management, and maintaining alignment with County funding constraints throughout design and construction.
4% to 20%
Schedule Strategy
Provides a realistic and well-thought-out approach to project scheduling. Identifies key risks to schedule and mitigation strategies.
3% to 15%
Quality of Presentation
Presentation is clear, well-organized, and effectively communicates key information.
Visual aids and speakers enhance understanding.
Question / Answer Session
Responses demonstrate depth of knowledge, transparency, problem-solving ability, and alignment with project goals.
Overall Fit / Confidence
Overall confidence in the team’s ability to successfully deliver the project, based on demonstrated approach, team composition, responsiveness, and alignment with County priorities.
4% to 20%
Total
20 to 100
Solicitation # B2600077 Page 16
Schedule E - Proposal Response Form
Proposal Submittal Instructions The following items must be completed and submitted with your proposal on or before the proposal opening deadline.
1) Vendor’s Proposal – Outlined in Schedule D
2) Schedule E – Proposal Response Form
3) Attachments A and B (Letter of Interest and executed Bidder Non-Disclosure Agreement) on file with the County. These are submitted together prior to the pre-bid conference, not with the Proposal package itself. See Schedule A, “Letter of Interest, Pre-Bid Conference, and Access to Project Drawings.”
4) Any potential or future Addenda must be completed/acknowledged.
5) All other items as requested in the Bid Specifications and/or Scope of Work.
Failure to include any of the above items upon submittal of your Proposal may result in your Proposal being incomplete, non-responsive, and your Proposal being rejected. If there are any exclusions or contingencies submitted with your Proposal, it may be disqualified.
Fees Provide fees for this project below:
Description of Services Lump Sum Cost / Fixed Fee Percentage
Preconstruction Services Fixed Fee (Lump Sum) $
Construction Services Fixed Fee (%) %
General Conditions as a (%) of the Cost of the Work %
Project Insurance (GL, Excess, Auto, Pollution, PL) (%) %
Subguard or Default Insurance (%) %
Builders Risk Insurance Coverage (%) %
General Contractor Performance and Payment Bond Cost (%) %
The proposer acknowledges and agrees that the above stated fees and rates (as may be subsequently modified by negotiation) shall become conditions of the Contract Agreement.
Attestation
The undersigned, by his or her signature, hereby acknowledges and represents that:
1. The Proposal proposed herein meets all the conditions, specifications and special provisions set forth in the Invitation for Proposal for Request B2600077
2. The quotations set forth herein are exclusive of any federal excise taxes and all other state and local taxes.
3. He or she is authorized to bind the below-named Proposer for the amount shown on the accompanying Proposal sheets.
4. Acknowledgement that bidder is required to submit a current IRS Form W9 upon award and prior to contracting.
5. Acknowledgement of Schedule F – Insurance and Bonds
6. Acknowledgment of Schedule G – Weld County Contract
Solicitation # B2600077 Page 17
7. By submitting a responsive proposal, the supplier agrees to be bound by all terms and conditions of the solicitation as established by Weld County.
8. Weld County reserves the right to reject any and all Proposals, to waive any informality in the Proposals, and to accept the Proposal that, in the opinion of the Board of County Commissioners, is to the best interests of Weld County. The Proposal(s) may be awarded to more than one vendor.
Item Entry
Company Name:
Address:
Phone
Email:
FEIN/Federal Tax ID #:
CONTRACTOR:
By: ____________________________ ______________
Date of Signature Name: __________________________
Title: ___________________________
Solicitation # B2600077 Page 18
Schedule F – Insurance and Bonds
Insurance
Contractor shall provide coverage with limits of liability no less than those stated below:
Required Types of Insurance.
1) Workers’ Compensation and Employer’s Liability Insurance covering all the Contractor’s employees acting within the course and scope of their employment. The policy shall contain a waiver of subrogation against the County. This requirement shall not apply when a Contractor or subcontractor is exempt under Colorado Workers’ Compensation Act, AND when such Contractor or subcontractor executes the appropriate sole proprietor waiver form.
Minimum Limits:
Coverage A (Workers' Compensation) Statutory Coverage B (Employers' Liability) $ 100,000 $ 100,000 $ 500,000
2) Commercial General Liability Insurance including public liability and property damage covering all operations required by the Work. The policy shall be endorsed to include the following additional insured language: County, its subsidiary, parent, associated and/or affiliated entities, successors, or assigns, its elected officials, departments, employees, agents, and volunteers shall be named as additional insureds with respect to liability arising out of the activities performed by, or on behalf of the Contractor, including completed operations."
Such policy shall include minimum limits as follows:
Each Occurrence $ 2,000,000
General Aggregate $ 4,000,000
Products/Completed Operations Aggregate $ 4,000,000
Personal Advertising Injury $ 2,000,000
Fire Damage (Any One Fire) $ 100,000 Medical Payments (Any One Person) $ 10,000
Completed Operations coverage must be kept in effect for up to the statute of repose after project completion.
Solicitation # B2600077 Page 19
3) Automobile Liability:
Contractor's Automobile Insurance Policy shall include Minimum Limits as follows:
Bodily Injury/Property Damage (Each Accident) $ 1,000,000
Bodily injury and property damage for any owned, hired, and non-owned vehicles used in the performance of this contract. The County is to be endorsed as an additional insured on policy for Automobile Liability with respect to liability arising out of the activities performed by, or on behalf of the Contractor, including completed operations.
4) Professional Liability: Contractor shall maintain Professional Liability Insurance covering wrongful acts, errors and/or omissions, including design errors, if applicable, for damage sustained by reason of or in the course of operations under this Contract resulting from professional services provided by the Contractor as part of the Contract.
The policy/coverages shall be amended to include the following:
a. Coverage shall apply for three (3) years after project is complete.
b. Policy is to be on a primary basis, if other professional coverage is carried.
Per Loss $ 2,000,000
Aggregate $ 4,000,000
5) Umbrella or Excess Liability Insurance: Contractor shall maintain limits of $5,000,000 and shall become primary in the event the primary liability policy limits are impaired or exhausted.
The policy shall be written on an Occurrence form and shall be following form of the primary.
6) Pollution Liability. Weld County requires this coverage whenever work at issue under this Contract involves potential pollution risk to the environment or losses caused by pollution conditions that may arise from the operations of the Contractor described in the Exhibits.
The policy shall cover the Contractor’s completed operations. Coverage shall apply to sudden and gradual pollution conditions resulting from the escape of release of smoke, vapors, fumes, acids, alkalis, toxic chemicals, liquids, or gases, natural gas, waste materials, or other irritants, contaminants, or pollutants (including asbestos). If the coverage is written on a claims-made basis, the Contractor warrants that any retroactive date applicable to coverage under the policy precedes the effective date of this Contract; and that continuous coverage will be maintained, or an extended discovery period will be exercised for a period of three (3) years beginning from the time that work under this contract is completed.
Solicitation # B2600077 Page 20
Minimum Limits:
Per Loss $ 1,000,000
Aggregate $ 1,000,000
7) Builders' Risk Insurance or Installation Floater – Completed Value Basis: Unless otherwise provided in the attached Exhibits, the Contractor shall purchase and maintain, in a company or companies lawfully authorized to do business in Colorado, Builders' Risk Insurance in the amount of the initial contract amount as described in the attached Exhibits, plus the value of subsequent modifications, change orders, and cost of material supplied or installed by others, comprising total value of the entire Project at the site on a replacement cost basis without optional deductibles.
a. The policy must provide coverage from the time any covered property becomes the responsibility of the Contractor, and continue without interruption during construction, renovation, or installation, including any time during which the covered property is being transported to the construction installation site, or awaiting installation, whether on or off site.
b. Such Builders' Risk Insurance shall be maintained, unless otherwise provided in the Contract Documents or otherwise agreed in writing by all persons and entities who are beneficiaries of such insurance, until final payment has been made or until no person or entity other than the County ’s has insurable interest in the property to be covered, whichever is later.
c. The Builders' Risk insurance shall include interests of the County and if applicable, affiliated or associate entities, the General Contractor, subcontractors and sub-tier contractors in the Project.
d. The Builders' Risk Coverage shall be written on a Special Covered Cause of Loss form and shall include theft, vandalism, malicious mischief, collapse, false-work, temporary buildings, transit, debris removal including demolition, increased cost of construction, architect’s fees and expenses, flood (including water damage), earthquake, and if applicable, all below and above ground structures, piping, foundations including underground water and sewer mains, piling including the ground on which the structure rests and excavation, backfilling, filling, and grading.
e. The Builders’ Risk shall include a Beneficial Occupancy Clause. The policy shall specifically permit occupancy of the building during construction. Contractor shall take reasonable steps to obtain consent of the insurance company and delete any provisions with regard to restrictions within any Occupancy Clauses within the Builder’s Risk Policy.
The Builder’s Risk Policy shall remain in force until acceptance of the project by the County.
f. Equipment Breakdown Coverage (a.k.a. Boiler & Machinery) shall be included as
Solicitation # B2600077 Page 21 required by the Contract Documents or by law, which shall specifically cover insured equipment during installation and testing (including cold and hot testing).
g. The deductible shall not exceed $25,000 and shall be the responsibility of the Contractor for all covered perils within the required policy.
Additional Insurance Related Requirements
No limitation of Liability: The insurance coverages specified in this Agreement are the minimum requirements for this Contract and in no way limit the indemnity covenants contained in this Contract or decrease or limit any liability of Contractor.
The County in no way warrants that the minimum limits contained herein are sufficient to protect the Contractor from liabilities that might arise out of the performance of the Work under by the Contractor, its agents, representatives, employees, or subcontractors. The Contractor shall assess its own risks and if it deems appropriate and/or prudent, maintain higher limits and/or broader coverages. The Contractor is not relieved of any liability or other obligations assumed or pursuant to the Contract by reason of its failure to obtain or maintain insurance in sufficient amounts, duration, or types. The Contractor shall maintain, at its own expense, any additional kinds or amounts of insurance that it may deem necessary to cover its obligations and liabilities under this Agreement.
Certification of Compliance with Insurance Requirements. The Contractor stipulates that it has met the insurance requirements identified herein.
All insurers must be licensed or approved to do business within the State of Colorado, and unless otherwise specified, all policies must be written on a per occurrence basis. The Contractor shall provide the County with a Certificate of Insurance evidencing all required coverages, before commencing work or entering the County premises. The Contractor shall furnish the County with certificates of insurance (ACCORD) form or equivalent approved by the County as required by this Contract. The certificates for each insurance policy are to be signed by a person authorized by that insurer to bind coverage on its behalf. The Contractor shall name on the certificate,” Weld County, its associated and/or affiliated entities, successors, or assigns; its elected officials, employees, agents, and volunteers as Additional Insureds” for Commercial General Liability and Auto Liability for work that is being performed by the Contractor.
On insurance policies where the County is named as an additional insured, the County shall be an additional insured to the full limits of liability purchased by the Contractor even if those limits of liability are in excess of those required by this Contract.
Upon request by the County, Contractor must provide a copy of the actual insurance policy and/or required endorsements effecting coverage(s) required by the Contract for examination for evidence of required coverages. Copies are not kept as a record, are deemed confidential, and are not subject to disclosure under Colorado's Open Records Act (CORA). All certificates
Solicitation # B2600077 Page 22 and endorsements are to be received and approved by the County before work commences.
Each insurance policy required by this Agreement must be in effect at or prior to commencement of work under this Agreement and remain in effect for the duration of the project, and for a longer period of time if required by other provisions in this Agreement.
Failure to maintain the insurance policies as required by this Agreement or to provide evidence of renewal is a material breach of contract.
Any modification or variation from the insurance requirements in this Agreement shall be made by the County Attorney’s Office, whose decision shall be final. Such action will not require a formal contract amendment but may be made by administrative action.
Bonds
1. For projects over $50,000 the following bonds are required:
a. Performance Bond in the amount of 100% of the contract value, will be required at time of contract execution, or as otherwise defined in the Specifications/Scope of Work.
b. Payment Bond (Labor and Materials) in the amount of 100% of the contract value, will be required at time of contract execution, or as otherwise defined in the Specifications/Scope of Work.
2. Surety companies executing bonds must appear on the U.S. Treasury Department’s most current list (Circular 570) as amended and be authorized to transact business in the State of Colorado.
3. A 5% Retainage Fee will be held for Construction contracts over $150,000.
4. Bonds may be submitted on the Standard AIA form or Weld County Form.
Insurance Mailing Information
Certificates of Insurance, endorsements and bonds shall be provided to the County via electronic correspondence or mail using the information below:
Email:
Project Manager: Will Hopkins Email: whopkins@weld.gov Telephone: (970) 400-2044
Mail:
Weld County Facilities Department ATTN: Will Hopkins PO Box 758 Greeley, CO 80632
Solicitation # B2600077 Page 23
Schedule G - Weld County Contract
Contractual Obligations
1. The County will use the following AIA agreements to form the basis for the final agreement with the successful Contractor: Weld County Standard Contract shown in Schedule G of this document will be incorporated into the final agreement as an Exhibit.
The County reserves the right to add or delete provisions to the form prior to Agreement execution.
a. AIA A133-2019 – Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price
2. Issuance of this solicitation does not commit the County to award any agreement or to procure.
3. If a formal contract is required, the Contractor agrees and understands that a Notice of Award does not constitute a contract or create a property interest of any nature until a contract is signed by the Awardee and the Board of County Commissioners and/or their authorized designee.
4. Contractor is responsible for reviewing the Weld County Standard Contract and understanding the terms and conditions contained therein, including, but not limited to, insurance requirements, indemnification, illegal aliens, equal opportunity, non-appropriation, and termination.
5. Contractor’s Response to this solicitation is a willingness to enter into the Weld County Standard Contract or Contractor shall identify and include any proposed revisions they have for the Weld County Standard Contract. Any proposed revisions made by the Contractor after the County Notice of Intent to Award the Solicitation may be grounds for rescinding said Notice. The identification of willingness to enter into the standard Agreement is for general purposes at this time, but is part of the evaluation process and must be included. There may be negotiations on a project-by-project basis that provide further clarification.
6. If the County chooses not to continue the CM/GC Contract beyond the completion of the Preconstruction Services, the CM/GC’s compensation shall be limited to the Preconstruction Services maximum, not to exceed fee stated in the CM/GC Contract.
Weld County Standard Contract
The following represents a sample of Weld County's standard Contract for Construction. This document is provided for reference and is intended to be congruent with the terms and conditions that will be captured in the executed AIA A133 agreement.
Solicitation # B2600077 Page 24
Agreement for Construction Services Between Weld County and [Contractor]
For [Insert Name of Project]
THIS AGREEMENT is made and entered into this [Insert] day of [Insert], 2025, by and between the Board of Weld County Commissioners, on behalf of the [Department], hereinafter referred to as “County,” and [Contractor], hereinafter referred to as “Contractor”.
WHEREAS, County desires to retain Contractor to perform construction services as required by County and set forth in the attached Exhibits; and
WHEREAS, Contractor is willing to perform and has the specific ability, qualifications, and time to perform the required construction services to provide the services according to the terms of this Agreement; and
WHEREAS, Contractor is authorized to do business in the State of Colorado and has the time, skill, expertise, and experience necessary to provide the equipment, materials and services as set forth below;
NOW, THEREFORE, in consideration of the mutual promises and covenants contained herein, the parties hereto agree as follows:
1. Introduction. The terms of this Agreement are contained in the terms recited in this document and in the Exhibits, each of which forms an integral part of this Agreement and are incorporated herein. The parties each acknowledge and agree that this Agreement, including the attached Exhibits, define the performance obligations of Contractor and Contractor’s willingness and ability to meet those requirements (the “Work”). If a conflict occurs between this Agreement and any Exhibit or other attached document, the terms of this Agreement shall control, and the remaining order of precedence shall be based upon order of attachment.
Exhibit A consists of County’s Invitation for Bid (IFB) as set forth in Bid Package No. [Insert Bid Number].
Exhibit B consists of Contractor’s Response to County’s Request for Bid.
2. Service or Work. Contractor agrees to procure the materials, equipment and/or products necessary for the Work and agrees to diligently provide all services, labor, personnel and materials necessary to perform and complete the Work described in the attached Exhibits.
Contractor shall faithfully perform the Work in accordance with the standards of professional care, skill, training, diligence and…