This document is a Construction Contract Change Order (Change Order Number 1) for the Florida Fish and Wildlife Conservation Commission (FWC), involving Chapel Branch & Lagniappe LLC as the contractor. The project is titled "Escribano Point (Road Improvements)" and is associated with FWC Contract No. 23261 and Solicitation Number FWC 23/24-61C. The contract is located in Florida, with the owner's address in Tallahassee and the contractor based in Chipley.
The change order modifies the original contract by removing the original helical anchor design (grouted piles) and installing 350 NCHP to 50' instead. The financial impact increases the contract value by $36,950.76, bringing the new contract sum from $1,062,408.41 to $1,099,359.17. The project period remains 300 days, with the original and new substantial completion date set for 6/3/2025. The Notice to Proceed with Construction is dated 8/7/2024. The change order represents a final agency action and has been digitally signed by the contractor's owner and the Commission's Chief of Staff on 9/19/2024 and 10/1/2024 respectively.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-770000-19159-TA15CO1.pdf | ||
| CN-770000-23261-CO2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT 11: CONSTRUCTION CONTRACT CHANGE ORDER (CO)
Change Order Number: 1 _________ FWC Contract No. 23261
Solicitation Number: FWC 23/24-61C Project Title: ESCRIBANO POINT (ROAD
IMPROVEMENTS)
OWNER
Name: Florida Fish and Wildlife Conservation
Commission __________________________________
Address: 1875 East Orange Ave. Tallahassee, FL
32311 _______________________________________
Phone: 850-661-7016 __________________________
CONTRACTOR
Name: Chapel Branch & Lagniappe LLC
Address: 805 Main St
Chipley, Florida 32428 ________________________
Phone: (850) 209-9873 ________________________
Description of Change. (Attach additional pages if required) Decrease Increase
Remove Original Helical Anchor Design (Grouted Piles)
Install 350 NCHP to 50' 10/12/14 instead of grouted piles
$94,600.00
$131,550.76
Subtotal $94,600.00 $131,550.76
Total (+/-) $36,950.76
Notice to Proceed with Construction Date:
_8/7/2024_______________ Contract Information
Project Period # of Days Date Original Contract Sum: $1,062,408.41
Original Substantial Completion: 300 6/3/2025 Previously Approved
CO/Amendment:
$ 0
Present Substantial Completion: 6/3/2025 Present Contract Amount: $1,062,408.41
Current change will add/deduct
0 This CO will add/deduct (+/-): $36,950.76
New Substantial Completion: 6/3/2025 New Contract Sum: $1,099,359.17
This Change Order is an amendment to the Contract between the Contractor and the Owner, and all contract provisions shall apply unless specifically exempted. The amount and time change designated are the maximum agreed to by both the Owner and the Contractor for this change. In consideration of the foregoing adjustments in contract term and contract sum, the Contractor hereby releases Owner from all claims, demands or causes of action arising out of the transactions, events and occurrences giving rise to this Change Order. This written Change Order is the entire agreement between Owner and Contractor with respect to this Change Order. No other agreements or modifications shall apply to this contract amendment unless expressly provided herein. This Change Order represents final agency action.
Contractor Signature Commission Signature
Chapel Branch & Lagniappe LLC Florida Fish and Wildlife Conservation Commission
Contractor Signature Executive Director (or Designee) Signature
Print Name Print Name
Title Title
Date Date
Tony Lagman
Owner
09/19/2024
Jessica Crawford
Chief of Staff
10/1/2024
Tony Lagman
Digitally signed by Tony Lagman Date: 2024.09.19 09:24:34 -05'00'
Jessica Crawford
Digitally signed by Jessica Crawford Date: 2024.10.01 12:24:15 -04'00'