This document is a Construction Contract Change Order (CO) between the Florida Fish and Wildlife Conservation Commission (FWC), located in Tallahassee, FL, and Chapel Branch & Lagniappe LLC, based in Chipley, FL. The change order is associated with the Escribano Point Road Improvements project, identified by FWC Contract No. 23261 and Solicitation Number 23/24-61C.
The change order details modifications to the original contract, specifically involving the removal of grating and cross bracing, and the installation of strongbacks with re-installation and welding of grating according to revised structural drawings dated 12/11/2024. The change results in a cost increase of $53,837.20, bringing the total contract amount from $1,099,359.17 to $1,153,196.37. The project period remains unchanged at 300 days, with the substantial completion date still set for 6/3/2025. The change order was signed by Tony Lagman from Chapel Branch & Lagniappe LLC on 2/13/25 and by Jessica Crawford, Chief of Staff for the Florida Fish and Wildlife Conservation Commission, on 3/25/2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-770000-19159-TA15CO1.pdf | ||
| CN-770000-23261-CO1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revised: 3.19.2024 FWC 24/25 Terms & Conditions
EXHIBIT 11: CONSTRUCTION CONTRACT CHANGE ORDER (CO)
Change Order Number: __________ FWC Contract No. #
Solicitation Number: ______________________ Project Title: ________________________________
OWNER
Name: _______________________________________
Address: ____________________________________
Phone: ______________________________________
CONTRACTOR
Name: ______________________________________
Address: ____________________________________
Phone: ______________________________________
Description of Change. (Attach additional pages if required) Decrease Increase
Subtotal
Total (+/-)
Notice to Proceed with Construction Date: __________________ Contract Information
Project Period # of Days Date Original Contract Sum: $_______________
Original Substantial Completion: Previously Approved CO: $_______________
Present Substantial Completion: Present Contract Amount: $_______________
Current change will add/deduct (+/-): This CO will add/deduct (+/-): $_______________
New Substantial Completion: New Contract Sum: $_______________
CO2
23/24-61C Escribano Point Road Improvements 7280.001
Florida Fish and Wildlife Conservation Commission Chapel Branch & Lagniappe LLC
1875 East Orange Avenue, Tallahassee FL 32311 805 Main Street Chipley, FL 32428
850-661-7016 850-209-9873
Remove Grating & Cross Bracing Install Strongbacks, Re-Install and weld grating per structural drawings revised 12/11/2024.
13,856.00 39,981.20
53,837.20
53,837.20
300 6/3/2025
300 6/3/2025
300 6/3/2025
23261
8/7/2024
1,062,408.41
39,950.76
1,099,359.17
53,837.20
1,153,196.37
This Change Order is an amendment to the Contract between the Contractor and the Owner, and all contract provisions shall apply unless specifically exempted. The amount and time change designated are the maximum agreed to by both the Owner and the Contractor for this change. In consideration of the foregoing adjustments in contract term and contract sum, the Contractor hereby releases Owner from all claims, demands or causes of action arising out of the transactions, events and occurrences giving rise to this Change Order. This written Change Order is the entire agreement between Owner and Contractor with respect to this Change Order. No other agreements or modifications shall apply to this contract amendment unless expressly provided herein. This Change Order represents final agency action.
Contractor Signature Commission Signature
Chapel Branch & Lagniappe LLC Florida Fish and Wildlife Conservation Commission
Contractor Signature Executive Director (or Designee) Signature
Print Name Print Name
Title Title
Date Date
Tony Lagman
Member
2/13/25
Jessica Crawford
Digitally signed by Jessica Crawford Date: 2025.03.25 10:04:31 -04'00'
Jessica Crawford
Chief of Staff
3/25/2025
| FWC 23261 CO2.pdf |
| EXHIBIT 11: CONSTRUCTION CONTRACT CHANGE ORDER (CO) |
| 23261 |
File details come from the government source that posted it. Updated .