About this file

This document is an Amendment No. 2 to a Standard Professional Services Agreement between the State of Florida Department of Transportation and SAI Consulting Engineers, Inc. The agreement pertains to a design group project (Design Group 23-18) involving bridge replacement in two Florida counties: Oak Grove Road over Chestnut Creek Bridge (Bridge No. 604136) in Walton County and CR 183A over Sandy Creek Bridge (Bridge No. 520006) in Holmes County.

The amendment authorizes additional environmental services for both bridge replacement projects under Contract CAN84, with a total supplemental amount of $11,739.60 for each financial project (FPID 439375-1 and FPID 449075-1). The specific services include preparing and applying for Individual Permits from the Florida Department of Environmental Protection (FDEP) and Section 404 Permits from the U.S. Army Corps of Engineers (USACE), developing a uniform mitigation assessment method for proposed wetland impacts, and responding to review questions from permitting agencies. The amendment adjusts the contract's compensation summary, reducing certain service categories while increasing plans update services, with the total maximum limiting amount for the agreement remaining at $2,607,017.48.

View the file

Other files

File Type Posted
CN-550000-BEI38-W0090000.pdf PDF
CN-550000-CAN84-S0010000.pdf PDF
CN-550000-CAN84-00020000.pdf PDF
CN-550000-CAN84-S0010100.pdf PDF
CN-550000-CAN84.pdf PDF
ContractBudgetExport.csv CSV file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

State of Florida Department of Transportation

AMENDMENT

TO

STANDARD PROFESSIONAL SERVICES AGREEMENT

Amendment No.: 2 Execution Date:

Original Contract No.: CAN84 Original Execution Date: May 10, 2023 Consultant Name: SAI Consulting Engineers, Inc.

Agreement Description: Design Group 23-18; Oak Grove Road over Chestnut Creek Bridge (Bridge No.

604136) in Walton County; CR 183A over Sandy Creek Bridge (Bridge No. 520006) in Holmes County Purpose of Amendment: Reallocation of Funds and Remove Funds

The terms of the original agreement, referenced above, are hereby amended as follows:

Contract Compensation Summary of Exhibit “B”, Method of Compensation, of the original Agreement is amended as follows:

For Financial Project No. 44907513201, Survey Services (LA4) is decreased by $57.20, Geotechnical Services (LA4) is decreased by $36,311.86, Public Involvement (LA5) is decreased by $10.47, and Plans Update (LA4) is increased by $11,740.00. This decrease brings the Total Maximum Limiting Amount established for this project to $1,143,958.47. For Financial Project No. 43937513201, Environmental Services (LS2) is decreased by $11,153.00, Survey Services (LA4) is decreased by $8.46, Geotechnical Services (LA4) is decreased by $9,943.07, Public Involvement (LA5) is decreased by $27.46, and Plans Update (LA4) is increased by $11,740.00. This decrease brings the Total Maximum Limiting Amount established for this project to $1,463,059.01 and the Total Maximum Limiting Amount established for said agreement to $2,607,017.48.

Consultant shall perform plans update services upon execution of this amendment.

The provisions of this Agreement and any amendments thereto, will remain in full force and effect through completion of all services required of the Consultant or a 10-year term from the original date of execution of this Agreement.

The following attachments are hereby incorporated into this agreement:

Scope of Services, Page 2 Contract Compensation Summary, Page 3

SAI Consulting Engineers, Inc. STATE OF FLORIDA

DEPARTMENT OF TRANSPORTATION

By: By:

Authorized Signature Authorized Signature

Name: Name: Colby Cleveland, P.E.

Title: Title: Interim Director of Transportation Development

Professional Services Review: Legal Review:

Docusign Envelope ID: 8501524C-7DBC-4E1D-946F-8EBA77C2CD6A

Glenn D. Stickel

President

June 11, 2025

SUPPLEMENTAL AMENDMENT No. 2

SCOPE OF SERVICES

FOR

Design Group 23-18

Bridge Replacement

449075-1-32-01: Oak Grove Road over Chestnut Creek (Bridge No. 604136), in Walton County

439375-1-32-01: CR 183A over Sandy Creek (Bridge No. 520006), in Holmes County

May 14, 2025

1.0 PURPOSE

The purpose of this request for a Supplemental Agreement (SA) is for the authorization of additional environmental services to be performed for both bridge replacement projects under

Contract CAN84.

FPID 439375-1, Supplemental Agreement No. 2 Total amount $11,739.60

FPID 449075-1, Supplemental Agreement No. 2 Total amount $11,739.60

2.0 SERVICES TO BE PROVIDED BY THE CONSULTANT

The scope of services for this Amendment is as follows:

2.4 Environmental Permits and Environmental Clearances

• Provide additional environmental services for the preparation and application of

Individual Permit from FDEP, Section 404 Permit from USACE, preparation of uniform mitigation assessment method for the proposed wetland impacts and respond to review questions from the permitting agencies.

Attachments

Staff Hour Estimate

Docusign Envelope ID: 71499636-E3C4-4BAC-BE74-11C912B12322

Financial Project No. 44907513201 43937513201 Estimate/

Federal Aid Project No. D323 019 B D323 010 B Limit

Basic Services Including Direct Expense (LS2) $780,792 $1,017,414 L

Environmental Services (LS2) $28,539 $45,709 L

Survey Services (LA4) $127,738 $139,911 L

Geotechnical Services (LA4) $212,560 $250,448 L

Public Involvement (LA5) $8,765 $8,765 L

Plans Update (LA4) $10,204 $10,204 L

Total Maximum Limiting Amount $1,168,598 $1,472,451

Amendment No. 2:

Financial Project No. 44907513201 43937513201 Estimate/

Federal Aid Project No. D323 019 B D323 010 B Limit

Basic Services Including Direct Expense (LS2) $0.00 $0.00 L

Environmental Services (LS2) $0.00 ($11,153.00) L

Survey Services (LA4) ($57.20) ($8.46) L

Geotechnical Services (LA4) ($36,311.86) ($9,943.07) L

Public Involvement (LA5) ($10.47) ($27.46) L

Plans Update (LA4) $11,740.00 $11,740.00 L

Total Maximum Limiting Amount ($24,639.53) ($9,391.99)

Financial Project No. 44907513201 43937513201 Estimate/

Federal Aid Project No. D323 019 B D323 010 B Limit

Basic Services Including Direct Expense (LS2) $780,792.00 $1,017,414.00 L

Environmental Services (LS2) $28,539.00 $34,556.00 L

Survey Services (LA4) $127,680.80 $139,902.54 L

Geotechnical Services (LA4) $176,248.14 $240,504.93 L

Public Involvement (LA5) $8,754.53 $8,737.54 L

Plans Update (LA4) $21,944.00 $21,944.00 L

Total Maximum Limiting Amount $1,143,958.47 $1,463,059.01

Total Maximum Amount of Contract

Contract Compensation Summary

Exhibit "B"

Method of Compensation

Contract Compensation Summary

Contract Compensation Summary

$2,607,017.48

Original Agreement (Executed 05/10/23); and AMD No. 1 (Executed 6/25/24):

Original Agreement (Executed 05/10/23); AMD No. 1 (Executed 6/25/24); and AMD No. 2:

Insert from: "MOC AMD2 CAN84.pdf"
Sheet1

File details come from the government source that posted it. Updated .