About this file
This document is a Supplemental Agreement (Change Order No. 003) between the Florida Department of Transportation (FDOT) and Community Asphalt Corporation for a construction contract (Contract No. E4P20) located in Palm Beach County. The agreement is part of a county-wide project with Financial Project ID 229833-7-52-01, and involves the State of Florida, with Travelers Casualty and Surety Company of America listed as the surety.
The supplemental agreement authorizes new pay items for installing a concrete sidewalk and American Disabilities Act (ADA) ramps on the north side of Lake Worth Road, necessitated by a conflict with underground gas utilities. The additional work is being added under a "Push-Button Contract" with no increase to the original contract amount of $600,000.00. The change order includes several new line items such as a soil tracking prevention device, reinforcement steel, inlet protection systems, and an inlet type J structure bottom, with individual item costs ranging from $80.52 to $11,089.10. The work is requested by the Traffic Operations Division and is based on Work Document Number PBC-3-2014 dated August 28, 2014.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-E4P20-00030000.pdf | ||
| CN-550000-E4P20-00040000.pdf | ||
| CN-550000-E4P20-00060000.pdf | ||
| ContractBudgetExport.csv | CSV file | |
| ContractDeliverablesExport.csv | CSV file | |
| CN-550000-E4P20-00090000.pdf | ||
| CN-550000-E4P20-00100000.pdf | ||
| CN-550000-E4P20-00110000.pdf | ||
| CN-550000-E4P20-00020000.pdf | ||
| CN-550000-E4P20-00050000.pdf | ||
| CN-550000-E4P20.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RICK SCOTT
GOVERNOR
Centennial
FD01
...1101 1.;7---r20;5
Florida Department of Transportation 3400 West Commercial Boulevard Fort Lauderdale, FL 33309-3421
JIM BOXOLD
SECRETARY
MEMORANDUM
Date: Friday, February 13, 2015
TO: Contract Payment Section M/S 42
FROM: Becky B. Johnson, District 4 Construction Contracts Administrator
COPIES: File
SUBJECT: TRANSMITTAL OF APPROVED SUPPLEMENTAL AGREEMENT
Please find enclosed the approved Supplemental Agreement/Change Order 3 dated 2/12/2015 in the amount of $0.00 and 0 days for the following project:
| Financial Project No.: | 22983375201 |
| Federal Project No.: | na |
| Contract No.: | E4P20 |
| County: | Palm Beach |
Scanned by:
Attributed by:
Document#:
Executed By: "r•
(SEAL)
Contractor Signature
Printed Name Title Date
15-ate
(SEAL)
Surety
BY
Florida Licensed Insurance Agent Date
Executed By:
Secretary or Designee Si Printed Name Title
--24V/S ture arolyn Gish, P.E.
Date District Construction Engineer
Printed Name Date
91/, z_\\
Attorney ignat reDepartment of Transportation, Legal Review
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
SUPPLEMENTAL AGREEMENT
No. 003 Contract No.: E4P20
Road No(s). County-Wide Federal Aid Project No(s). N/A
700-010-45
CONSTRUCTION
04/11
Fin. Proj. ID 229833-7-52-01
This agreement entered into on "t-Cb • 121 2015 , such an agreement to be effective on the last date of execution by a party hereto, by and between the State of Florida Department of Transportation, "Department", and Community Asphalt Corporation., "Contractor", and Travelers Casualty and Surety Company of America, "Surety", the same being supplementary to Contract E4P20 by and between the parties aforesaid, dated 03/04/2014, for the construction or improvement of the road(s) and bridge(s) assigned the project number(s) shown above, in Palm Beach Count(y)(ies) Florida.
(1) The Department and the Contractor hereby amend this Contract as follows:
(Continued on Page 2 attached hereto and made a part hereof)
Revised Plan Sheet Nos. N/A
(2) The quantities to be paid shall be determined as provided in the Standard Specification, Edition of 2014.
The quantities so determined shall be paid at the unit prices stated on the attached sheets.
(3) It is further agreed that this supplemental agreement shall not alter or change in any manner the force and effect of the original Contract No. E4P20, including any previous amendments thereto, except insofar as the same is altered and amended by this supplemental agreement.
(4) The Department and the Contractor agree that the contract time adjustment and sum agreed to in the Supplemental Agreement constitute a full and complete settlement of the matters set forth herein, including all direct and indirect costs for equipment, manpower, materials, overhead, profit and delay relating to the issues set forth in the Supplemental Agreement. This settlement is limited to and applies to any claims arising out of or on account of the matters described and set forth in this Supplemental Agreement.
Granted Time this Agreement 0 Days
Net Change in Contract this Agreement: Increase $ 0.00 Decrease $ 0.00 No Change E
Approved By:
Secretary or Designee Signature Printed Name Eduardo Caballero, P.E.
Title Palm Beach Operations Engineer Date
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
SUPPLEMENTAL AGREEMENT
700-010-45
CONSTRUCTION
04/11
| Page 2 | of 4 | ||
| No. 003 | Contract No.: E4P20 | ||
| Road No(s). | County-Wide | Federal Aid Project No(s). | N/A |
| Fin. Proj. ID | 229833-7-52-01 |
(1) (continued):
To Provide New Pay Items to the Contract for the Installation of a Concrete Sidewalk and American Disabilities Act (ADA)
Ramps at the north side of Lake Worth Road. This additional work is necessary due to the discovery of a conflict with underground gas utilites at the referenced location and to complete Work Document Number PBC-3-2014, as requested by the Traffic Operations Division.
This is considered as a Push-Button Contract. Due to budgetary restrictions, this additional work will not increase the original contract amount of $600,000.00.
Rpt-ID: RCOCORPT
User: cn409we
Florida Date: 01/28/2015
Department of Transportation Page:A-of3-j c'-'711
Change Order Report
Contract ID: E4P20
Change Order Nbr: 003 Force Acct ID: 0
Change Order Type: Supplemental Aggreement
CO Description: To Add New Pay Items for Sidewalk & ADA Ramps-$0.00-PB
Zero Dollar Change Order: No
Project Nbr Itm Nbr Catg Item Code Unit Unit Price Bid Qty Prey Apprvd Qty Curr CO Qty Curr Apprvd Qty Amount of Change
22983375201 0051 0200 0104 15 EA $113.51 0 0 1 0 This Chng: $113.51
Prey Revised: $0.00 Item Description SOIL TRACKING PREVENTION DEVICE CO Item Description Add a New Pay Item for Mail Box, Furnish and Install
New Revised: $113.51 Supplemental Description) To Add a New Pay Item for Mail Box, Furnish & Install Bid Contract: $0.00 Supplemental Description2 (Non-Federal Participation) Net Change: $113.51
Pct Change:
22983375201 0136 0200 9999 3 LS $-14,040.69 0 0 1 0 This Chng: $-14,040.69
Item Description GENERIC CONTRACT CHANGE(S/M ONLY) CO Item Description Budgetary Ceiling Item-For Accounting Purposes Only
New Revised: $-14,040.69
| Supplemental Description) Budgetary Ceiling Item-For Accounting Purposes Only | Bid Contract: $0.00 |
| Supplemental Description2 (Non-Federal Participation) | Net Change: $-14,040.69 |
22983375201 0274 0200 0415 1 6 LB $37.00 0 0 68 0 This Chng: $2,516.00
Item Description REINF STEEL- MISCELLANEOUS CO Item Description To Add a New Pay Item for Reinforcement ctoal-hilicrallanani lc New Revised: $2,516.00 Supplemental Description) To Add a New Pay Item for Reinforcement Steel-Miscellaneous Bid Contract: $0.00 Supplemental Description2 (Non-Federal Participation) Net Change: $2,516.00
22983375201 0278 0200 0425 1543 EA $11,089.10 0 0 1 0 This Chng: $11,089.10
Item Description INLETS, DT BOT,TYPE D, J BOT, <10' CO Item Description To Add a New Pay Item for Inlet Type J Structure Bottom-CIP
New Revised: $11,089.10 Supplemental Description) To Add a New Pay Item for Inlet Type J Structure Bottom, Bid Contract: $0.00 Supplemental Description2 Cast-In-Place (Non-Federal Participation) Net Change: $11,089.10
Florida Rpt-ID: RCOCORPT Date: 01/28/2015
User: cn409we Department of Transportation Page: 2-ef-2-
Project Nbr Itm Nbr Catg Item Code Unit Unit Price Bid Qty Prey Apprvd Qty Curr CO Qty Curr Apprvd Qty Amount of Change
22983375201 0279 0200 0104 18 EA $80.52 0 0 4 0 This Chng: $322.08
Item Description INLET PROTECTION SYSTEM CO Item Description To Add a New Pay Item for Inlet Protection System
New Revised: $322.08 Supplemental Description) To Add a New Pay Item for Inlet Protection System Bid Contract: $0.00
Supplemental Description2 (Non-Federal Participation) Net Change: $322.08
Total Value for Change Order 003 = $0.00
General or Standard Change Order Explanation
To Add New Pay Items to the Contract for the Installation of a Concrete Sidewalk on the North side of Lake Worth Road and American Disabilities Act
(ADA) Ramp to complete Work Document Number PBC-3-201 dated August 28, 2014, as requested by the Traffic Operations Division. This additional work is necessary due to a conflict with the existing underground gas lines at the referenced location.
To: (Attorney): JEB From: Wanda/Becky Ext.: 2248
Submittals: Date: 02/02/15 Date:
Date:
Reviewed by: Date:
Approved: I/ Subject to Comments: 0
\_5
PLEASE CLOCK HERE
nECEIVE
1 FLB 1 1 2015
L
DOT D4 OFFICE OF THE GENERAL COUNSEL
CONTRACT DOCUMENT TRACKING FORM
DIVISION (File Type):
X TRANS. OPERATIONS
CONTRACT DOCUMENT TYPE (
Adopt -A - Highway
Change Orders
Closeouts and 21-A's
Consultant Agreement
Consultant Supplemental Amendment
Contractual Services
X
Construction / Maint. Supplemental
Construction Spec. Package
TRANS. SUPPORT
RUSH 0
District Contract
Joint Participation Agreement
Joint Participation Agreement Supplemental
Joint Project Agreement
Other
Railroad Agreement
RFP / ITB
Subordination of Utility Agreement
TRANS. DEVELOPMENT
COMMENTS: THE SURETY'S SIGNATURE IS NOT REQUIRED FOR THESE DOCUMENTS
THE E-VERIFY LANGUAGE IS NOT REQUIRED FOR THESE DOCUMENTS; THE PROJECT
LETTING DATE IS 01/03/14
SUPPLEMENTAL NO: 003 AMENDMENT NO: RFP/ITB NO: ITEM SEGMENT:
STATE PROJECT NO: 229833-7-52-01 CONTRACT NO: E4P20 AMOUNT: $0.00
VENDOR/ CONTRACTOR / CONSULTANT: COMMUNITY ASPHALT CORPORATION
Not Approved: 0
COMMENTS: $(), m) 64- - fipLitioivf4tet J/Lrittacei-)
Reviewed by:
Approved: 0
COMMENTS:
Date:
Subject to Comments: 0 Not Approved: 0
Reviewed by: Date:
Approved: 0 Subject to Comments: 0 Not Approved: 0
COMMENTS: