Levee Scour - Emergency Shoreline Protection (CS-004A) Contract Summary
The State of Louisiana, Coastal Protection and Restoration Authority (CPRA) issued a Request for Quotes for the Levee Scour - Emergency Shoreline Protection project (CS-004A) located in Cameron Parish, Louisiana. The project involves emergency shoreline protection measures through the placement of net-wrapped round hay bales along an eroded levee section, supplemented by supporting materials including southern yellow pine lumber and zinc-coated steel strapping. Bid items include: (1) mobilization and demobilization on a lump-sum basis; (2) 4-foot by 5-foot net-wrapped hay bales with a minimum 600-pound weight (225 units); (3) 2-inch by 2-inch by 8-foot #1 southern yellow pine (450 units); and (4) 1.25-inch zinc-coated steel strapping (5,800 linear feet). Quotes were due by October 27, 2026, at 2:00 P.M., submitted electronically via email. The work must be completed within 30 consecutive calendar days from the Notice to Proceed, with liquidated damages assessed at $500 per day for delays. Contractors must possess valid Louisiana licenses in Heavy Construction with Coastal Restoration and Habitat Enhancement specialty classification for earthwork, drainage, and levees to bid on contracts exceeding $50,000.
A Performance and Payment Bond equal to 100 percent of the contract amount is required, with the surety listed on the U.S. Department of Treasury Financial Management Service List or meeting Louisiana insurance requirements. The Owner reserves the right to reject any or all quotes and notes that contract execution is contingent upon availability of state bonds or federal funds. Contractors must comply with all federal, state, and local laws, including Davis-Bacon Act prevailing wage requirements and environmental protection regulations. The contract includes a one-year guarantee period for all work following final acceptance. No specific set-aside provisions are indicated in the solicitation documents.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LEVEE SCOUR – EMERGENCY SHORELINE PROTECTION
(CS-004A)
CAMERON PARISH, LOUISIANA
OCTOBER 2026
STATE OF LOUISIANA
COASTAL PROTECTION AND RESTORATION AUTHORITY
Post Office Box 44027 ● Baton Rouge, Louisiana 70804-4027 ● 150 Terrace Avenue ● Baton Rouge, Louisiana 70802
(225) 342-7308 ● Fax (225) 342-9417 ● http://www.coastal.la.gov
An Equal Opportunity Employer
October 13, 2026
The State of Louisiana, Coastal Protection and Restoration Authority (CPRA) is accepting Quotes for the Levee Scour – Emergency Shoreline Protection (CS-004A) until Tuesday, October 27, 2026 at 2:00 P.M.
All Quotes shall be submitted electronically via e-mail to cpra.bidding@la.gov using the attached Quote Form.
Contractors should review and understand the attached Technical Specifications and Project Plans prior to submitting Quotes.
Questions regarding the Plans and Specifications may be directed to cpra.bidding@la.gov
Quotes in excess of fifty thousand dollars ($50,000) shall be accepted from Contractors who are licensed under La. R.S. 37:2150-2192 for any of the following licensure classifications:
Major Classification: Heavy Construction, Specialty Classification: Coastal Restoration and Habitat Enhancement: Subclassification: Earthwork, Drainage, and Levees
The Owner, the Coastal Protection and Restoration Authority, reserves the right to reject any and all Quotes for any reason.
When this project is financed either partially or entirely with State Bonds or financed in whole or in part by federal or other funds which are not readily available at the time Quotes are received, the award of this Contract is contingent upon the granting of lines of credit, or the sale of bonds by the Bond Commission or the availability of federal or other funds. The State shall incur no obligation to the Contractor until the Contract between Owner and Contractor is fully executed.
Each person or entity by submitting a Quote represents that:
a. He has read and understands the Contract Documents including the Plans and Specifications and his Quote is made in accordance therewith.
b. His Quote is based solely upon the materials, systems and equipment described in the Plans and Specifications.
c. His Quote is not based on any verbal instructions contrary to the Contract Documents, including the Plans and Specifications.
d. He is familiar with the Code of Governmental Ethics requirement that prohibits public servants and/or their immediate family members from entering into contracts; he is aware that the Designer and its principal owners are considered Public Servants under the Code of Governmental Ethics for the limited purposes and scope of the Design Contract with the
State on this Project (see Ethics Board Advisory Opinion, No. 2009-378 and 2010-128); and neither he nor any principal of the entity with a controlling interest therein has an immediate family relation-ship with the Designer or any principal within the Designer’s firm. (see La.
R.S. 42:1113). Any person submitting a Quote in violation of this clause shall be disqualified and any contract entered into in violation of this clause shall be null and void.
e. The person or entity submitting a Quote must be fully qualified under any State or local licensing law for Contractors in effect at the time and at the location of the work before submitting his Quote. In the State of Louisiana, La. R.S. 37:2150, et seq. will be considered, if applicable.
PERFORMANCE AND PAYMENT BOND
a. Bond Required
When entering into a Contract with CPRA, the Contractor shall furnish and pay for a Performance and Payment Bond written by a company licensed to do business in Louisiana, which shall be signed by the surety’s agent or attorney-in-fact, in an amount equal to 100% of the Contract amount. Surety must be listed currently on the U. S. Department of Treasury Financial Management Service List (Treasury List) as approved for an amount equal to or greater than the contract amount, or must be an insurance company domiciled in Louisiana or owned by Louisiana residents. If surety is qualified other than by listing on the Treasury list, the contract amount may not exceed fifteen percent of policyholders' surplus as shown by surety’s most recent financial statements filed with the Louisiana Department of Insurance and may not exceed the amount of $500,000. However, a Louisiana domiciled insurance company with at least an A- rating in the latest printing of the A. M. Best’s Key Rating Guide shall not be subject to the $500,000 limitation, provided that the contract amount does not exceed ten percent of policyholders’ surplus as shown in the latest A. M. Best’s Key Rating Guide nor fifteen percent of policyholders’ surplus as shown by surety's most recent financial statements filed with the Louisiana Department of Insurance. The Bond shall be signed by the surety’s agent or attorney-in-fact. The Bond shall be in favor of the Coastal Protection and Restoration Authority.
b. Time of Delivery and Form of Bond
The Contractor shall deliver the required bond to the Owner simultaneous with the execution of the Contract.
Bond shall be in the form furnished by the Coastal Protection and Restoration Authority, entitled CONTRACT BETWEEN OWNER AND CONTRACTOR AND PERFORMANCE AND PAYMENT BOND, a copy of which is included in the Contract Documents.
The Contractor shall require the Attorney-in-Fact who executes the required bond on behalf of the surety to affix thereto a certified and current copy of his power of Attorney.
REFERENCE CONTRACT DOCUMENTS
Any Contractor whose Quote is selected for the Work, will be required to sign the following:
A: A form of agreement between Contractor and the Owner (Contract).
B: An attestations affidavit.
C: A non-collusion affidavit.
Examples of all three of the above-referenced documents may be found in the attached.
QUOTE FORM
QUOTE FOR: Levee Scour – Emergency Shoreline Protection (CS-004A)
The undersigned hereby declares and represents that she/he: a) has carefully examined and understands the Contract Documents, Plans and Specifications, b) has not received, relied on, or based his quote on any verbal instructions contrary to the Contract Documents c) has personally inspected and is familiar with the project site, and hereby proposes to provide all labor, materials, tools, appliances and facilities as required to perform, in a workmanlike manner, all work and services for the completion of the referenced project, all in strict accordance with the Contract Documents prepared by: CPRA and dated: October 2026.
NAME:_______________________________________________________________________________
ADDRESS:____________________________________________________________________________
LOUISIANA CONTRACTOR’S LICENSE NUMBER: ___________________
NAME OF AUTHORIZED SIGNATORY: ______
TITLE OF AUTHORIZED SIGNATORY: ______
SIGNATURE OF AUTHORIZED SIGNATORY: _____________
DATE: _______________________
ITEM
NO. DESCRIPTION UNIT QUANTITY PROPOSED UNIT
COST
TOTAL
PROPOSED COST
1 Mobilization and Demobilization LS 1 $____________ $_______________
4’ X 5’ Net Wrapped Round Hay Bale (600 Lb. Minimum)
Quantity noted on plan sheets are based on linear footage of shoreline to protect. Additional quantity added to bid item for contingency.
Each 225 $_____________ $_______________
3 2” X 2” X 8’ #1 Southern Yellow Pine Each 450 $_____________ $_______________
1-1/4” Zinc-Coated Steel Strapping
LF 5,800 $______________ $______________
SUM OF TOTAL PROPOSED COSTS FOR ALL ITEMS
FOR INFORMATION ONLY – ATTESTATIONS AFFIDAVIT
This document will be prepared by the Coastal Protection and Restoration Authority in the form appropriate for the project.
Name of Project Project No.
Levee Scour – Emergency Shoreline Protection CS-004A
PARISH OF CAMERON
ATTESTATIONS AFFIDAVIT
Before me, the undersigned notary public, duly commissioned and qualified in and for the parish and state aforesaid, personally came and appeared Affiant, who after being duly sworn, attested as follows:
PAST CRIMINAL CONVICTIONS
A. No sole proprietor or individual partner, incorporator, director, manager, officer, organizer, or member who has a minimum of a ten percent (10% ownership in the entity named below has been convicted of, or has entered a plea of guilty or nolo contendere to any of the following state crimes or equivalent federal crimes:
(a) Public bribery (R.S.14:118) (c) Extortion (R.S. 14:66)
(b) Corrupt influencing (R.S. 14:120) (d) Money laundering (R.S. 14:23)
B. Within the past five years from the project date, no sole proprietor or individual partner, incorporator, director, manager, officer, organizer, or member who has a minimum of ten percent (10%) ownership in the entity named below has been convicted of, or has entered a plea of guilty or nolo contendere to any of the following state crimes or equivalent federal crimes, during the solicitation or execution of a contract or bid awarded pursuant to the provisions of Chapter 10 of Title 38 of the Louisiana Revised Statutes:
(a) Theft (R.S. 14:67) (e)Bank fraud (R.S. 14:71.1)
(b) Identity Theft (R.S. 14:67.16) (f)Forgery (R.S. 14:72)
(c) False accounting (R.S. 14:70) (g) Contractors; misapplication of payments
(d) Issuing worthless checks (R.S. 14:71) (R.S. 14:202)
(h) Malfeasance in office (R.S. 14:134)
LA. R.S. 38:2212.10 Verification of Employees
A. At the time of the submission of the quote/estimate, Appearer is registered and participates in a status verification system to verify that all new employees in the state of Louisiana are legal citizens of the United States or are legal aliens.
B. If awarded the contract, Appearer shall continue, during the term of the contract, to utilize a status verification system to verify the legal status of all new employees in the state of Louisiana.
C. If awarded the contract, Appearer shall require all subcontractors to submit to it a sworn affidavit verifying compliance with Paragraphs (A) and (B) of this Subsection.
Name of Project Project No.
Levee Scour – Emergency Shoreline Protection CS-004A
LA. R.S. 23:1726(B) Certification Regarding Unpaid Workers Compensation Insurance
A. R.S. 23:1726 prohibits any entity against whom an assessment under Part X of Chapter 11 of Title 23 of the Louisiana Revised Statutes of 1950 (Alternative Collection Procedures & Assessments) is in effect, and whose right to appeal that assessment is exhausted, from submitting a quote for or obtaining any contract pursuant to Chapter 10 of Title 38 of the Louisiana Revised Statutes of 1950 and Chapters 16 and 17 of Title 39 of the Louisiana Revised Statutes of 1950.
B. By signing this quote, Affiant certifies that no such assessment is in effect against the quoting entity.
NAME OF CONTRACTOR NAME OF AUTHORIZED SIGNATORY OF CONTRACTOR
DATE TITLE OF AUTHORIZED SIGNATORY OF CONTRACTOR
SIGNATURE OF AUTHORIZED
SIGNATORY OF CONTRACTOR
Sworn to and subscribed before me by Affiant on the _____ day of _____________ , 2026.
Notary Public
Printed Name:______________________________
Bar Roll/Notary No.:________________________
My Commission expires:_____________________
FOR INFORMATION ONLY –
EXAMPLE CONTRACT BETWEEN OWNER AND CONTRACTOR
This document will be prepared by the Coastal Protection and Restoration Authority in the form appropriate for the project.
CONTRACT BETWEEN OWNER AND CONTRACTOR
AND PERFORMANCE AND PAYMENT BOND
This agreement entered into this day of , 2026, by (CONTRACTOR NAME) hereinafter called the "Contractor", whose business address is_____________, and the State of Louisiana, Coastal Protection and Restoration Authority, herein represented by its Executive Director executing this Contract, and hereinafter called the "Owner".
Witnesseth that the Contractor and the Owner, in consideration of premises and the mutual covenants;
consideration and agreement herein contained, agree as follows:
Statement of Work: The Contractor shall furnish all labor and materials and perform all of the work required to build, construct and complete in a thorough and workmanlike manner:
Project No. CS-004A
Project Name: Levee Scour – Emergency Shoreline Protection in strict accordance with Contract Documents prepared by Owner.
It is recognized by the parties herein that said Contract Documents, including by way of example and not of limitation, the Plans, Specifications (including General Provisions, Special Provisions, and Technical Specifications), Any Addenda thereto, Instructions To Bidders, this Contract, Advertisement For Bids, Affidavit, Bid Form, Bonds (Bid, Performance, and Payment),any Submitted Post-Bid Documentation, Notice of Award, Notice to Proceed, Change Orders, and Claims, if any, impose duties and obligations upon the parties herein, and said parties thereby agree that they shall be bound by said duties and obligations. For these purposes, all of the provisions contained in the aforementioned Contract Documents are incorporated herein by reference with the same force and effect as though said Contract Documents were herein set out in full.
Time for Completion: The work shall be commenced on a date to be specified in a written order of the Owner and shall be completed within 30 consecutive calendar days from and after the said date.
Liquidated Damages: Contractor shall be assessed Liquidated Damages in the amount of five hundred dollars and zero cents ($500.00) per day for each consecutive calendar day which work is not complete beginning with the first day beyond the completion time.
Compensation to be paid to the Contractor: The Owner will pay and the Contractor will accept in full consideration for the performance of the Contract the sum of ______________Dollars ($) which sum represents the Contract Price.
Performance and Payment Bond: To these presents personally came and intervened_________________, herein acting for , a corporation organized and existing under the laws of the State of , and duly authorized to transact business in the State of Louisiana, as surety, who declared that having taken cognizance of this Contract and of the Construction Documents mentioned herein, he hereby in his capacity as its Attorney in Fact obligates his said company, as Surety for
(The remainder of this page is intentionally blank.)
the said Contractor, unto the said Owner, up to the sum of _______________Dollars ($). By issuance of this bond, the surety acknowledges they are in compliance with R.S. 38:2219.
The condition of this performance and payment bond shall be that should the Contractor herein not perform the Contract in accordance with the terms and conditions hereof, or should said Contractor not fully indemnify and save harmless the Owner, from all cost and damages which he may suffer by said Contractor's non-performance or should said Contractor not pay all persons who have and fulfill obligations to perform labor and/or furnish materials in the prosecution of the work provided for herein, including by way of example workmen, laborers, mechanics, and furnishers of materials, machinery, equipment and fixtures, then said Surety agrees and is bound to so perform the Contract and make said payment(s).
Provided, that any alterations which may be made in the terms of the Contract or in the work to be done under it, or the giving by the Owner of any extensions of time for the performance of the Contract, or any other forbearance on the part of either the Owner or the Contractor to the other shall not in any way release the Contractor or the Surety from their liability hereunder, notice to the Surety of any such alterations, extensions or other forbearance being hereby waived.
The Contractor agrees to abide by the requirements of the following as applicable: Title VI of the Civil Rights Act of 1964 and Title VII of the Civil Rights Act of 1964, as amended by the Equal Opportunity Act of 1972, Federal Executive Order 11246 as amended, the Federal Rehabilitation Act of 1973, as amended, the Vietnam Era Veteran's Readjustment Assistance Act of 1974, Title IX of the Education Amendments of 1972, the Age Discrimination Act of 1975, the Fair Housing Act of 1968 as amended, and Contractor agrees to abide by the requirements of the Americans with Disabilities Act of 1990.
Contractor agrees not to discriminate in its employment practices, and will render services under this Contract without regard to race, color, religion, sex, sexual orientation, national origin, veteran status, political affiliation, disability, or age in any matter relating to employment. Any act of discrimination committed by Contractor, or failure to comply with these statutory obligations when applicable shall be grounds for termination of this Contract.
In Witness whereof, the parties hereto on the day and year first above written have executed this agreement in seven (7) counterparts, each of which shall, without proof or accountancy for the other counterparts, be deemed an original thereof.
CPRA WITNESSES: COASTAL PROTECTION AND
RESTORATION AUTHORITY
BY: _______________________________
Print Micheal Hare, Executive Director
Signature
CONTRACTOR WITNESSES: Contractor Name
______________________________ BY: _______________________________
Print ______________________________ Name: _____________________________ Signature Title: ______________________________
SURETY WITNESSES:
_______________________________ SURETY:____________________________
_______________________________ BY:_________________________________
Signature ATTORNEY IN FACT
Print ADDRESS:___________________________
TELEPHONE NUMBER:
PARISH OF Cameron
PROJECT NO. CS-004A
NAME: Levee Scour – Emergency Shoreline Protection
A F F I D A V I T
Before me, the undersigned authority, duly commissioned and qualified within and for the State and Parish aforesaid, personally came and appeared __________________________ representing who, being by me first duly sworn deposed and said that he has read this affidavit and does hereby agree under oath to comply with all provisions herein as follows:
PART I.
Section 2224 of Part II of Chapter 10 of Title 38 of the Louisiana Revised Statutes, as amended.
(1) That affiant employed no person, corporation, firm, association, or other organization, either directly or indirectly, to secure the public contract under which he received payment, other than persons regularly employed by the affiant whose services in connection with the construction, alteration or demolition of the public building or project or in securing the public contract were in the regular course of their duties for affiant; and
(2) That no part of the Contract price received by affiant was paid or will be paid to any person, corporation, firm, association, or other organization for soliciting the Contract, other than the payment of their normal compensation to persons regularly employed by the affiant whose services in connection with the construction, alteration or demolition of the public building or project were in the regular course of their duties for affiant.
PART II.
Section 2190 of Part I of Chapter 10 of Title 38 of the Louisiana Revised Statutes, as amended.
That affiant, if an architect or engineer, or representative thereof, does not own a substantial financial interest, either directly or indirectly, in any corporation, firm, partnership, or other organization which supplies materials for the construction of a public work when the architect or engineer has performed architectural or engineering services, either directly or indirectly, in connection with the public work for which the materials are being supplied.
For the purposes of this Section, a "substantial financial interest" shall exclude any interest in stock being traded on the American Stock Exchange or the New York Stock Exchange.
That affiant, if subject to the provisions of this section, does hereby agree to be subject to the penalties involved for the violation of this section.
AFFIANT
SWORN TO AND SUBSCRIBED BEFORE ME THIS DAY OF , 2026.
NOTARY
Printed Name:__________________________________
Bar Roll/Notary No.:_____________________________
My Commission expires:__________________________
PART I GENERAL PROVISIONS
GP-1 DEFINITION OF TERMS
Whenever used in the Bidding Requirements or Contract Documents and printed with initial capital letters, the terms listed below will have the meanings indicated which are applicable to the singular or plural thereof. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs and the titles of other documents or forms.
Unless stated otherwise in the Contract Documents, words or phrases which have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning.
a. Acceptance: A written approval from the Engineer which certifies that specific items of work in the Contract have been completed and/or obligations have been fulfilled by the Contractor.
b. Addenda: Those written or graphic documents which are issued prior to opening of Bids in accordance with the Bidding Requirements and clarify or change the bidding requirements or the proposed Contract Documents.
c. Application of Payment: That form which is used by the Contractor to request partial and final payment and is deemed acceptable to the Owner. It shall be accompanied by any supporting documentation required by the Contract Documents.
d. A.S.T.M.: American Society for Testing and Materials.
e. Bid: An offer or proposal submitted on the prescribed form setting forth the prices for the Work.
f. Bidder: The person, association of persons, firm, or corporation submitting a proposal for the Work.
g. Bidding Requirements: The Advertisement for Bids, Instructions to Bidders, Form of Bid Security, if any, and Bid Form with any supplements.
h. Change Order: A written order which is submitted to the Contractor, signed by the Owner, and authorizes an addition, deletion, or revision in the Work, or an adjustment in the contract price or the contract time issued after the effective date of the Contract.
i. Claim: A written demand or assertion by Owner or Contractor seeking an adjustment of Contract Price or Contract Times, or both or other relief with respect to the terms of the Contract.
j. Contract: The written agreement between the Owner and the Contractor which defines the work to be completed and shall be understood to also include all Contract Documents.
k. Contract Documents: The Contract, all addenda which pertains to the Contract Documents, Bid Documents and specified Attachments accompanying the Bid and any post-bid documentation submitted prior to the Notice of Award, Contractor’s Bid when attached as an exhibit to the Agreement, the Bonds (Bid and Performance/Payment), General Provisions, Special Provisions, Technical Specifications, Plans, and all Field or Change Orders issued after the execution of the Agreement. Shop Drawings and other submittals by the Contractor are not
l. Contract Price: The moneys payable by the Owner to the Contractor for the Work in accordance with the Contract Documents as stated in the Contract.
m. Contract Time: The number of calendar days specified in the Contract for completion of the Work, together with any extensions authorized through change orders.
n. Contractor: The person, association of persons, firm, or corporation entering into the duly awarded Contract.
o. Contracting Agency: The State of Louisiana, Coastal Protection and Restoration Authority (CPRA).
p. Day: When any period of time is referred to in the Contract Documents using days, it will be computed to exclude the first day and include the last day of such period.
If the last day of any such period falls on a Saturday, Sunday, or a legal holiday, that day will be omitted from the computation. A calendar day is measured as twenty-four (24) hour period starting at midnight and ending the following midnight.
q. Design Report: A written report by the Engineer which provides the design methodology for the Work.
r. Effective Date of the Contract: The date indicated in the Contract on which it becomes effective.
s. Engineer: The State of Louisiana, Coastal Protection and Restoration Authority, or its designee.
t. Equipment: All machinery, implements, and power-tools, in conjunction with the necessary supplies for the operation, upkeep, maintenance, and all other tools and apparatuses necessary for the proper construction and acceptable completion of the Work.
u. Extension of Contract: Any extension of time for completion of Work beyond the Contract Time which is granted by the Owner, recommended by the Engineer and approved by the Coastal Protection and Restoration Authority in the form of a Change Order.
v. Federal Sponsor: The federal agency which has been tasked, if applicable, to manage the implementation of the project.
w. Field Order: A written order issued by the Engineer which requires minor changes in the Work but which does not involve a change in the Contract Price or Contract Time.
x. Laboratory: The firm, company, or corporation which is used to test materials and is approved for use by the Engineer.
y. Laws and Regulations; Laws or Regulations: Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction.
z. Materials: Any substance used in the Work to build structures, but does not include material used in false work or other temporary structures not incorporated in the Work.
aa. Milestone: A principal event specified in the Contract Documents relating to an intermediated completion date or time prior to the Contract Times.
bb. Notice of Award: A written notice to the successful Bidder stating that the Bid has been accepted by the Owner and that the successful Bidder is required to execute the Contract and furnish the Payment and Performance Bond and Non-Collusion Affidavit.
cc. Notice to Proceed: The written notice to the Contractor by the Owner which provides the starting date for the Contract Time.
dd. Owner: The Owner is the State of Louisiana (State) which acts through the Contracting Agency.
ee. Performance and Payment Bond: The approved form of security furnished by the Contractor and Surety for the faithful performance of the Work, and the payment for all labor, materials, and/or obligations incurred by the Contractor in the prosecution thereof.
ff. Plans: That part of the Contract Documents prepared or approved by the Engineer which graphically shows the scope, intent, and character of the Work to be completed by the Contractor.
gg. Project Site: The location where the Work is to be performed as stated in the Contract Documents.
hh. Resident Project Representative: An authorized representative of the Engineer who is responsible to inspect the Work and materials furnished by the Contractor.
ii. Right-of-way: That entire area reserved for constructing, maintaining, and protecting the proposed improvement, structures, and appurtenances of the Work.
jj. Samples: Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portions of the Work will be judged.
kk. Shop Drawings: All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for the Contractor and submitted by the Contractor to illustrate some portion of the Work to be performed.
ll. Specifications: That part of the Contract Documents consisting of written technical descriptions of materials, equipment, systems, standards, and workmanship as applied to the work to be performed and certain administrative details applicable thereto.
mm. State: The State of Louisiana.
nn. Structures: Bridges, plugs, weirs, bulkheads, berms, dams, levees, and other miscellaneous construction encountered during the Work and not otherwise classified herein.
oo. Subcontractor: Any person, association of persons, firm, or corporation who contracts with the Contractor to perform any part of the project covered by the Contract.
pp. Submittals: Certificates, samples, shop drawings, and all other project data which are submitted to the Engineer in order to verify that the correct products will be installed on the project.
qq. Successful Bidder: The lowest responsive and responsible Bidder whom the Owner makes an award.
rr. Special Provisions: That part of the Contract Documents which amends or supplements these General Provisions.
ss. Surety: The corporate body, licensed to do business in Louisiana, bound with and for the Contractor’s primary liability, and engages to be responsible for payment of all obligations pertaining to acceptable performance of the Work contracted.
tt. Temporary Structures: Any non-permanent structure required while engaged in the prosecution of the Contract.
uu. Work: All work specified herein or indicated on the Plans.
vv. Work Plan: A written plan by the Contractor that details how the Work will be provided including layout drawings, projected schedule (Initial Progress Schedule), and a list of labor hours, materials, and equipment.
GP-2 BID REQUIREMENTS
The Contract and Bonds which govern the Work shall be performed in accordance with the Plans, Specifications, and the Louisiana Standard Specifications for Roads and Bridges, 2016 edition. The Bidder understands that all quantities for performing the Work have been estimated by the Engineer, and that the Bid shall be the sum of the quantities multiplied by their respective unit rates. The Contract shall be awarded by the Owner through a comparison of all bids. It is the responsibility of each Bidder before submitting a Bid to:
2.1. Examine the Bidding Documents including the Plans and Specifications and any Addenda or related data identified in the Bidding Documents;
2.2. Visit the Project Site to become familiar with the local conditions if they are believed to affect cost, progress, or the completion of the Work;
2.3. Become familiar and satisfied with all federal, state, and local Laws and Regulations that may affect cost, progress, or the completion of the Work;
2.4. Study and correlate all information known to the Bidder including observations obtained from Bidder’s visits, if any, to the Project Site, with the Bidding Documents;
2.5. Submit a written notice to the Engineer within three (3) days regarding any conflicts, errors, ambiguities, or discrepancies discovered in the Bidding Documents and confirm that the written resolution thereof by the Engineer is acceptable to the Bidder; and
2.6. Determine that the Bidding Documents are generally sufficient to convey an understanding of all terms and conditions for completing the required Work.
The submission of a Bid will constitute an incontrovertible representation that the Bidder has complied with every requirement of these Specifications. The Bidder shall comply with all other requirements specified in the Advertisement For Bids and the Instruction To Bidders.
GP-3 AVAILABILITY OF PLANS AND SPECIFICATIONS
One (1) set of Plans and Specifications shall be furnished to each Bidder. Three (3) sets of the Plans and Specifications shall be furnished to the Contractor upon award of the Contract. Additional sets may be furnished to the Contractor upon request from the Coastal Protection and Restoration Authority, 150 Terrace Avenue, Suite 100, Baton Rouge, Louisiana 70802.
GP-4 LAWS, REGULATIONS, STANDARDS, SPECIFICATIONS, AND CODES
Bidders are required to become familiar and remain in compliance with all Federal, State, and local laws, ordinances, and regulations and all orders and decrees of bodies or tribunals having any jurisdiction or authority which may affect those employed for the execution of the Work or which may affect the conduct of the Work. The Contractor shall indemnify the Owner and its representatives against any claim or liability arising from all violations of any laws, bylaws, ordinances, codes, regulations, orders, or decrees, whether by the Contractor or by the Contractor’s employees. The filing of a bid will be presumptive evidence that the Bidder has complied with this requirement. The Owner will not be responsible for any inaccurate interpretations or conclusions drawn by the Contractor from information and documentation provided by the Owner.
References to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws and Regulations, whether such reference be specific or by implication, may not be in effect at the time of opening the Bids (or on the Effective Date of the Contract if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. No provision of any such standard, specification, manual, or code, or any instruction of a supplier shall be effective to change the duties or responsibilities of the Owner or Engineer, or any of their Subcontractors, consultants, agents, or employees from those set forth in the Bid Documents. No such provision shall be effective to assign to the Owner or Engineer, or any of their consultants, agents, or employees any duty or authority to supervise or direct the perfor-mance of the Contractor’s obligations or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents.
The obligations imposed by these specifications are in addition to and are not to be construed in any way as a limitation of any rights available to the Engineer or Owner which are otherwise imposed by any laws or regulations or other provisions within the
The Contractor shall abide by laws set forth in the Davis-Bacon Act of 1931 which states that all laborers and mechanics employed by recipients, the recipient’s contractors, or subcontractors on this project shall be paid wages at rates no less than those prevailing on projects of a character similar in the locality as determined by the Secretary of Labor in accordance with Subchapter IV of Chapter 31 of Title 40 United States Code.
Additionally, with respect to the labor standards specified in this section, the Secretary of Labor shall have the authority and functions set forth in Reorganization Plan Number 14 of 1950 (64 Stat. 1267; 5 U.S.C. App.) and The Copeland Act of Title 40 (40 U.S.C.
§ 3145). Prevailing Wage Determination Schedules, as determined by the United States Department of Labor, are provided in the Appendix. Prevailing Wage Determination Schedules are subject to modification by the United States Department of Labor. The Contractor is responsible for utilizing the most current Prevailing Wage Determination Schedule. These documents can be downloaded from the following link:
http://www.wdol.gov/dba.aspx#3. Modifications to Prevailing Wage Determination Schedules shall be effective if received (or posted) no less than 10 days prior to bid opening.
GP-5 PRE-BID CONFERENCE AND SITE VISIT
A Pre-Bid Conference and/or Job Site Visit may be held at the location and on the date provided in the Advertisement For Bids. If the Pre-Bid Conference and/or Job Site Visit is stated in the Advertisement for Bids to be a MANDATORY Pre-Bid Conference and/or MANDATORY Job Site Visit, bids shall be accepted only from those bidders who attend the Pre-Bid Conference and/or Job Site Visit in its entirety. Failure to attend a mandatory Pre-Bid Conference and/or mandatory Job Site Visit in its entirety will result in a null or void Bid.
All questions shall be in writing and faxed or emailed to the Coastal Protection and Restoration Authority contact person listed in the Advertisement For Bids after the Pre- Bid Conference and by the due date announced at the Pre-Bid conference. In order to ensure adequate response time, all questions and/or requests for clarification or interpretation of the Bid Documents should be received by the Coastal Protection and Restoration Authority at least seven days prior to the date for receipt of bids. Oral statements will not be binding or legally effective. The Coastal Protection and Restoration Authority will issue addenda in response to all questions arising at the Pre- Bid Conference and site visit to all prospective Bidders on record. All prospective
Bidders on record may contact the Coastal Protection and Restoration Authority contact person for any additional information.
GP-6 NOTICE OF AWARD
The Owner, or its designated bidding agent, shall provide written notice to the Successful Bidder stating that the Owner will sign and deliver the Contract upon compliance with the conditions enumerated therein and within the time specified.
GP-7 NOTICE TO PROCEED AND CONTRACT TIME
The Contractor shall start the Work and begin the Contract Time on the dates provided in the Notice to Proceed. The Work shall be conducted using sufficient labor, materials, and equipment as necessary to ensure completion within the Contract Time. The Contract Time for completion of the Base Bid for the Work is provided in the Instructions To Bidders, unless an extension is granted to the Contract Time as specified in GP-44.
If the Bid contains an Alternate Bid(s), and the Alternate Bid(s) is awarded and included in the Contract, the Contract Time associated with the Alternate Bid(s) will be as provided in the Instructions To Bidders.
Unless otherwise noted in the Contract Documents, Contract Time will be on a calendar day basis. Contract Time shall consist of the number of calendar days stated in the Instructions To Bidders and the Contract beginning with the date noted in the written Notice to Proceed, including Saturdays, Sundays, holidays and non-work days.
The following table defines the monthly anticipated adverse weather days that are expected to occur during the Contract Time and will constitute the baseline monthly weather time for evaluations. The schedule is based upon National Oceanic and Atmospheric Administration (NOAA) or similar data for the regional geographic area.
Monthly Anticipated Adverse Weather Calendar Days
Jan. Feb. Mar. Apr. May Jun. Jul. Aug
Sep. Oct. Nov
Dec.
5 5 4 4 4 5 7 7 5 3 3 4
Adverse weather days must prevent Work for fifty percent (50%) or more of the work day and delay work critical to the timely completion of the project. The number of actual adverse weather days shall be calculated chronologically from the first to the last day of each month.
If adverse weather conditions are the basis for a claim for additional time, the Contractor shall document that weather conditions had an adverse effect on the scheduled construction. An increase in Contract Time due to weather due to weather shall not be cause for an increase in the contract sum.
GP-8 WORK PLAN
The Contractor shall develop a written Work Plan which accounts for all of the construction activities required by the Contract Documents. The Work Plan shall include a list of the individual construction tasks to be completed and the estimated dates for beginning and completing the tasks. It shall also include all other items which are applicable to completing the Work such as, but not limited to, the following:
a. Typical report form for the Bi-Weekly Progress Meeting;
b. Typical form for Daily Progress Report;
c. Hurricane and Severe Storm Plan;
d. Site-specific Health and Safety Plan;
e. The delivery method and source(s) of all construction materials (company or producer name, mailing and physical address, phone number, and name of contact person).
f. The personnel, material, subcontractors, fabricators, suppliers, types of equipment, and equipment staging areas the Contractor proposes to use for construction;
g. Shop drawings, test results, and sample submittals;
h. Survey layout and stakeout;
i. All supplemental items specified in the Special Provisions.
The Work Plan shall be submitted to the Engineer prior to the Pre-Construction Conference by the date provided in the Special Provisions. The Engineer shall review the Work Plan and have the Contractor make any necessary revisions prior to acceptance of the plan. No payment for mobilization will be made until the Work Plan has been accepted by the Engineer.
GP-9 PROGRESS SCHEDULE
The Contractor shall develop a written Progress Schedule which provides for an orderly progression of the Work, submittals, tests, and deliveries in order to complete the Work within the specified Milestones and Contract Time. All of the items listed in the Work Plan shall be integrated into the Progress Schedule. The format of the schedule shall be composed using Microsoft Project®, or any other software deemed acceptable by the Engineer. It shall be updated weekly by the Contractor, at a minimum. The Progress Schedule shall also include, but not be limited to the following:
a. All of the elements in the Work Plan, including updates;
b. A work order issued from Louisiana One Call ordering all their subscribers in the project area to mark their utilities;
c. A telephone log verifying that all property owners and utilities have been contacted.
This log should list the time, date, and names of the personnel representing the property owners, utilities, and Contractor;
The Progress schedule must reflect the anticipated adverse weather delays described in GP-7 on all weather dependent activities.
The Progress Schedule shall be submitted to the Engineer prior to the Pre-Construction Conference by the date provided in the Special Provisions. The Engineer shall perform a review and have the Contractor make any necessary revisions prior to acceptance of the schedule. Acceptance will not impose responsibility on the Owner or Engineer for the sequencing, scheduling, or progression of the Work. The Contractor is fully responsible for progression of the Work in order to maintain compliance with the Progress Schedule and Contract Time.
GP-10 DAILY PROGRESS REPORTS
The Contractor shall record the following daily information on Daily Progress Reports:
a. Date and signature of the author of the report;
b. Dollar amount of all bid items that are fabricated, installed, backfilled, pumped, constructed, damaged, replaced, etc. The amount of material shall be expressed in the units stated in the bid;
c. Field notes of all surveys;
d. Notes on all inspections;
e. Details of Health and Safety meetings;
f. A brief description of any Change Orders, Field Orders, Claims, Clarifications, or Amendments;
g. Condition of all navigation aids (i.e., warning signs, lighted marker buoys) and any repairs performed on them;
h. Weather conditions (adverse weather day, wind speed and direction, temperature, wave height, precipitation, etc.);
i. The amount of time lost to severe weather or personnel injury, etc;
j. Notes regarding compliance with the Progress Schedule;
k. Visitor log (Instructions for format will be furnished by the Field Engineer).
The daily progress reports shall be submitted to the Engineer at the Bi-Weekly Progress Meetings specified in GP-13 in both hard copy and digital format (Adobe Acrobat® Format, or approved equal). The typical form for Daily Progress Reports shall be developed by the Contractor and incorporated into the Work Plan.
GP-11 HURRICANE AND SEVERE STORM PLAN
The Contractor shall develop and maintain a written Hurricane and Severe Storm Plan.
The Plan shall include, but not be limited to, the following:
a. What type of actions will be taken before storm strikes at the Project Site. The plan should specify what weather conditions or wave heights will require shutdown of the Work and removal of equipment, personnel, etc.
b. Notes from continuous monitoring of NOAA marine weather broadcasts and other local commercial weather forecasts.
c. Equipment list with details on their ability to handle adverse weather and wave conditions.
d. List of safe harbors or ports and the distance and travel time required to transfer equipment from the Project Site.
e. Hard copies of any written approvals or operations schedules associated with the use of the safe harbors or ports.
f. Method of securing equipment at the safe harbors or ports.
g. List of tug boats and work boats and their respective length, horsepower, etc. which will adequately transfer the equipment to safe harbor or port under adverse weather conditions.
h. Methods which will be used to secure equipment left onsite during adverse weather
i. Evacuation or immediate reaction plans to be taken by personnel for sudden storm occurrences.
j. Operations procedures which will be used to secure critical dredging equipment such as spuds, swing wires, anchor wires, or tugs during adverse weather
k. Communications protocol with local law enforcement and fire and rescue agencies.
The Contractor shall incorporate the Hurricane and Severe Storm Plan into the Work Plan. The Owner and Engineer are not responsible for the adequacy of this plan.
GP-12 HEALTH AND SAFETY PLAN AND INSPECTIONS
The Contractor shall develop and maintain a written Health and Safety Plan which allows the Work to be performed in compliance with all applicable laws, ordinances, rules, and regulations of any government agency having jurisdiction over the safety of personnel or property. This includes maintaining compliance with the Code of Federal Regulations, Title 29, Occupational Safety and Health Administration (OSHA) and all applicable Health and Safety Provisions of the State of Louisiana.
The Contractor shall institute a daily inspection program to assure that the requirements of the Health and Safety Plan are being fulfilled. Inspections shall include the nature of deficiencies observed, corrective action taken or to be taken, location of inspection, date, and signature of the person responsible for its contents. The results of the inspections shall be recorded on Daily Progress Reports and kept at the Project Site during the Work.
The Contractor shall incorporate the Health and Safety Plan into the Work Plan. The Owner and Engineer are not responsible for the adequacy of this plan.
GP-13 PROGRESS MEETINGS AND REPORTS
The Engineer shall schedule meetings to review the progress of the Work, coordinate future efforts, discuss compliance with the Progress Schedule and resolve miscellaneous problems. The Engineer or Resident Project Representative, Contractor, and all Subcontractors actively working at the Project Site shall attend each meeting.
Representatives of suppliers, manufacturers, and other Subcontractors may also attend at the discretion of the Contractor. The Contractor shall record the details of each meeting in a Progress Report. The format of this report shall be developed by the Contractor, approved by the Engineer, and included in the Work Plan. The progress meetings and reports shall be scheduled according to the Special Provisions.
GP-14 PRE-CONSTRUCTION CONFERENCE
A Pre-Construction Conference shall be held by the Contractor, Owner, Engineer, local stakeholders, and other appropriate personnel prior to starting construction on the date specified in the Special Provisions. This conference shall serve to establish a mutual understanding of the Work to be performed, the elements of the Progress Schedule and Work Plan, expectations for bi-weekly progress meetings, the Plans and Specifications, processing Applications for Payment, and any other items of concern. If any subcontractors are not present, another pre-construction conference will be required.
GP-15 CONTRACT INTENT
The Bid Documents are complementary; what is called for by one is as binding as if called for by all. Clarifications and interpretations or notifications of minor variations and deviations of the Contract Documents will be issued by Engineer as provided in these Specifications. Any labor, documentation, services, materials, or equipment that may reasonably be inferred from the Bid Documents or from prevailing custom or trade usage as being required to produce the intended result will be provided at no additional cost to the Owner.
GP-16 ENGINEER AND AUTHORITY OF ENGINEER
The Engineer will be the designated representative of the Owner, the initial interpreter of the Contract Documents and the judge over acceptability of all the Work. Claims, disputes, and other matters relating to the acceptability of the Work, performance by the Contractor or the interpretation of the requirements of the Contract Documents must be submitted to the Engineer in writing. Upon written request from the Contractor, the Engineer shall issue written clarifications or interpretations which are consistent with the overall intent of the Contract Documents. Such written clarifications and interpretations will be binding on the Owner and the Contractor. Either the Owner or the Contractor may make a Claim if a written clarification or interpretation justifies an adjustment in the Contract Price or Contract Times.
The Engineer has the authority to suspend the Work in whole or in part due to failure of the Contractor to correct conditions unsafe for workmen or the general public, carry out provisions of the Contract, perform conformance work, or to carry out orders. The Engineer shall submit a written order to the Contractor for work which must be suspended or resumed. Nothing in this provision shall be construed as establishing responsibility on the part of the Engineer for safety which is the responsibility of the Contractor.
The Engineer or Resident Project Representative shall keep a daily record of weather and flood conditions and may suspend the Work as deemed necessary due to periods of unsuitable weather, conditions considered unsuitable for execution of the Work, or for any other condition or reason deemed to be in the public interest.
GP-17 CONFORMITY WITH PLANS AND SPECIFICATIONS
All work and materials involved with the Work shall conform with the lines, grades, cross sections, dimensions, and other requirements shown on the Plans or indicated in these Specifications unless otherwise approved by the Engineer.
GP-18 CLARIFICATIONS AND AMENDMENTS TO CONTRACT DOCUMENTS
The Contract Documents may be clarified or amended by the Engineer to account for additions, deletions, and revisions to the Work after the Effective Date of the Contract.
The clarifications and amendments shall be addressed by either a Change Order…