About this file

This is a Combined Synopsis/Solicitation Notice from the Federal Emergency Management Agency (FEMA) for Vehicle Generators, Request for Quote (RFQ) 70FB8025Q00000014. The solicitation seeks the acquisition of 13 8kW and 2 12kW generators for mobile command vehicles used by FEMA's Disaster Emergency Communications Division. These generators will replace 20-year-old existing generators that have exceeded their 10,000-hour life expectancy by 5,000 hours and are becoming unreliable.

The procurement is a Total 100% Small Business Set-Aside under NAICS Code 335312 (Motor and Generator Manufacturing), with a size standard of 1,250 employees. The government intends to award a single firm-fixed-price purchase order using a Lowest Price Technically Acceptable (LPTA) evaluation method. Quotes are due by August 19, 2025, at 2:00 PM ET, with a delivery period of 120 days after award. The solicitation incorporates various Federal Acquisition Regulation (FAR) and Homeland Security Acquisition Regulation (HSAR) clauses, and includes specific requirements such as a prohibition on using Artificial Intelligence without express authorization and compliance with specific federal contracting provisions.

View the file

Other files for this federal contract opportunity

Other files attached to Generator, newest first.
File Type Posted
Questions-Responses.xlsx XLSX spreadsheet
Attachment 1-Generator Replacements - SOW.pdf PDF
Attachment 3-BNJ Generator - Copy_Redacted.pdf PDF
Attachment 2-Pricing Sheet.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

August 08, 2025

COMBINED SYNOPSIS/SOLICITATION NOTICE

For

VEHICLE GENERATOR

Request for Quote 70FB8025Q00000014

(i) This is a combined synopsis/solicitation for commercial products prepared in accordance with the format in the Federal Acquisition Regulation (FAR) subpart 13.106-2 and FAR part 12, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotes are being requested and a write solicitation will not be issued.

(ii) The solicitation, 70FB8025Q00000014, is being issued as a Request for Quote (RFQ) for a Single Award Purchase Order.

(iii) The solicitation documentation and incorporated provisions and clauses are those in effect through Federal Acquisition Circular FAC 2025-05, Effective August 07, 2025 and Homeland Security Acquisition Regulations (HSAR) effective December 26, 2024. It is the responsibility of the contractor to be familiar with the applicable provisions and clauses which can be accessed in full text at:

https://www.acquisition.gov https://www.acquisition.gov/hsar ; and https://www.dhs.gov/publication/current-hsar-deviations

(iv) This requirement is a Total 100% Small Business Set-Aside. The North American Industry

Classification System (NAICS) Code is 335312 Motor and Generator Manufacturing, with a size standard of 1250 employees.

(v) A list of items and unit of measure is at Attachment 2: Pricing Sheet.

(vi) Descriptions of requirements for the items to be acquired is at Attachment 1: Statement Of Work.

https://www.acquisition.gov/ https://www.acquisition.gov/hsar https://www.dhs.gov/publication/current-hsar-deviations

(vii) Attachment 1: Statement Of Work for date(s) and place(s) of delivery and acceptance FOB point.

(viii) FAR 52.212-1, Instructions to Offerors – Commercial Products and Commercial Services apply to this acquisition.

Quotes provided in response to this solicitation must correspond to the specification as stated in the Statement Of Work and conform to the provisions and clauses listed herein

(ix) The provision 52.212-2 Evaluation – Commercial Products and Commercial Services applies to this acquisition. Evaluation will be based on Lowest Priced Technically Acceptable (LPTA).

(x) The provision at 52.212-3, Offeror Representations and Certifications – Commercial Products and Commercial Services, shall be completed and valid in the System of Award and Management (SAM). The offeror must have valid Representations and Certifications filed in the System for Award Management (SAM).

(xi) The clause at 52.212-4, Contract Terms and Conditions – Commercial Items, applies to this acquisition.

(xii) FAR 52.212-5, Contract Terms and Conditions Required to Implement Statues or Executive Orders – Commercial Products and Commercial Services, applies to this acquisition.

(xiii) See Terms and Conditions for additional solicitation requirements.

(xiv) A Defense Priorities and Allocations System (DPAS) rating is not assigned; there is no DPAS rating.

(xv) Questions are due by August 13, 2025, at 11:00AM ET.

Proposals are due by August 19, 2025, at 02:00 PM ET.

(xvi) Contact the following individuals regarding the solicitation:

Lassey Wilson-Bahun, Contracting Officer, Lassey.wilsonbahun@fema.dhs.gov mailto:Lassey.wilsonbahun@fema.dhs.gov

Solicitation: 70FB8025Q00000014 Vehicle Generators

GENERAL

FEMA Disaster Emergency Communications Division Program Office seeks the acquisition of (13) 8kw and (2) 12kw Generators mounted mobile command vehicles that are used by the Agency for vehicle mounted generators. The vehicles provide mobile command and control disaster emergency communications to FEMA Incident Support Teams and directly support FEMA’s Federal, State, Tribal, and Local partners in the field. These new generators will replace the existing 20-year-old generators, that have exceeded the 10,000-hour life expectancy from the manufacturer by 5,000 hours and are becoming unstable and unreliable in the field.

These new 8kw and 12kw are replacements for the current 7.5kw generators, which are no longer available and are the generators that are being installed in the new vehicle builds. They are the only diesel powered, mountable generator that is large enough to provide the power required to support the vehicles missions in the field, but small enough to fit into the very restricted compartments that house them.

CONTRACT TYPE

This solicitation will result in a Single Award Purchase Order containing firm-fixed-price (FFP) contract line-item numbers (CLIN).

CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2) (FEB 1998)

This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at www.acquisition.gov/far.

FAR Clause Title Date

52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG 1996

52.246-16 RESPONSIBILITY OF SUPPLIES APR 1984

52.223-1 BIOBASED PRODUCT CERTIFICATION MAY 2024

Deviation

(FEB 2025)

52.223-4 RECOVERED MATERIAL CERTIFICATION MAY 2008

52.223-23 SUSTAINABLE PRODUCT AND SERVICES MAY 2024

Deviation

(FEB 2025)

52.242-15 STOP-WORK ORDER AUG 1989

52.247-34 F.O.B DESTINATION NOV 1997

PERIOD OF PERFORMANCE

Delivery within 120 days of award

DELIVERY LOCATIONS

Delivery location per Section VI of the Statement of Work

IDENTIFICATION OF GOVERNMENT OFFICIALS

The Government Officials assigned to this contract are as follows:

Contracting Officer – Lassey Wilson-Bahun Email: Lassey.wilsonbahun@fema.dhs.gov

Contracting Officer’s Representative – TBD Name: TBD Email: TBD

The Contracting Officer is the only individual who has the authority on behalf of the Government, among other things, to take the following actions under the contract:

(a) Assign additional work within the general scope of the contract.

(b) Issue a change in accordance with the clause entitled Changes.

http://www.acquisition.gov/far mailto:Lassey.wilsonbahun@fema.dhs.gov

(c) Change the cost or price of the contract.

(d) Change any of the terms, conditions, specifications, or services required by the contract.

(e) Accept non-conforming work. (f) Waive any requirement of the contract.

INVOICES

An invoice is a written request for payment under this contract for supplies delivered. Payment of invoices submitted under this contract shall be made in accordance with the terms and conditions of the Prompt Payment clause in accordance with the terms and conditions of the Prompt Payment clause in accordance with the provisions of other clauses in this contract.

Failure or refusal to provide the following information on all invoices submitted under this contract may result in the invoice being considered improper for payment in accordance with the Prompt Payment clause.

In order to be proper, an invoice must include, as applicable, the following:

(a) GENERAL INFORMATION

(1) Name of Contractor

(2) Invoice Date

(3) Contract number (including task order number, if any), contract line-item number, contract description of supplies or services, quantity, contract unit of measure and unit price, and extended total.

(4) Shipment number and date of shipment (bill-of-lading number and weight of shipment will be shown for shipments on Government bills of lading).

(5) Name, title, phone number and complete mailing address of responsible Official who can be contacted in the event of an improper invoice, if there are questions, or additional information is needed by this agency to process payment.

(6) Any other information or documentation required by other provisions of the Contract (such as evidence of shipment).

(7) Invoices shall be prepared and submitted as follows:

(b) ELECTRONIC FUNDS TRANSFER (EFT) INFORMATION

(1) As mandated by the Debt collection Improvement Act (DCIA) of 1996 and in accordance with FAR Clause 52.232-33-Payment By Electronic Funds Transfer—System for Award Management (JUL 2013) of this contract, the Contractor must submit the following written EFT information as specified in clause 52.232-33 of this award:

· The contract number (or other procurement identification number).

· The Contractor’s name and remittance address, as stated in the contract(s).

· The signature (manual or electronic, as appropriate), title, and telephone number of the Contractor official authorized to provide this information.

· The name, address, and 9-digit Routing Transit Number (RTN) of the Contractor’s financial agent.

· The Contractor’s account number and the type of account (checking, savings, or lockbox).

· If applicable, the Fedwire Transfer System (FTS) telegraphic abbreviation of the Contractor’s financial agent.

· If applicable, the Contractor shall also provide the name, address, telegraphic abbreviation, and 9-digit Routing Transit Number (RTN) of the correspondent financial institution receiving the wire transfer payment if the Contractor’s financial agent is not directly on-line to the FTS; and, therefore, not the receiver of the wire transfer payment.

(2) The Contractor should include the EFT information set forth below on all invoices submitted for payment under this contract. Failure to provide the information or failure to notify this agency of changes to this information may result in delays in payments and/or rejection of the invoice in accordance with the Prompt Payment clause of this contract. The following EFT information should be submitted on each invoice”.

(a) Routing Transit Number (RTN) – The Contractor shall provide the current 9-digit RTN of the payee’s bank

(b) Payee’s account number

(c) Contractor’s Tax Identification Number (TIN)

(The EFT information submitted must be that of the Contractor unless there is an official Assignment of Claims on file with the payment office.)

If at any time during the term of this contract, the Contractor changes any EFT information, (i.e.

financial agent, RTN, account number, etc.) the new EFT information must replace the old EFT information on subsequent invoices submitted under this contract.

To avoid delays in processing invoices, the Contractor must also submit written notification of EFT information changes to the office designated in this award document as soon as the new information is known to the Contractor. This notification must be in writing and signed by the individual authorized by the Contractor to make such changes.

In addition, you need to maintain current information in the System for Award Management (SAM) database. The government may reject invoices if you have not maintained your registration, including Electronic Funds Transfer (EFT) information, in the SAM database.

FAR 52.252-2 – Clauses Incorporated by Reference (FEB 1998) This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at www.acquisition.gov/far.

FAR 52.202-1 Definitions. (JUN 2020) FAR 52.203-6 Restrictions on Subcontractor Sales to the Government. - Alternate I (NOV 2021) FAR 52.204-12 Unique Entity Identifier Maintenance. (OCT 2016) FAR 52.204-13 System for Award Management Maintenance. (OCT 2018) FAR 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) FAR 52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014) FAR 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (JAN 2025) FAR 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters. (OCT 2018) FAR 52.211-6 Brand Name or Equal (Aug 1999) FAR 52.233-3 Protest after Award. – Alternate I (JUN 1985) FAR 52.232-39 Unenforceability of Unauthorized Obligations. (JUN 2013) FAR 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drove Act-Covered Foreign Entities. (NOV 2024) FAR 52.242-13 Bankruptcy. (JUL 1995) FAR 52.243-1 Changes – Fixed Price (AUG 1987)

FAR 52.249-8 Default (Fixed-Price Supply and Service). (APR 1984) FAR 52.249-14 Excusable Delays (APR 1984) FAR 52.252-6 Authorized Deviations in Clauses (NOV 2020) http://www.acquisition.gov/far

FAR 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND

SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB COVERED ENTITIES

(DEVIATION 20-05) (JUL 2024)

(a) Definitions. As used in this clause – Kaspersky Lab covered article means any hardware, software, or service that–

(1) Is developed or provided by a Kaspersky Lab covered entity;

(2) Includes any hardware, software, or service developed or provided in whole or in part by a Kaspersky Lab covered entity; or

(3) Contains components using any hardware or software developed in whole or in part by a Kaspersky Lab covered entity.

Kaspersky Lab covered entity means–

(1) Kaspersky Lab;

(2) Any successor entity to Kaspersky Lab, including any change in name, e.g., “Kaspersky”;

(3) Any entity that controls, is controlled by, or is under common control with Kaspersky Lab;

or

(4) Any entity of which Kaspersky Lab has a majority ownership. (b) Prohibition. Section 1634 of Division A of the National Defense Authorization Act for Fiscal Year 2018 (Pub. L. 115-91) prohibits Government use of any Kaspersky Lab covered article. The Contractor is prohibited from—

(1) Providing any Kaspersky Lab covered article that the Government will use on or after October 1, 2018; and

(2) Using any Kaspersky Lab covered article on or after October 1, 2018, in the development of data or deliverables first produced in the performance of the contract.

(c) Reporting requirement.

(1) In the event the Contractor identifies covered article provided to the Government during contract performance, or the Contractor is notified of such by a subcontractor at any tier or by any other source, the Contractor shall report, in writing, via email, to the Contracting Officer, Contracting Officer's Representative, and the Enterprise Security Operations Center (SOC) at NDAA Incidents@hq.dhs.gov, with required information in the body of the email. In the case of the Department of Defense, the Contractor shall report to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the Enterprise SOC, Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) and Contracting Officer's Representative(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https://dibnet.dod.mil.

(2) The Contractor shall report the following information pursuant to paragraph (c)(1) of this clause:

(i) Within 3 business days from the date of such identification or notification: the contract number; the order number(s), if applicable; supplier name; brand; model number (Original Equipment Manufacturer (OEM) number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.

(ii) Within 10 business days of submitting the report pursuant to paragraph (c)(1) of this clause: any further available information about mitigation actions undertaken or recommended. In addition, the Contractor shall describe the efforts it undertook to prevent use or submission of a Kaspersky Lab covered article, any reasons that led to the use or submission of the Kaspersky Lab covered article, and any additional efforts that will be incorporated to prevent future use or submission of Kaspersky Lab covered articles. (d) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (d), in all subcontracts, including subcontracts for https://dibnet.dod.mil/ the acquisition of commercial items.

(End of clause)

FAR 52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS

AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (DEVIATION 20-05) (DEC 2020)

(a) Definitions. As used in this clause-

"Backhaul" means intermediate links between the core network, or backbone network, and the small subnetworks at the edge of the network (e.g., connecting cell phones/towers to the core telephone network).

Backhaul can be wireless (e.g., microwave) or wired (e.g., fiber optic, coaxial cable, Ethernet).

"Covered foreign country" means – The People's Republic of China.

"Covered telecommunications equipment or services" means-

(1) Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities);

(2) For the purpose of public safety, security of Government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities);

(3) Telecommunications or video surveillance services provided by such entities or using such equipment; or

(4) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.

"Critical technology" means-

(l) Defense articles or defense services included on the United States Munitions List set forth in the International Traffic in Arms Regulations under subchapter M of chapter I of title 22, Code of Federal Regulations;

(2) Items included on the Commerce Control List set forth in Supplement No. 1 to part 774 of the Export Administration Regulations under subchapter C of chapter VII of title 15, Code of Federal Regulations, and controlled-

(i) Pursuant to multilateral regimes, including for reasons relating to national security, chemical and biological weapons proliferation, nuclear nonproliferation, or missile technology; or

(ii) For reasons relating to regional stability or surreptitious listening;

(3) Specially designed and prepared nuclear equipment, parts and components, materials, software, and technology covered by part 810 of title 10, Code of Federal Regulations (relating to assistance to foreign atomic energy activities);

(4) Nuclear facilities, equipment, and material covered by part 110 of title 10, Code of Federal Regulations (relating to export and import of nuclear equipment and material);

(5) Select agents and toxins covered by part 331 of title 7, Code of Federal Regulations, part 121 of title 9 of such Code, or part 73 of title 42 of such Code; or

(6) Emerging and foundational technologies controlled pursuant to section 1758 of the Export Control Reform Act of2018 (50 U.S.C. 4817).

"Interconnection arrangements" means arrangements governing the physical connection of two or more networks to allow the use of another's network to hand off traffic where it is ultimately delivered (e.g., connection of a customer of telephone provider A to a customer of telephone company B) or sharing data and other information resources.

"Reasonable inquiry" means an inquiry designed to uncover any information in the entity's possession about the identity of the producer or provider of covered telecommunications equipment or services used by the entity that excludes the need to include an internal or third-party audit.

"Roaming" means cellular communications services (e.g., voice, video, data) received from a visited network when unable to connect to the facilities of the home network either because signal coverage is too weak or because traffic is too high.

"Substantial or essential component" means any component necessary for the proper function or performance of a piece of equipment, system, or service.

(b) Prohibition.

(1) Section 889(a)(l)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub.

L. 115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. The Contractor is prohibited from providing to the Government any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104.

(2) Section 889(a)(l)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub.

L. 115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract, or extending or renewing a contract, with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system, unless an exception at paragraph (c) of this clause applies or the covered telecommunication equipment or services are covered by a waiver described in FAR 4.2104. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract.

(c) Exceptions. This clause does not prohibit contractors from providing-

(1) A service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(2) Telecommunications equipment that cannot route or redirect user data traffic or permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(d) Reporting requirement.

(1) In the event the Contractor identifies covered telecommunications equipment or services used as a substantial or essential component of any system, or as critical technology as part of any system, during contract performance, or the Contractor is notified of such by a subcontractor at any tier or by any other source, the Contractor shall report the information in paragraph (d)(2) of this clause in writing via email to the Contracting Officer, Contracting Officer's Representative, and the Network Operations Security Center (NOSC) at NDAA Incidents@hq.dhs.gov, with required information in the body of the email. In the case of the Department of Defense, the Contractor shall report to the website at https://dibnet.dod.mil. For indefinite delivery contracts, the Contractor shall report to the NOSC, Contracting Officer for the indefinite delivery contract and the Contracting Officer(s) and Contracting Officer's Representative(s) for any affected order or, in the case of the Department of Defense, identify both the indefinite delivery contract and any affected orders in the report provided at https:// dibnet.clod.mil.

(2) The Contractor shall report the following information pursuant to paragraph (d)(l) of this clause

(i) Within one business day from the date of such identification or notification:

the contract number; the order number(s), if applicable; supplier name; supplier unique entity identifier (if known); supplier Commercial and Government Entity (CAGE) code (if known); brand; model number (original equipment manufacturer number, manufacturer part number, or wholesaler number); item description; and any readily available information about mitigation actions undertaken or recommended.

(ii) Within 10 business days of submitting the information in paragraph (d)(2)(i) of this clause: any further available information about mitigation actions undertaken or recommended. In addition, the Contractor shall describe the efforts it undertook to prevent use or submission of covered telecommunications equipment or services, and any additional efforts that will be incorporated to prevent future use or submission of covered telecommunications equipment or services.

(e) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (e) and excluding paragraph (b)(2), in all subcontracts and other contractual instruments, including subcontracts for the acquisition of commercial items.

FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND

COMMERCIAL SERVICES (NOV 2023)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights-

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act ( 31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include-

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_233_1 https://www.acquisition.gov/far/part-52#FAR_52_202_1

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer-System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer-Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by

EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act ( 31 U.S.C.3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR Part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.-

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act ( 31 U.S.C.3903) and prompt payment regulations at 5 CFR Part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall-

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the-

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this https://www.acquisition.gov/far/part-52#FAR_52_232_33 https://www.acquisition.gov/far/part-52#FAR_52_232_34 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-52#FAR_52_212_5 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if–

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price https://www.acquisition.gov/far/part-33#FAR_33_211 https://www.acquisition.gov/far/part-32#FAR_32_607_2 https://www.acquisition.gov/far/part-32#FAR_32_608_2 reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C.

1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C.

chapter 87, Kickbacks; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;

(3) The clause at 52.212-5.

(4) Addenda to this solicitation or contract, including any license agreements for computer software.

(5) Solicitation provisions if this is a solicitation.

(6) Other paragraphs of this clause.

(7) The Standard Form 1449.

(8) Other documents, exhibits, and attachments.

(9) The specification.

(t) [Reserved] https://www.acquisition.gov/far/part-52#FAR_52_212_5 https://www.gsa.gov/forms-library/solicitationcontractorder-commercial-items

(u) Unauthorized Obligations.

(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti- Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an "I agree" click box or other comparable mechanism (e.g., "click-wrap" or "browse-wrap" agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of clause)

FAR 52.212-5 Contract Terms and Conditions Required To Implement Statutes or Executive Orders— Commercial Products and Commercial Services. (Jan 2025)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Nov 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).

(5) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) ( 31 U.S.C.

3903 and 10 U.S.C. 3801).

(6) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(7) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Public Laws 108-77 and 108-78 ( 19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has https://www.acquisition.gov/far/part-52#FAR_52_203_19 https://www.acquisition.gov/far/part-52#FAR_52_204_23 https://www.acquisition.gov/far/part-52#FAR_52_204_25 https://www.acquisition.gov/far/part-52#FAR_52_209_10 https://www.acquisition.gov/far/part-52#FAR_52_232_40 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section3801&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_233_3 https://www.acquisition.gov/far/part-52#FAR_52_233_4 indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.]

__ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Jun 2020), with Alternate I (Nov 2021) (41 U.S.C. 4704 and 10 U.S.C. 4655).

_x_ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Nov 2021) (41 U.S.C. 3509)).

__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

__ (4) 52.203-17, Contractor Employee Whistleblower Rights (Nov 2023) ( 41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community—see FAR 3.900(a).

__ (5) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) (Pub. L. 109-

282) ( 31 U.S.C. 6101 note).

__ (6) [Reserved].

__ (7) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

__ (8) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L.

111-117, section 743 of Div. C).

_x_ (9) 52.204-27, Prohibition on a ByteDance Covered Application (Jun 2023) (Section 102 of Division R of Pub.

L. 117-328).

__ (10) 52.204-28, Federal Acquisition Supply Chain Security Act Orders—Federal Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts. (Dec 2023) ( Pub. L. 115–390, title II).

__ (11)

(i) 52.204-30, Federal Acquisition Supply Chain Security Act Orders—Prohibition. (Dec 2023) ( Pub. L. 115–390, title II).

__ (ii) Alternate I (Dec 2023) of 52.204-30.

__ (12) 52.209-6, Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Jan 2025) ( 31 U.S.C. 6101 note).

__ (13) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) ( 41 U.S.C. 2313).

__ (14) [Reserved].

__ (15) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Oct 2022) ( 15 U.S.C. 657a).

__ (16) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Oct 2022) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

__ (17) [Reserved]

__ (18) https://www.acquisition.gov/far/part-52#FAR_52_203_6 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section4655&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_203_13 https://www.acquisition.gov/far/part-52#FAR_52_203_15 https://www.acquisition.gov/far/part-52#FAR_52_203_17 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section4712&num=0&edition=prelim https://www.acquisition.gov/far/part-3#FAR_3_900 https://www.acquisition.gov/far/part-52#FAR_52_204_10 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section6101&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_204_14 https://www.acquisition.gov/far/part-52#FAR_52_204_15 https://www.acquisition.gov/far/part-52#FAR_52_204_27 https://www.acquisition.gov/far/part-52#FAR_52_204_28 https://www.govinfo.gov/link/plaw/115/public/390 https://www.acquisition.gov/far/part-52#FAR_52_204_30 https://www.govinfo.gov/link/plaw/115/public/390 https://www.acquisition.gov/far/part-52#FAR_52_204_30 https://www.acquisition.gov/far/part-52#FAR_52_209_6 https://www.govinfo.gov/link/uscode/31/6101 https://www.acquisition.gov/far/part-52#FAR_52_209_9 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section2313&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_219_3 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637a&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_219_4

(i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

__ (ii) Alternate I (Mar 2020) of 52.219-6.

__ (19)

(i) 52.219-7, Notice of Partial Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

__ (ii) Alternate I (Mar 2020) of 52.219-7.

__ (20) 52.219-8, Utilization of Small Business Concerns (Jan 2025)( 15 U.S.C. 637(d)(2) and (3)).

__ (21)

(i) 52.219-9, Small Business Subcontracting Plan (Jan 2025) ( 15 U.S.C. 637(d)(4)).

__ (ii) Alternate I (Nov 2016) of 52.219-9.

__ (iii) Alternate II (Nov 2016) of 52.219-9.

__ (iv) Alternate III (Jun 2020) of 52.219-9.

__ (v) Alternate IV (Jan 2025) of 52.219-9.

__ (22)

(i) 52.219-13, Notice of Set-Aside of Orders (Mar 2020) (15 U.S.C. 644(r)).

__ (ii) Alternate I (Mar 2020) of 52.219-13.

__ (23) 52.219-14, Limitations on Subcontracting (Oct 2022) (15 U.S.C. 657s).

__ (24) 52.219-16, Liquidated Damages—Subcontracting Plan (Sep 2021) (15 U.S.C. 637(d)(4)(F)(i)).

__ (25) 52.219-27, Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program (Feb 2024) (15 U.S.C. 657f).

__ (26)

(i) 52.219-28, Postaward Small Business Program Rerepresentation (Jan 2025) (15 U.S.C. 632(a)(2)).

__ (ii) Alternate I (Mar 2020) of 52.219-28.

__ (27) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (Oct 2022) (15 U.S.C. 637(m)).

__ (28) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (Oct 2022) (15 U.S.C. 637(m)).

__ (29) 52.219-32, Orders Issued Directly Under Small Business Reserves (Mar 2020) ( 15 U.S.C. 644(r)).

__ (30) 52.219-33, Nonmanufacturer Rule (Sep 2021) ( 15 U.S.C. 637(a)(17)).

_x_ (31) 52.222-3, Convict Labor (Jun 2003) (E.O. 11755).

_x_ (32) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Jan 2025)( E.O. 13126).

__ (33) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).

https://www.acquisition.gov/far/part-52#FAR_52_219_6 https://www.acquisition.gov/far/part-52#FAR_52_219_6 https://www.acquisition.gov/far/part-52#FAR_52_219_7 https://www.acquisition.gov/far/part-52#FAR_52_219_7 https://www.acquisition.gov/far/part-52#FAR_52_219_8 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_219_9 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637&num=0&edition=prelim https://www.acquisition.gov/far/part-52#FAR_52_219_9 https://www.acquisition.gov/far/part-52#FAR_52_219_9 https://www.acquisition.gov/far/part-52#FAR_52_219_9 https://www.acquisition.gov/far/part-52#FAR_52_219_9 https://www.acquisition.gov/far/part-52#FAR_52_219_13 https://www.acquisition.gov/far/part-52#FAR_52_219_13 https://www.acquisition.gov/far/part-52#FAR_52_219_14 https://www.acquisition.gov/far/part-52#FAR_52_219_16 https://www.acquisition.gov/far/part-52#FAR_52_219_27 https://www.acquisition.gov/far/part-52#FAR_52_219_28…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .