CN-550000-CAT76-W0010000.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|CAT76|1ad883a1da67d9fb05326d534c460f00
Contract number
CAT76
Issued by
Florida

About this file

This document is a Task Work Order for Professional Services issued by the Florida Department of Transportation (FDOT) for the SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road project. The primary consultant is Propel Engineering, LLC, with several subconsultants including ELAND, Ritzel-Mason, GCME, and L.E. Security, Inc. The contract (CAT76) involves professional engineering services for infrastructure improvements, specifically Intelligent Transportation Systems (ITS) along the specified roadway segment.

The total contract value is $913,135.62, with the work scope including deployment of fiber optic cable, replacement of existing Variable Speed Limit Signs (VSLS), addition of CCTV cameras, installation of Bluetooth/AVI readers, and development of a new electrical subsystem. The contract period runs from July 24, 2024, to July 23, 2029, with services broken down into multiple project activities such as project common tasks, roadway analysis, utilities coordination, environmental permits, survey, ITS analysis, and geotechnical work. The contract was competitively negotiated using a Request for Proposal method, with funds approved for fiscal year 2025 and a total budgetary ceiling of $5,000,000.00.

View the file

Other files

File Type Posted
CN-550000-CAT76-00030000.pdf PDF
CN-550000-CAT76.pdf PDF
CN-550000-CAT76-00020000.pdf PDF
CN-550000-AT057.pdf PDF
ContractBudgetExport.csv CSV file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER FOR PROFESSIONAL SERVICES

375-030-25

PROCUREMENT

08/21

Consultant:

Address:

Date:

7/23/2029

*Limiting or Estimating/Budgeted Amount.

Distribution:

Consultant Acceptance:

Signature

Consultant, Procurement, Financial Services, FDOT Project Manager, File

President

$913,135.62

$0.00

(name) (title)

Majharul Alam, P.E.

$913,135.62

Total authorizations to date (including this one):

Departmental Approval:

$673,907.41 Limit

SUE & Survey Services $168,074.80 Limit

ITS improvements along SR 25/US 27 Miami-Dade/Broward County Line to S of Griffin Road

Propel Engineering, LLC.

2711 Vista Parkway, Suite B-7, West Palm Beach, FL 33411

(To be entered upon execution of T.W.O.)

Brief Task Description:

In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).

Compensation elements are as follows:

Element Description Amount Estimate/LimitMethod of Compensation

The total amount or the limiting amount of the compensation will be:

All services required under this Task Work Order will be completed on or before:

$913,135.62

(LS2) Lump sum paid based on % of completion

(LA4) Units worked at loaded billing rates in Table 6

Page 1 Total

Page 2 thru 6 Subtotal

Total

(LA4) Units worked at loaded billing rates in Table 6Geotechnical Services

Basic Services

Limit$71,153.41

$913,135.62

(name) (title) Signature

Luciana Amato Contract Coordinator

Other Notes:

An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.

Task Work Order No.:

Contract No.: Payment FM No.:

CAT76 449819-2-32-01

Docusign Envelope ID: 66268D68-9B9D-4748-910B-DE1945055215

02/26/2025 | 9:32 AM EST

GCME, Inc

GCME, Inc.

ITEM # & DESCRIPTION Unit # of Units Unit Price Total

211-Asphalt Pavement Coring - 6in dia with Base Depth Check Each 0 $ 263.90 $ - 212-Asphalt Pvmnt Coring - 6in dia without Base Depth Check Each 0 $ 158.01 $ - 305-Concrete Pavement Coring - 4in Dia Each 0 $ 206.18 $ - 306-Concrete Pavement Coring - 6in Dia Each 0 $ 292.57 $ - 401-Geo Auger Borings-H& & Truck/Mud Bug LF 0 $ 12.49 $ - 402-Geo Auger Borings-Track LF 0 $ 15.76 $ - 406-Geo Barge (Rental without labor) Day 0 $ 5,923.08 $ - 408-Geo Concrete Pad & Cover for Monitoring Wells Each 0 $ 402.58 $ - 415-Geo Double Ring Infiltration ASTM D3385 Each 0 $ 619.63 $ - 418-Geo Drill Crew Support Vehicle Day 5 $ 231.37 $ 1,156.85 422-Geo Extra SPT Samples-Barge/Track/Amphib 0-50 Ft Each 0 $ 70.44 $ - 423-Geo Extra SPT Samples-Barge/Track/Amphib 50-100 Ft Each 0 $ 79.73 $ - 424-Geo Extra SPT Samples-Barge/Track/Amphib 100-150 Ft Each 0 $ 95.77 $ - 427-Geo Extra SPT Samples-Truck/Mud Bug 0-50 Ft Each 0 $ 59.72 $ - 428-Geo Extra SPT Samples-Truck/Mud Bug 50-100 Ft Each 0 $ 65.00 $ - 429-Geo Extra SPT Samples-Truck/Mud Bug 100-150 Ft Each 0 $ 77.86 $ - 432-Geo Field Perm 0-10 Ft Open-End Borehole Method Each 0 $ 426.01 $ - 433-Geo Field Perm 10-25Ft Open-End Borehole Method Each 0 $ 560.33 $ - 435-Geo Grout Boreholes- Barge/Track/Amphib 0-50 Ft LF 0 $ 9.68 $ - 436-Geo Grout Boreholes- Barge/Track/Amphib 50-100 Ft LF 0 $ 11.61 $ - 437-Geo Grout Boreholes- Barge/Track/Amphib 100-150 Ft LF 0 $ 15.06 $ - 440-Geo Grout Boreholes- Truck/Mud Bug 0-50 Ft LF 525 $ 7.15 $ 3,753.75 441-Geo Grout Boreholes- Truck/Mud Bug 50-100 Ft LF 0 $ 8.72 $ - 442-Geo Grout Boreholes- Truck/Mud Bug 100-150 Ft LF 0 $ 10.68 $ - 445-Geo Grouted Monitor Well 2in 0-50 Ft LF 0 $ 47.65 $ - 450-Geo Piezometer 2in 0-50 Ft LF 0 $ 52.21 $ - 452-Geo Rock Coring Brg/Track/Amph 0-50 Ft 4in ID & over LF 0 $ 82.97 $ - 454-GeoRocCoring Brg/Track/Amph 50-100 Ft 4in ID & over LF 0 $ 94.16 $ - 456-GeoRocCoring Brg/Track/Amph 100-150 Ft 4in ID & over LF 0 $ 105.96 $ - 462-Geo Rock Coring Truck/Mud Bug 0-50 Ft 4in ID & over LF 0 $ 61.15 $ - 464-Geo Rock Coring Truck/Mud Bug 50-100 Ft 4in ID over LF 0 $ 70.47 $ - 466-GeoRocCoring Truck/MudBug 100-150 Ft 4in ID & over LF 0 $ 76.82 $ - 473-Geo SPT Barge/Track/Amphib 0-50 Ft LF 0 $ 26.86 $ - 474-Geo SPT Barge/Track/Amphib 50-100 Ft LF 0 $ 34.28 $ - 475-Geo SPT Barge/Track/Amphib 100-150 Ft LF 0 $ 53.84 $ - 478-Geo SPT Truck/Mud Bug 0-50 Ft LF 525 $ 17.50 $ 9,187.50 479-Geo SPT Truck/Mud Bug 50-100 Ft LF 0 $ 20.83 $ - 480-Geo SPT Truck/Mud Bug 100-150 Ft LF 0 $ 32.07 $ - 483-Geo Temp Casing 3in Barge/Track/Amphib 0-50 Ft LF 525 $ 16.27 $ 8,541.75 484-Geo Temp Casing 3in Barge/Track/Amphib 50-100 Ft LF 0 $ 19.14 $ - 485-Geo Temp Casing 3in Barge/Track/Amphib 100-150 Ft LF 0 $ 23.29 $ - 488-Geo Temp Casing 3in Truck/Mud Bug 0-50 Ft LF 0 $ 11.16 $ - 489-Geo Temp Casing 3in Truck/Mud Bug 50-100 Ft LF 0 $ 13.46 $ - 490-Geo Temp Casing 3in Truck/Mud Bug 100-150 Ft LF 0 $ 16.20 $ - 505-Geo Temp Casing 6in Barge/Track/Amphib 0-50 Ft LF 0 $ 25.24 $ - 506-Geo Temp Casing 6in Barge/Track/Amphib 50-100 Ft LF 0 $ 28.00 $ - 507-Geo Temp Casing 6in Barge/Track/Amphib 100-150 Ft LF 0 $ 36.97 $ - 508-Geo Temp Casing 6in Truck/Mud Bug 0-50 Ft LF 0 $ 17.36 $ - 509-Geo Temp Casing 6in Truck/Mud Bug 50-100 Ft LF 0 $ 20.29 $ -

FEE ESTIMATE - Nego Project: ITS & VSLS Structures along US 27

Broward County, Florida FPID No.: 449819-2-32-01

GCME-Fee Pp_WO#1_449819-2 US 27 ITS WO#1_US27_Fee_01-17-25 Page 1

GCME, Inc

GCME, Inc.

ITEM # & DESCRIPTION Unit # of Units Unit Price Total

FEE ESTIMATE - Nego Project: ITS & VSLS Structures along US 27

Broward County, Florida FPID No.: 449819-2-32-01

510-Geo Temp Casing 6in Truck/Mud Bug 100-150 Ft LF 0 $ 24.14 $ - 514-Geo Truck/Mud Bug Mobil (30 miles straightline distance) Each 1 $ 649.70 $ 649.70 515-Geo Undisturbed Samples Barge/Track/Amphib 0-50 Ft Each 0 $ 259.75 $ - 516-Geo Undisturbed Samples Barge/Track/Amphib 50-100Ft Each 0 $ 319.69 $ - 517-Geo Undisturbed Samples Brg/Track/Amph 100-150 Ft Each 0 $ 372.89 $ - 519-Geo Undisturbed Samples Truck/Mud Bug 0-50 Ft Each 0 $ 183.21 $ - 520-Geo Undisturbed Samples Truck/Mud Bug 50-100 Ft Each 0 $ 213.05 $ - 521-Geo Undisturbed Samples Truck/Mud Bug 100-150 Ft Each 0 $ 254.06 $ - 531-Geo Truck/Mudbug Drill Rig and Crew (2-person) Hour 0 $ 284.75 $ - 532-Geo Truck/Mudbug Drill Rig and Crew (3-person) Hour 0 $ 361.59 $ - 539-Geo Wash Boring, 0-50 Ft LF 0 $ 13.21 $ - 540-Geo Wash Boring, 50-100 Ft LF 0 $ 15.49 $ - 601-Mobilization - Tugboat Each 0 $ 2,846.15 $ - 604-Mobilization Barge Large Each 0 $ 15,833.33 $ - 605-Mobilization Barge Small Each 0 $ 11,134.34 $ - 606-Mobilization Concrete Coring Each 0 $ 441.25 $ - 609-Mobilization Drill Rig Barge Mount Each 0 $ 11,500.00 $ - 610-Mobilization Drill Rig Track Mount Each 0 $ 2,409.17 $ - 612-Mobilization Drill Rig Truck Mount Each 1 $ 565.46 $ 565.46 614-Mobilization Mudbug/All Terrain Vehicle Each 0 $ 1,434.83 $ - 618-Mobilization Support Boat Each 0 $ 707.32 $ - 700-MOT Arrow Board Each 0 $ 86.17 $ - 701-MOT Attenuator Truck Hour 0 $ 224.00 $ - 702-MOT Channelizing Devices - Type I, II, VP, Drum (each) Each 0 $ 3.57 $ - 706-MOT Portable Sign Each 0 $ 40.32 $ - 707-MOT Post Mounted Sign Each 10 $ 20.30 $ 203.00 708-MOT Provide Channelizing Devices - Cone Each 100 $ 6.14 $ 614.00 712-MOT Support Vehicle Hour 50 $ 115.50 $ 5,775.00 805-Soils Corrosion Series FM 5-550 through 5-553 Test 0 $ 232.22 $ - 809-Soils Hydrometer Only AASHTO T88 Test 0 $ 133.51 $ - 810-Soils Limerock Bearing Ratio (LBR) FM 5-515 Test 0 $ 417.82 $ - 811-Soils Liquid Limit AASHTO T89 Test 6 $ 68.74 $ 412.44 812-Soils Materials Finer than 200 Sieve FM 1-T011 Test 0 $ 50.00 $ - 817-Soils Moisture Content Laboratory AASHTO T265 Test 57 $ 25.00 $ 1,425.00 819-Soils Organic Content Ignition FM 1 T-267 Test 25 $ 49.94 $ 1,248.50 821-Soils Particle Size Anlys AASHTO T88 (Incl. Hydrometer) Test 0 $ 190.00 $ - 822-Soils Particle Size Anlys AASHTO T88 (No Hydrometer) Test 32 $ 76.56 $ 2,449.92 826-Soils Plastic Limit & Plasticity Index AASHTO T90 Test 6 $ 72.19 $ 433.14 832-Soils Split Tensile Strgth of Rock Cores ASTM D3967 Test 0 $ 147.59 $ - 838-Soils Unconfined Compression - Rock ASTM D7012, Method C Test 0 $ 149.25 $ -

MOT Off-Duty Law Officer with Vehicle [L.E. Security, Inc.] Hour 40 $ 75.00 $ 3,000.00

Field and Laboratory Services [GCME]

$39,416.01

GCME-Fee Pp_WO#1_449819-2 US 27 ITS WO#1_US27_Fee_01-17-25 Page 2

Field and Laboratory Services [GCME & L.E. Security, Inc.]

$36,416.01

Name of Consultant Project Information Sheet

Financial Project Identification Number: 449819-2-32-01 TBD

Name of Prime / Subconsultant: Propel Engineering, LLC. County: Broward

Project Description: SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road

Begin Milepost: 7.08 Miles

Number of Lanes: (Urban / Rural / Int.) Lane Configuration: Divided (Divided / Undivided)

Project Type: Minor Roadway Classification: (NHS/FIHS/Off Sys.)

CAP Level: I

Design Variations:

Proposed Design Contract Time: months/days Date of Negotiation: Context Classification:

3. Project Common & Project General Tasks

4. Roadway Analysis

5. Roadway Plans

6a. Drainage Analysis

6b. Drainage Plans

6c. Selective C&G

7. Utilities

8. Environmental Permits and Env. Clearances

9. Structures Summary

10. Structures - Bridge Development Report

11. Structures - Temporary Bridge

12. Structures - Short Span Concrete

13. Structures - Medium Span Concrete

14. Structures - Structural Steel

15. Structures - Segmental Concrete

16. Structures - Movable Span

17. Structures - Retaining Walls

18. Structures - Miscellaneous

19. Signing and Pavement Marking Analysis

20. Signing and Pavement Marking Plans

21. Signalization Analysis

22. Signalization Plans

23. Lighting Analysis

24. Lighting Plans

25. Landscape Analysis

26. Landscape Plans

27. Survey

28. Photogrammetry

29. Mapping

30. Terrestrial Mobile LiDAR

31. Architecture Development

32. Noise Barriers Impact Design Assessment

33. Intelligent Transportation Systems Analysis

34. Intelligent Transportation Systems Plans

35. Geotechnical

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Access Management Classification:

I TTCP Level: Survey Level:

1. Design Exceptions: 1.

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Federal Aid Project Identification Number:

0 End Milepost: 7.08 Project Length:

4 Typical Section: Rural

Project Activity:

Estimated By: Negotiated By: (name - firm)

Consultant FDOT Consultant FDOT

2. 2.

3. 3.

4. 4.

5. 5.

(Minor / Major)

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Project Information Page 1 of 39 2/4/2025

Project Staff Hour Summary

Name of Consultant: Propel Engineering, LLC.

Activity

No.

Activity PROPEL KCA ELAND

RITZEL-

MASON

GCME

L.E.

Security, Inc.

Sub 6 Sub 7 Sub 8 Sub 9 Sub 10 Sub 11 Sub 12 Total Hours

3 Project Common and General Tasks 220 220

4 Roadway Analysis 213 213

5 Roadway Plans 237 237

6a Drainage Analysis 0 0

6b Drainage Plans 0 0

6c Selective C&G 0 0

7 Utilities 158 158

8 Env. Permits and Env. Clearances 26 26

9 Structures - Summary, Misc. Tasks, Dwgs. 0 0

10 BDR 0 0

11 Temporary Bridge 0 0

12 Short Span Concrete Bridge 0 0

13 Medium Span Concrete Bridge 0 0

14 Structural Steel Bridge 0 0

15 Segmental Concrete Bridge 0 0

16 Movable Span 0 0

17 Retaining Walls 0 0

18 Miscellaneous Structures 0 0

19 Signing & Pavement Marking Analysis 0 0

20 Signing & Pavement Marking Plans 0 0

21 Signalization Analysis 0 0

22 Signalization Plans 0 0

23 Lighting Analysis 0 0

24 Lighting Plans 0 0

25 Landscape Analysis 0 0

26 Landscape Plans 0 0

27 Survey - Field and Office Support 241 241

28 Photogrammetry 0 0

29 Mapping 0 0

30 Terrestrial Mobile LiDAR 0 0

31 Architecture Development 0 0

32 Noise Barriers Impact Design Assessment 0 0

33 ITS Analysis 2564 2564

34 ITS Plans 548 548

35 Geotechnical 219 219

854 0 3,112 241 219 0 0 0 0 0 0 0 0 4,426

27 Survey Field Crew Days 71 71

Notes: 1. Staff hours for prime consultant come directly from each discipline's worksheet.

2. Staff hours for subconsultants are to be entered manually into columns D through O.

3. For workbooks prepared by subconsultants, their project hours will be totaled in column C.

Project Total

449819-2-32-01

Project Staff Hours

SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Summary Page 2 of 39 2/4/2025

Financial Project Number: 449819-2-32-01 Project Name: SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road

FAP Number: TBD Date: 2/4/2025 Name of Consultant: Propel Engineering, LLC.

EMPLOYEE CLASSIFICATION

ON CADD

Grand

Total

Project

Manager

Staff Classi-fication 2

Staff Classi-fication 3

Staff Classi-fication 4

Staff Classi-fication 5

Staff Classi-fication 6

Staff Classi-fication 7

Staff Classi-fication 8

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12

Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours PERCENT

3. Project Common and Project General Tasks 220 0 0 0 0 0 0 0 0 0 0 0 0 0 0

4. Roadway Analysis 213 0 0 0 0 0 0 0 0 0 0 0 0 0 0

5. Roadway Plans 237 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

7. Utilities 158 0 0 0 0 0 0 0 0 0 0 0 0 0 0

8. Environmental Permits and Env. Clearances 26 0 0 0 0 0 0 0 0 0 0 0 0 0 0

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

23. Lighting Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

27. Survey (Field & Office Support) 241 0 0 0 0 0 0 0 0 0 0 0 0 0 0

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

33. Intelligent Transportation Systems Analysis 2564 0 0 0 0 0 0 0 0 0 0 0 0 0 0

34. Intelligent Transportation Systems Plans 548 0 0 0 0 0 0 0 0 0 0 0 0 0 0

35. Geotechnical 219 0 0 0 0 0 0 0 0 0 0 0 0 0 0

TOTALS 4426 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Hours from

"Summary" sheet

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - GRAND TOTAL

STAFF HOURS

TOTAL

RANGE

WORK ACTIVITY

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Staff Hour Summary--Grand Total Page 3 of 39 2/4/2025 8:49 AM

Field Survey Estimate:

Notes: 0 4-person crew days 0 0

1. This worksheet provides the distribution of the grand total staff hours for a project.

2. Percentages for staff hour distribution by classification are entered below in rows 65 to 99 of this sheet.

3. Total Staff Hours (column O) may not match staff hours from Summary worksheet (column B) due to rounding. Staff hours calculated for employee classifications are to be adjusted so totals in columns B and O match.

4. Formulas under "Total Staff Hours Range" (columns O & P) may be adjusted to provide desired range.

5. This spreadsheet to be provided in Technical Proposals for Districts that require a breakdown of hours by classification.

Financial Project Number: 449819-2-32-01 Project Name: SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road

FAP Number: TBD Date: 2/4/2025 Name of Consultant: Propel Engineering, LLC.

Hours from

"Summary" sheet

Grand Total Project

Manager

Staff Classi-fication 2

Staff Classi-fication 3

Staff Classi-fication 4

Staff Classi-fication 5

Staff Classi-fication 6

Staff Classi-fication 7

Staff Classi-fication 8

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12 Total

3. Project Common and Project General Tasks 220 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

4. Roadway Analysis 213 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

5. Roadway Plans 237 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6a. Drainage Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6b. Drainage Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6c. Selective C&G 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

7. Utilities 158 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

8. Environmental Permits and Env. Clearances 26 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

10. Structures - Bridge Development Report 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

11. Structures - Temporary Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

12. Structures - Short Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

13. Structures - Medium Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

14. Structures - Structural Steel Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

15. Structures - Segmental Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

16. Structures - Movable Span 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

17. Structures - Retaining Walls 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

18. Structures - Miscellaneous 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

19. Signing & Pavement Marking Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

20. Signing & Pavement Marking Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

21. Signalization Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

22. Signalization Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

23. Lighting Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

24. Lighting Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

25. Landscape Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

26. Landscape Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

27. Survey (Field & Office Support) 241 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

28. Photogrammetry 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

29. Mapping 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

30. Terrestrial Mobile LiDAR 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

31. Architecture Development 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

32. Noise Barriers Impact Design Assessment 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

33. Intelligent Transportation Systems Analysis 2564 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

34. Intelligent Transportation Systems Plans 548 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

35. Geotechnical 219 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

Note: This spreadsheet to be used in Technical Proposal for Districts requiring the Grand Total hours be provided along with percentage distribution by classification.

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - GRAND TOTAL

Staff Hour Distribution Percentages - Grand Total

(Prime Consultant)

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Staff Hour Summary--Grand Total Page 4 of 39 2/4/2025 8:49 AM

Financial Project Number: 449819-2-32-01 Project Name: SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road

FAP Number: TBD Date: 2/4/2025 Name of Consultant: PROPEL

WORK EMPLOYEE CLASSIFICATION

ACTIVITY ON CADD

Firm Total

Project

Manager 3

Home

Chief

Engineer 2

Home

Senior

Engineer 1

Home

Senior

Designer

Home

Engineering

Intern Home

Engineering

Technician

Home

Senior Utility

Coordinator

Home

Utility

Coordinator

Home

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12

Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours PERCENT

3. Project Common and Project General Tasks 220 44 11 66 55 22 22 0 0 0 0 0 0 220 242

4. Roadway Analysis 213 21 11 43 64 53 21 0 0 0 0 0 0 213 234

5. Roadway Plans 237 12 12 47 83 59 25 0 0 0 0 0 0 238 262

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

7. Utilities 158 0 0 0 0 0 0 95 63 0 0 0 0 158 174

8. Environmental Permits,and Env. Clearances 26 1 1 3 9 8 4 0 0 0 0 0 0 26 29

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

23. Lighting Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

TOTALS 854 78 35 159 211 142 72 95 63 0 0 0 0 855 941

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

Hours from

"Summary" sheet

TOTAL

STAFF HOURS

RANGE

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Staff Hour Summary - PROPEL Page 5 of 39 2/4/2025 8:49 AM

Notes: 0 4-person crew days 855 941

1. This worksheet provides the distribution of a firm's total staff hours for a project.

2. Percentages for staff hour distribution by classification are entered below in rows 64 to 98 of this sheet.

3. Total Staff Hours (column O) may not match staff hours from Summary worksheet (column B) due to rounding. Staff hours calculated for employee classifications are to be adjusted so totals in columns B and O match.

4. Formulas under "Total Staff Hours Range" (columns O & P) may be adjusted to provide desired range.

Financial Project Number: 449819-2-32-01 Project Name:SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road

FAP Number: TBD Date: 2/4/2025 Name of Consultant: PROPEL

Hours from

"Summary" sheet

Firm Total

Project

Manager 3

Home

Chief

Engineer 2

Home

Senior

Engineer 1

Home

Senior

Designer

Home

Engineering

Intern Home

Engineering

Technician

Home

Senior Utility

Coordinator

Home

Utility

Coordinator

Home

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12 Total

3. Project Common and Project General Tasks 220 20.0% 5.0% 30.0% 25.0% 10.0% 10.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

4. Roadway Analysis 213 10.0% 5.0% 20.0% 30.0% 25.0% 10.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

5. Roadway Plans 237 5.0% 5.0% 20.0% 35.0% 25.0% 10.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

6a. Drainage Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6b. Drainage Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6c. Selective C&G 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

7. Utilities 158 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 60.0% 40.0% 0.0% 0.0% 0.0% 0.0% 100.00%

8. Environmental Permits,and Env. Clearances 26 5.0% 5.0% 10.0% 35.0% 30.0% 15.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

10. Structures - Bridge Development Report 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

11. Structures - Temporary Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

12. Structures - Short Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

13. Structures - Medium Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

14. Structures - Structural Steel Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

15. Structures - Segmental Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

16. Structures - Movable Span 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

17. Structures - Retaining Walls 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

18. Structures - Miscellaneous 0 0.0% 10.0% 10.0% 15.0% 20.0% 20.0% 20.0% 5.0% 0.0% 0.0% 0.0% 0.0% 100.00%

19. Signing & Pavement Marking Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

20. Signing & Pavement Marking Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

21. Signalization Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

22. Signalization Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

23. Lighting Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

24. Lighting Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

25. Landscape Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

26. Landscape Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

27. Survey (Field & Office Support) 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

28. Photogrammetry 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

29. Mapping 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

30. Terrestrial Mobile LiDAR 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

31. Architecture Development 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

32. Noise Barriers Impact Design Assessment 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

33. Intelligent Transportation Systems Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

34. Intelligent Transportation Systems Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

35. Geotechnical 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

Staff Hour Distribution Percentages - Firm Total

FIRM TOTAL

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Staff Hour Summary - PROPEL Page 6 of 39 2/4/2025 8:49 AM

ESTIMATE OF WORK EFFORT AND COST - PRIME CONSULTANT

Name of Project: SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road Consultant Name: Propel Engineering, LLC.

County: Broward Consultant No.: enter consultants proj. number

FPN: 449819-2-32-01 Date: 2/4/2025

FAP No.: TBD Estimator: insert name

SH Salary Average

By Cost By Rate Per

$255.96 $191.97 $251.48 $184.58 $102.38 $92.31 $184.58 $120.62 $0.00 $0.00 $0.00 $0.00 Activity Activity Task

3. Project Common and Project General Tasks 220 44 11 66 55 22 22 0 0 0 0 0 0 220 $44,407 $201.85

4. Roadway Analysis 213 21 11 43 64 53 21 0 0 0 0 0 0 213 $37,478 $175.95

5. Roadway Plans 237 12 12 47 83 58 25 0 0 0 0 0 0 237 $40,761 $171.99

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

7. Utilities 158 0 0 0 0 0 0 95 63 0 0 0 0 158 $25,134 $159.08

8. Environmental Permits,and Env. Clearances 26 1 1 3 9 8 4 0 0 0 0 0 0 26 $4,052 $155.84

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

23. Lighting Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

Total Staff Hours 854 78 35 159 211 141 72 95 63 0 0 0 0 854

Total Staff Cost $19,964.88 $6,718.95 $39,985.32 $38,946.38 $14,435.58 $6,646.32 $17,535.10 $7,599.06 $0.00 $0.00 $0.00 $0.00 $151,831.59 $177.79

Check = $151,831.59

Survey Field Days by Subconsultant SALARY RELATED COSTS: $151,831.59

4 - Person Crew: OVERHEAD: 0% $0.00

OPERATING MARGIN: 0% $0.00

Notes: FCCM (Facilities Capital Cost Money): 0.00% $0.00

1. This sheet to be used by Prime Consultant to calculate the Grand Total fee. EXPENSES: 0.00% $0.00

2. Manually enter fee from each subconsultant. Unused subconsultant rows may be hidden. Survey (Field - if by Prime)

4-person crew days @ -$ / day $0.00

SUBTOTAL ESTIMATED FEE: $151,831.59

Subconsultant: KCA $0.00

Subconsultant: ELAND $522,075.82

Subconsultant: RITZEL-MASON $168,074.80

Subconsultant: GCME $68,153.41

Subconsultant: L.E. Security, Inc. $3,000.00

Subconsultant: Sub 6 $0.00

Subconsultant: Sub 7 $0.00

Subconsultant: Sub 8 $0.00

Subconsultant: Sub 9 $0.00

Subconsultant: Sub 10 $0.00

Subconsultant: Sub 11 $0.00

Subconsultant: Sub 12 $0.00

SUBTOTAL ESTIMATED FEE: $913,135.62

Geotechnical Field and Lab Testing $0.00

SUBTOTAL ESTIMATED FEE: $913,135.62

Optional Services $0.00

GRAND TOTAL ESTIMATED FEE: $913,135.62

Chief

Engineer 2

Home

Senior

Engineer 1

Home

Senior

Designer

Home

Engineering

Intern Home Staff Classification

Total Staff

Hours From

"SH

Summary -

Firm"

Project

Manager 3

Home

Staff Classi-fication 12

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Engineering

Technician

Home

Senior Utility

Coordinator

Home

Utility

Coordinator

Home

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Fee Sheet - Prime Page 39 of 7 2/4/2025 8:49 AM

Financial Project Number: 449819-2-32-01 Project Name: SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road

FAP Number: TBD Date: 2/4/2025 Name of Consultant: ELAND

Firm Total

Senior

Engineer 1

Home

Engineer 1

Home

Chief

Designer

Home

Senior

Engineering

Technician

Hom

Engineering

Intern Home

Designer

Home

Staff Classi-fication 7

Staff Classi-fication 8

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12

Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours PERCENT

3. Project Common and Project General Tasks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

4. Roadway Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

5. Roadway Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

7. Utilities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

8. Environmental Permits,and Env. Clearances 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

23. Lighting Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

33. Intelligent Transportation Systems Analysis 2564 513 769 385 256 385 256 0 0 0 0 0 0 2564 2820

34. Intelligent Transportation Systems Plans 548 110 164 82 55 82 55 0 0 0 0 0 0 548 603

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

TOTALS 3,112 623 933 467 311 467 311 0 0 0 0 0 0 3,112 3,423

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

Hours from

"Summary" sheet

TOTAL

STAFF HOURS

RANGE

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Staff Hour Summary - ELAND Page 8 of 39 2/4/2025 8:49 AM

Notes: 0 4-person crew days 3,112 3,423

1. This worksheet provides the distribution of a firm's total staff hours for a project.

2. Percentages for staff hour distribution by classification are entered below in rows 64 to 98 of this sheet.

3. Total Staff Hours (column O) may not match staff hours from Summary worksheet (column B) due to rounding. Staff hours calculated for employee classifications are to be adjusted so totals in columns B and O match.

4. Formulas under "Total Staff Hours Range" (columns O & P) may be adjusted to provide desired range.

Financial Project Number: 449819-2-32-01 Project Name:SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road

FAP Number: TBD Date: 2/4/2025 Name of Consultant: ELAND

Hours from

"Summary" sheet

Firm Total

Senior

Engineer 1

Home

Engineer 1

Home

Chief

Designer

Home

Senior

Engineering

Technician

Hom

Engineering

Intern Home

Designer

Home

Staff Classi-fication 7

Staff Classi-fication 8

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12 Total

3. Project Common and Project General Tasks 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

4. Roadway Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

5. Roadway Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6a. Drainage Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6b. Drainage Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6c. Selective C&G 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

7. Utilities 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

8. Environmental Permits,and Env. Clearances 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0.0% 15.0% 25.0% 30.0% 30.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

10. Structures - Bridge Development Report 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

11. Structures - Temporary Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

12. Structures - Short Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

13. Structures - Medium Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

14. Structures - Structural Steel Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

15. Structures - Segmental Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

16. Structures - Movable Span 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

17. Structures - Retaining Walls 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

18. Structures - Miscellaneous 0 0.0% 10.0% 10.0% 15.0% 20.0% 20.0% 20.0% 5.0% 0.0% 0.0% 0.0% 0.0% 100.00%

19. Signing & Pavement Marking Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

20. Signing & Pavement Marking Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

21. Signalization Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

22. Signalization Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

23. Lighting Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

24. Lighting Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

25. Landscape Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

26. Landscape Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

27. Survey (Field & Office Support) 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

28. Photogrammetry 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

29. Mapping 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

30. Terrestrial Mobile LiDAR 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

31. Architecture Development 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

32. Noise Barriers Impact Design Assessment 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

33. Intelligent Transportation Systems Analysis 2564 20.0% 30.0% 15.0% 10.0% 15.0% 10.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

34. Intelligent Transportation Systems Plans 548 20.0% 30.0% 15.0% 10.0% 15.0% 10.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

35. Geotechnical 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

Staff Hour Distribution Percentages - Firm Total

FIRM TOTAL

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Staff Hour Summary - ELAND Page 9 of 39 2/4/2025 8:49 AM

ESTIMATE OF WORK EFFORT AND COST - SUBCONSULTANT

Name of Project: SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road Consultant Name: ELAND

County: Broward Consultant No.: enter consultants proj. number

FPN: 449819-2-32-01 Date: 2/4/2025

FAP No.: TBD Estimator: insert name

SH Salary Average

By Cost By Rate Per

$278.65 $166.12 $167.45 $112.94 $108.97 $94.13 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Activity Activity Task

3. Project Common and Project General Tasks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

4. Roadway Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

5. Roadway Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

7. Utilities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

8. Environmental Permits,and Env. Clearances 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

23. Lighting Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

33. Intelligent Transportation Systems Analysis 2,564 513 769 385 256 385 256 0 0 0 0 0 0 2,564 $430,125 $167.76

34. Intelligent Transportation Systems Plans 548 110 164 82 55 82 55 0 0 0 0 0 0 548 $91,950 $167.79

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

Total Staff Hours 3,112 623 933 467 311 467 311 0 0 0 0 0 0 3,112

Total Staff Cost $173,598.95 $154,989.96 $78,199.15 $35,124.34 $50,888.99 $29,274.43 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $522,075.82 $167.76

Check = $522,075.82

SALARY RELATED COSTS: $522,075.82

OVERHEAD: 0% $0.00

OPERATING MARGIN: 0% $0.00

Notes: FCCM (Facilities Capital Cost Money): 0.00% $0.00

1. This sheet to be used by Subconsultant to calculate its fee. EXPENSES: 0.00% $0.00

SUBTOTAL ESTIMATED FEE: $522,075.82

Survey (Field) 71 4-person crew days @ -$ / day $0.00

Geotechnical Field and Lab Testing $0.00

SUBTOTAL ESTIMATED FEE: $522,075.82

Optional Services $0.00

GRAND TOTAL ESTIMATED FEE: $522,075.82

Senior

Engineering

Technician

Staff Classification Total Staff

Hours From

"SH Summary -

Firm"

Senior

Engineer 1

Home

Engineer 1

Home

Chief

Designer

Home

Staff Classi-fication 11

Staff Classi-fication 12

Engineering

Intern Home

Designer

Home

Staff Classi-fication 7

Staff Classi-fication 8

Staff Classi-fication 9

Staff Classi-fication 10

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Fee Sheet - ELAND Page 39 of 10 2/4/2025 8:49 AM

Financial Project Number: 449819-2-32-01 Project Name: SR-25/US-27 Miami-Dade/Broward County Line to S of Griffin Road

FAP Number: TBD Date: 2/4/2025 Name of Consultant: RITZEL-MASON

Firm Total

SUR Senior

Surveyor 1

Home

SUR

Survey/GIS/

SUE Analyst

3 Home

Staff Classi-fication 3

Staff Classi-fication 4

Staff Classi-fication 5

Staff Classi-fication 6

Staff Classi-fication 7

Staff Classi-fication 8

Staff Classi-fication 9

Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12

Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours PERCENT

3. Project Common and Project General Tasks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

4. Roadway Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

5. Roadway Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

7. Utilities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

8. Environmental Permits,and Env. Clearances 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

23. Lighting Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

27. Survey (Field & Office Support) 240.601768 96 144 0 0 0 0 0 0 0 0 0 0 240 264

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

TOTALS 241 96 144 0 0 0 0 0 0 0 0 0 0 240 264

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

Hours from

"Summary" sheet

TOTAL

STAFF HOURS

RANGE

CAT76 FM 449819-2 SR 25-US 27 ITS Negotiated Staff Hours 2025 0204

Staff Hour Summary - RM Page 11 of 39 2/4/2025 8:49 AM

Notes: 0 4-person crew days 240 264

1. This worksheet provides the distribution of a firm's total staff hours for a project.

2. Percentages for staff hour distribution by classification are entered below in rows 64 to 98 of this sheet.

3. Total Staff Hours (column O) may not match staff hours from Summary worksheet (column B) due to rounding. Staff hours calculated for employee classifications are to be adjusted so totals in columns B and O match.

4. Formulas under "Total Staff…