This document is a Notice to Proceed with Construction issued by the Florida Wildlife Commission (FWC) to Westwind Contracting, located in Pembroke Park, FL. The notice is specific to the Dinner Island South Berm Project, identified by FWC Purchase Order No. 24204 and project number 7310.023. Michael Cottingham is designated as the FWC Contract Manager, and the document authorizes Westwind Contracting to mobilize and commence construction activities.
The project timeline establishes a Notice to Proceed date of March 31, 2025, with a Substantial Completion deadline of August 28, 2025 (150 days from the Notice to Proceed), and a Final Completion date of September 27, 2025 (30 calendar days after substantial completion). No specific contract value or pricing details are provided in this document. The Notice to Proceed serves as a formal authorization for Westwind Contracting to begin work on the construction project, subject to the conditions outlined in the contract documents.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-770000-24204.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Notice to Proceed with Construction
March 31, 2025
Rodrigo Polizzi Westwind Contracting 3799 W. Hallandale Beach Blvd.
Pembroke Park, FL 33023
RE: FWC PO No 24204 Dinner Island South Berm Project 7310.023
Notice to Proceed with Construction
Dear Mr. Polizzi:
Please consider this as your formal NOTICE TO PROCEED WITH CONSTRUCTION. You may now mobilize on site and proceed with construction subject to the conditions of the contract.
The official commencement date for this project will be the date of this Notice to Proceed (NTP) and subsequent Substantial Completion and Final Completion dates will be as established in the contract documents.
Notice to Proceed - 03/31/2025 Substantial Completion - 150 days from NTP with Construction 08/28/2025 Final Completion - 30 calendar days from substantial 09/27/2025
Contract Manager for FWC will be Michael Cottingham
Sincerely, Michael Cottingham, FWC Contract Manager
3/28/2025
Notice to Proceed - 03/31/2025