CN-550000-CAT47-W0030000.pdf
PDF 192 KB Posted
- Contract number
- CAT47
- Issued by
- Florida
About this file
This document is a Task Work Order for Professional Services issued by the Florida Department of Transportation (FDOT) to BCC Engineering, LLC, located in Miami, Florida. The task work order is associated with Contract No. CAT47 and has a Payment FM No. of 456291-13201. The document is for a specific project involving bridge repair design in Bay County, Florida.
The task work order authorizes BCC Engineering to provide professional services for the replacement of the West Bay (ICWW) fender system on State Road 79 over the Intracoastal Waterway, specifically for Bridge Nos. 460077 and 460128. The total compensation for this task is limited to $278,001.00, to be completed by December 31, 2026. The scope of work includes developing detailed plans and technical specifications for a fiber-reinforced polymer fender system replacement, creating maintenance of traffic plans, and preparing bridge plans that meet FDOT and AASHTO design standards. The consultant is required to submit 60%, 100%, and final plan reviews to the department.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CAT47-00050000.pdf | ||
| CN-550000-CAT47-00060000.pdf | ||
| CN-550000-CAT47-W0020000.pdf | ||
| CN-550000-CAT47-00030000.pdf | ||
| CN-550000-CAT47-00040000.pdf | ||
| CN-550000-CAT47-W0040000.pdf | ||
| CN-550000-CAT47.pdf | ||
| CN-550000-CAA09-00110000.pdf | ||
| CN-550000-CAT47-W0010000.pdf | ||
| ContractBudgetExport.csv | CSV file | |
| CN-550000-CAT47-00020000.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
TASK WORK ORDER FOR PROFESSIONAL SERVICES
375-030-25
PROCUREMENT
08/21
Consultant:
Address:
Date:
12/31/2026
*Limiting or Estimating/Budgeted Amount.
Distribution:
Task Work Order No.:
Contract No.: Payment FM No.:
CAT47 45629113201
$555,199.00
(name) (title) Signature
Jason D. Peters, P.E. Director Of Transportation Operations
Other Notes:
An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.
(LA4) Units worked at loaded billing rates in Table 6
Page 1 Total
Page 2 thru 6 Subtotal
Total
Basic Services
BCC Engineering, LLC
6401 SW 87th Avenue, Suite 200, Miami, Florida 33173
(To be entered upon execution of T.W.O.)
Brief Task Description:
In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).
Compensation elements are as follows:
Element Description Amount Estimate/LimitMethod of Compensation
The total amount or the limiting amount of the compensation will be:
All services required under this Task Work Order will be completed on or before:
$278,001.00
$278,001.00 Limit
D/W Bridge Repair Design Fender Replacement SR 79 over ICWW at West Bay Bridge - See attached Scope
Signature
Financial Services PSU Pascarelli-Mathews Consultant PM-Jason Gentry Sarah Evans/Whit Pettis
Director of Structures
$278,001.00
$0.00
(name) (title)
Danny Raymat
$278,001.00
Encumber by task
Total authorizations to date (including this one):
Departmental Approval:
Consultant Acceptance:
Docusign Envelope ID: 87DC3DFF-140F-4DB9-A3B9-42C070191146
4/2/2025
Florida Department of Transportation
RON DESANTIS
GOVERNOR
1074 Highway 90 Chipley, FL 32428
JARED W. PERDUE, P.E.
SECRETARY
www.fdot.gov
SCOPE OF WORK
FM No. 456291-1
SR 79 Over ICWW at West Bay Bridge Nos. 460077 and 460128
Bay County
Provide plans and specifications for bridge repair and rehabilitation as described below:
1. Detailed plans and technical specifications for the removal and replacement of the West Bay (ICWW) fender system. The replacement will consist of fiber-reinforced polymer to comply with the newest design standards.
2. Maintenance of traffic plans as needed.
3. Bridge Plans shall include: Cover Sheet, Project Location Map, Scope of Work, General
Notes, EQ Report and Pay Item Notes, and any details necessary to produce a workable set of plans.
4. Consultant shall provide Phase II, Phase IV, and Plans to Shelf submittals to the department for review.
The plans and specifications shall be prepared according to the current Design Manual. Bridge design shall be in accordance with AASHTO LRFD Bridge Design Specifications and FDOT
Structures Manual.
The Consultant shall provide 60%, 100% and final plans to the Department for review. The
Consultant’s work estimate and fee proposal shall include the proposed time required for completion of the project. Plans shall be prepared in English Units.
February 26, 2025
Docusign Envelope ID: 87DC3DFF-140F-4DB9-A3B9-42C070191146
| Insert from: "456291-1 Scope of Work.pdf" |
| SCOPE OF WORK |
File details come from the government source that posted it. Updated .