CN-770000-22287-CO1.pdf
PDF 181 KB Posted
- Contract number
- 22287
- Issued by
- Florida
About this file
This document is a Construction Contract Change Order (CO) for the Florida Fish & Wildlife Conservation Commission (FWC), involving BayHead Consulting Inc. as the contractor. The change order is associated with the Fisheating Creek Modular Home project, under solicitation number FWC 22/23-92C and contract number 22287, located in Tallahassee, Florida.
The change order details modifications to the original construction contract, including materials and labor for elevated decks and ADA access ramps. Specific changes include increasing the modular Finished Floor Elevation by 36", requiring a 36' ramp with three 5'x5' landings, increasing the porch roof by 102 square feet, and resizing structural members for aluminum canopies. The financial impact increases the contract sum by $86,023.61, bringing the total contract amount from $449,632.54 to $535,656.15. The project period has been extended, with the new substantial completion date set for 7/21/2024, adding 60 days to the original timeline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-770000-21145-PM4C1.pdf | ||
| CN-770000-22287-NTP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revised: 11.1.2022 FWC 22/23-92C Terms & Conditions Page 78
EXHIBIT 11: CONSTRUCTION CONTRACT CHANGE ORDER (CO)
Change Order Number: __________ FWC Contract No. #
Solicitation Number: FWC 22/23-92C Project Title: ________________________________
OWNER
Name: _______________________________________
Address: ____________________________________
Phone: ______________________________________
CONTRACTOR
Name: ______________________________________
Address: ____________________________________
Phone: ______________________________________
Description of Change. (Attach additional pages if required) Decrease Increase
Subtotal
Total (+/-)
Notice to Proceed with Construction Date: __________________ Contract Information
Project Period # of Days Date Original Contract Sum: $_______________
Original Substantial Completion: Previously Approved CO: $_______________
Present Substantial Completion: Present Contract Amount: $_______________
Current change will add/deduct
This CO will add/deduct (+/-): $_______________
New Substantial Completion: New Contract Sum: $_______________
Fisheating Creek Modular Home 7221.041
Florida Fish & Wildlife Conservation Commission
620 South Meridian Road, Tallahassee, FL 32399
850-922-6160
Bayhead Consulting Inc.
460 N. Franklin Street, Sebring, FL 33870
561-239-2733
Materials and Labor to construct elevated decks and ADA access ramp due to change in design in modular Finished Floor Elevation. Increase in total elevation change from FFE to landing of 36" which requires 36' or ramp with (3) 5'x5' landings. Increase in porch roof of 102 square feet. Increase in in size of structural members for aluminum canopies (porch and carport) to account for additional 36" of exposure. Redesign of associated porches and ramps multiple times due to ongoing changes.
$89,354.61
Deduct concrete form and pour for slab on grade porches. Deduct excavation for modular to be set into ground.
$5,429.14
Bond increase @ 2.5% of total change. $2,098.14
$91,452.75$5,429.14
$86,023.61
86,023.61
535,656.15
449,632.54
449,632.54
180 5/22/2023
60 7/21/2024
240 7/21/2024
222871
11/24/2023
This Change Order is an amendment to the Contract between the Contractor and the Owner, and all contract provisions shall apply unless specifically exempted. The amount and time change designated are the maximum agreed to by both the Owner and the Contractor for this change. In consideration of the foregoing adjustments in contract term and contract sum, the Contractor hereby releases Owner from all claims, demands or causes of action arising out of the transactions, events and occurrences giving rise to this Change Order. This written Change Order is the entire agreement between Owner and Contractor with respect to this Change Order. No other agreements or modifications shall apply to this contract amendment unless expressly provided herein. This Change Order represents final agency action.
Contractor Signature Commission Signature
BayHead Consulting, Inc Florida Fish and Wildlife Conservation Commission
Contractor Signature Executive Director (or Designee) Signature
Print Name Print Name
Title Title
Date Date
Revised: 11.1.2022 FWC 22/23-92C Terms & Conditions Page 79
Jessica Crawford
Chief of Staff
6/19/2024
Jessica
Crawford
Digitally signed by Jessica
Crawford
Date: 2024.06.19
10:13:12 -04'00'
Gregory W. Griffin
Digitally signed by Gregory W.
Griffin
DN: C=US,
E=ggbhci@gmail.com, O="BayHead Consulting, Inc", CN=Gregory W. Griffin Date: 2024.06.09 16:30:51-04'00'
File details come from the government source that posted it. Updated .