This document is a Task Work Order for Professional Services issued by the Florida Department of Transportation (FDOT) to SRD Engineers, a consulting firm located in Tampa, Florida. The task work order is specifically for Contract No. CAI72, with a Payment FM No. of 439167-1-32-01, and is designated as Task Work Order No. 8.

The task work order authorizes SRD Engineers to provide design services for districtwide lighting along SR A1A from 35th Street to Crescent Beach Drive in Brevard County. The total compensation for these services is $30,562.50, which will be paid on a lump sum basis according to percentage of completion. The project involves conducting lighting analysis, field reviews, coordination with local power companies and electric utility agencies, and developing lighting designs that meet FDOT standards. The services are to be completed by April 1, 2027, and will primarily focus on replacing existing lighting with LED fixtures and ensuring compatibility with local electric utility systems. The work will encompass 181 total staff hours, with a breakdown of hours across different engineering classification levels.

View the file

Other files

File Type Posted
CN-550000-ASS19-00020000.pdf PDF
CN-550000-ASS19-00030000.pdf PDF
CN-550000-ASS19-00010000.pdf PDF
CN-550000-ASS19-W0010000.pdf PDF
CN-550000-ASS19-W0020000.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER FOR PROFESSIONAL SERVICES

375-030-25

PROCUREMENT

08/21

Consultant:

Address:

Date:

4/1/2027

*Limiting or Estimating/Budgeted Amount.

Distribution:

Task Work Order No.:

Contract No.: Payment FM No.:

CAI72 439167-1-32-01

$357,195.07

(name) (title) Signature

Ayman Mohamed, P.E. District Traffic Design Engineer

Other Notes:

An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.

(LS2) Lump sum paid based on % of completion

Page 1 Total

Page 2 thru 6 Subtotal

Total

Basic Design Services - SRD

SRD Engineers 17425 Bridge Hill Court Suite 200 Tampa, FL 33647

(To be entered upon execution of T.W.O.)

Brief Task Description:

In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).

Compensation elements are as follows:

Element Description Amount Estimate/LimitMethod of Compensation

The total amount or the limiting amount of the compensation will be:

All services required under this Task Work Order will be completed on or before:

$30,562.50

$30,562.50 Limit

The Consultant shall provide Design Services for Districtwide Lighting for SR A1A 35th Street to Crescent Beach Drive as stated in the attached Scope of Services.

FDOT PM: Ayman Mohamed FDOT CM: Diana Turner

Signature

FDOT / SRD, Inc.

Vice President

$30,562.50

$0.00

(name) (title)

Patrick Hatton, P.E.

$30,562.50

Total authorizations to date (including this one):

Departmental Approval:

Consultant Acceptance:

DocuSign Envelope ID: E7F0786C-16AE-4CF2-9E36-16DCE83F1A1F

05/29/2024 | 8:21 AM EDT

ATTACHMENT A

SCOPE OF SERVICES

D/W Lighting Financial Project ID No.:

TBD

SR A1A, From 35th Street to Crescent Beach Dr.

District Five

Work Order No. 8

A. DESCRIPTION OF SERVICES

SRD, Inc. has been contracted by the Florida Department of Transportation District Five to assist the District with the design and preparation of a complete set of lighting construction contract documents and incidental engineering services; plan reviews; preparation of design calculations;

preparation of lighting concept drawing and other miscellaneous services. These services shall be provided on an as needed basis to the District for the tasks outlined below.

B. SERVICES TO BE PERFORMED

The following tasks shall be performed in this Task Work Order.

The Consultant is to provide engineering services at the following:

SR A1A corridor lighting, from 35th Street to Crescent Beach Dr.

All efforts are to assist the Local Power Company’s efforts to light the corridor per latest standards. SRD will provide lighting analysis at the previously listed intersections, calculations, plans, and other technical documents in accordance with FDOT policy, procedures, and requirements.

Consultant is to conduct field reviews to confirm current field conditions for Compatibility with proposed lighting request.

Consultant is to replace the any existing lighting with LED fixtures.

Consultant is to coordinate with local electric utility agencies when it is determined that the electric utility will be the ones to install and maintain lighting using their own electric utility facilities. Consultant will develop designs for the electric utility agencies using existing lighting/electric features where possible and adding additional lighting components when required. Designs will need to be coordinated with local electric utility agency to ensure compatibility with their electric system components both existing and proposed and will need to meet the electric utility design standards in addition to FDOT requirements.

Consultant is to work with Engineer of Record on roadway projects where lighting is to be installed in conjunction with a roadway project to develop a compatible lighting design with the proposed roadway projects and to ensure inclusion of lighting project information into roadway plans.

Utilities: Notify the DEPARTMENT of any utility conflicts and coordinate with the Department on all relocation efforts.

SERVICES TO BE PROVIDED BY THE DEPARTMENT

The following services will be provided by the Department to assist SRD, Inc., in the completion of the assigned tasks:

1. Review and acceptance of completed scoping documents.

2. Attendance at project meetings.

3. Providing existing survey and AGI files.

4. Identification of specific meetings to attend.

C. LENGTH OF SERVICE

The beginning date of the services shall be the date of authorization for this work order. The services shall be completed by April 1, 2027.

D. FEE ESTIMATE

The fee estimates for this work are based on the anticipated project management effort needed to coordinate with stakeholders.

The estimated Lump Sum fee is attached.

Name of Consultant Project Information Sheet

Financial Project Identification Number: TBD N/A

Name of Prime / Subconsultant: SRD, Inc. County: Brevard

Project Description: TWO 8 - SR A1A, 35th Street to Crescent Beach Dr.

Begin Milepost: 0.825 Miles

Number of Lanes: (Urban / Rural / Int.) Lane Configuration: Divided (Divided / Undivided)

Project Type: Roadway Classification: (NHS/FIHS/Off Sys.)

CAP Level:

Design Variations:

Proposed Design Contract Time: months/days Date of Negotiation: Context Classification:

3. Project Common & Project General Tasks

4. Roadway Analysis

5. Roadway Plans

6a. Drainage Analysis

6b. Drainage Plans

6c. Selective C&G

7. Utilities

8. Environmental Permits and Env. Clearances

9. Structures Summary

10. Structures - Bridge Development Report

11. Structures - Temporary Bridge

12. Structures - Short Span Concrete

13. Structures - Medium Span Concrete

14. Structures - Structural Steel

15. Structures - Segmental Concrete

16. Structures - Movable Span

17. Structures - Retaining Walls

18. Structures - Miscellaneous

19. Signing and Pavement Marking Analysis

20. Signing and Pavement Marking Plans

21. Signalization Analysis

22. Signalization Plans

23. Lighting Analysis

24. Lighting Plans

25. Landscape Analysis

26. Landscape Plans

27. Survey

28. Photogrammetry

29. Mapping

30. Terrestrial Mobile LiDAR

31. Architecture Development

32. Noise Barriers Impact Design Assessment

33. Intelligent Transportation Systems Analysis

34. Intelligent Transportation Systems Plans

35. Geotechnical

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Access Management Classification:

TTCP Level: Survey Level:

1. Design Exceptions: 1.

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Federal Aid Project Identification Number:

30.153 End Milepost: 30.978 Project Length:

4 Typical Section: Urban

Project Activity:

Estimated By: Negotiated By: (name - firm)

Consultant FDOT Consultant FDOT

2. 2.

3. 3.

4. 4.

5. 5.

(Minor / Major)

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Patrick Hatton/SRD, Inc. Ayman Mohamed/FDOT Patrick Hatton/SRD, Inc. Ayman Mohamed/FDOT

Patrick Hatton/SRD, Inc. Ayman Mohamed/FDOT Patrick Hatton/SRD, Inc. Ayman Mohamed/FDOT

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

Enter name & firm Enter name & office Enter name & firm Enter name & office

TWO#8_A1A_StaffHour_Fee

Project Information Page 1 of 7 5/23/2024

Project Staff Hour Summary

Name of Consultant: SRD, Inc.

Activity

No.

Activity SRD, Inc.

Enter Name

Sub 1 Sub 2 Sub 3 Sub 4 Sub 5 Sub 6 Sub 7 Sub 8 Sub 9 Sub 10 Sub 11 Sub 12 Total Hours

3 Project Common and General Tasks 0 0

4 Roadway Analysis 0 0

5 Roadway Plans 0 0

6a Drainage Analysis 0 0

6b Drainage Plans 0 0

6c Selective C&G 0 0

7 Utilities 0 0

8 Env. Permits and Env. Clearances 0 0

9 Structures - Summary, Misc. Tasks, Dwgs. 0 0

10 BDR 0 0

11 Temporary Bridge 0 0

12 Short Span Concrete Bridge 0 0

13 Medium Span Concrete Bridge 0 0

14 Structural Steel Bridge 0 0

15 Segmental Concrete Bridge 0 0

16 Movable Span 0 0

17 Retaining Walls 0 0

18 Miscellaneous Structures 0 0

19 Signing & Pavement Marking Analysis 0 0

20 Signing & Pavement Marking Plans 0 0

21 Signalization Analysis 0 0

22 Signalization Plans 0 0

23 Lighting Analysis 181 181

24 Lighting Plans 0 0

25 Landscape Analysis 0 0

26 Landscape Plans 0 0

27 Survey - Field and Office Support 0 0

28 Photogrammetry 0 0

29 Mapping 0 0

30 Terrestrial Mobile LiDAR 0 0

31 Architecture Development 0 0

32 Noise Barriers Impact Design Assessment 0 0

33 ITS Analysis 0 0

34 ITS Plans 0 0

35 Geotechnical 0 0

181 0 0 0 0 0 0 0 0 0 0 0 0 181

27 Survey Field Crew Days 0 0

Notes: 1. Staff hours for prime consultant come directly from each discipline's worksheet.

2. Staff hours for subconsultants are to be entered manually into columns D through O.

3. For workbooks prepared by subconsultants, their project hours will be totaled in column C.

TWO 8 - SR A1A, 35th Street to Crescent Beach Dr.

Project Total

TBD

Project Staff Hours

TWO#8_A1A_StaffHour_Fee

Summary Page 2 of 7 5/23/2024

Financial Project Number: TBD Project Name: TWO 8 - SR A1A, 35th Street to Crescent Beach Dr.

FAP Number: N/A Date: 5/23/2024 Name of Consultant: SRD, Inc.

WORK EMPLOYEE CLASSIFICATION

ACTIVITY ON CADD

Firm Total

Project Manager 2

Chief Engineer 2

Senior Engineer 1

Engineer 1 Engineering

Intern Secretary /

Clarical

SUR

Secretary

SUR SUE

Tech I

SUE SUE

Tech 2 Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12

Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours PERCENT

3. Project Common and Project General Tasks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

4. Roadway Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

5. Roadway Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

7. Utilities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

8. Environmental Permits,and Env. Clearances 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

23. Lighting Analysis 181 27 13 36 45 60 0 0 0 0 0 0 0 181 199

24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

TOTALS 181 27 13 36 45 60 0 0 0 0 0 0 0 181 199

Hours from "Summary" sheet

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

STAFF HOURS

TOTAL

RANGE

TWO#8_A1A_StaffHour_Fee Staff Hour Summary - SRD Page 3 of 7 5/23/2024 9:24 AM

Field Survey Estimate:

Notes: 0 4-person crew days 181 199

1. This worksheet provides the distribution of a firm's total staff hours for a project.

2. Percentages for staff hour distribution by classification are entered below in rows 64 to 98 of this sheet.

3. Total Staff Hours (column O) may not match staff hours from Summary worksheet (column B) due to rounding. Staff hours calculated for employee classifications are to be adjusted so totals in columns B and O match.

4. Formulas under "Total Staff Hours Range" (columns O & P) may be adjusted to provide desired range.

Financial Project Number: TBD Project Name:TWO 8 - SR A1A, 35th Street to Crescent Beach Dr.

FAP Number: N/A Date: 5/23/2024 Name of Consultant: SRD, Inc.

Hours from "Summary" sheet

Firm Total Project

Manager 2 Chief

Engineer 2 Senior

Engineer 1 Engineer 1 Engineering

Intern Secretary /

Clarical

SUR

Secretary

SUR SUE

Tech I

SUE SUE

Tech 2 Staff Classi-fication 10

Staff Classi-fication 11

Staff Classi-fication 12 Total

3. Project Common and Project General Tasks 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

4. Roadway Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

5. Roadway Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6a. Drainage Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6b. Drainage Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

6c. Selective C&G 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

7. Utilities 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

8. Environmental Permits,and Env. Clearances 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

10. Structures - Bridge Development Report 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

11. Structures - Temporary Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

12. Structures - Short Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

13. Structures - Medium Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

14. Structures - Structural Steel Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

15. Structures - Segmental Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

16. Structures - Movable Span 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

17. Structures - Retaining Walls 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

18. Structures - Miscellaneous 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

19. Signing & Pavement Marking Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

20. Signing & Pavement Marking Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

21. Signalization Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

22. Signalization Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

23. Lighting Analysis 181 15.0% 7.0% 20.0% 25.0% 33.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%

24. Lighting Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

25. Landscape Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

26. Landscape Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

27. Survey (Field & Office Support) 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

28. Photogrammetry 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

29. Mapping 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

30. Terrestrial Mobile LiDAR 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

31. Architecture Development 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

32. Noise Barriers Impact Design Assessment 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

33. Intelligent Transportation Systems Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

34. Intelligent Transportation Systems Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

35. Geotechnical 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%

ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL

Staff Hour Distribution Percentages - Firm Total

FIRM TOTAL

TWO#8_A1A_StaffHour_Fee Staff Hour Summary - SRD Page 4 of 7 5/23/2024 9:24 AM

ESTIMATE OF WORK EFFORT AND COST - PRIME CONSULTANT

Name of Project: TWO 8 - SR A1A, 35th Street to Crescent Beach Dr. Consultant Name: SRD, Inc.

County: Brevard Consultant No.: enter consultants proj. number FPN: TBD Date: 5/23/2024 FAP No.: N/A Estimator: insert name

SH Salary Average

By Cost By Rate Per

$217.38 $301.74 $223.87 $141.66 $105.61 $77.87 $95.49 $53.53 $64.89 $0.00 $0.00 $0.00 Activity Activity Task

3. Project Common and Project General Tasks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

4. Roadway Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

5. Roadway Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

7. Utilities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

8. Environmental Permits,and Env. Clearances 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

23. Lighting Analysis 181 27 13 36 45 60 0 0 0 0 0 0 0 181 $30,563 $168.85

24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!

Total Staff Hours 181 27 13 36 45 60 0 0 0 0 0 0 0 181

Total Staff Cost $5,869.26 $3,922.62 $8,059.32 $6,374.70 $6,336.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $30,562.50 $168.85

Check = $30,562.50

Survey Field Days by Subconsultant SALARY RELATED COSTS: $30,562.50

4 - Person Crew: OVERHEAD: 0% $0.00

OPERATING MARGIN: 0% $0.00

Notes: FCCM (Facilities Capital Cost Money): 0.00% $0.00

1. This sheet to be used by Prime Consultant to calculate the Grand Total fee. EXPENSES: 0.00% $0.00

2. Manually enter fee from each subconsultant. Unused subconsultant rows may be hidden. Survey (Field - if by Prime) 0 4-person crew days @ -$ / day $0.00

SUBTOTAL ESTIMATED FEE: $30,562.50

Subconsultant: Enter Name Sub 1 $0.00

Subconsultant: Sub 2 $0.00

Subconsultant: Sub 3 $0.00

Subconsultant: Sub 4 $0.00

Subconsultant: Sub 5 $0.00

Subconsultant: Sub 6 $0.00

Subconsultant: Sub 7 $0.00

Subconsultant: Sub 8 $0.00

Subconsultant: Sub 9 $0.00

Subconsultant: Sub 10 $0.00

Subconsultant: Sub 11 $0.00

Subconsultant: Sub 12 $0.00

SUBTOTAL ESTIMATED FEE: $30,562.50

Geotechnical Field and Lab Testing $0.00

SUBTOTAL ESTIMATED FEE: $30,562.50

Optional Services $0.00

GRAND TOTAL ESTIMATED FEE: $30,562.50

Chief Engineer

Senior

Engineer 1 Engineer 1

Engineering

Intern Staff Classification

Total Staff Hours From

"SH

Summary -

Firm"

Project

Manager 2

Staff Classi-fication 12

SUE SUE Tech

Staff Classi-fication 10

Staff Classi-fication 11

Secretary /

Clarical SUR Secretary

SUR SUE Tech

I

TWO#8_A1A_StaffHour_Fee Fee Sheet - SRD Page 7 of 5 5/23/2024 9:24 AM

Project Activity 23: Lighting Analysis

Estimator: Patrick Hatton TWO 8 - SR A1A, 35th Street to Crescent Beach Dr.

TBD

NOTE: Signature Block is optional, per District preference

Task

No.

Task Units No. of Units

Hours/

Units Total Hours

23.1 Lighting Justification Report LS 1 0 0

23.2 Lighting Design Analysis Report (LDAR) LS 1 60 60

23.3 Voltage Drop Calculations EA 0 0 0

23.4 FDEP Coordination and Report LS 1 0 0

23.5 Reference and Master Design Files LS 1 58 58

23.6 Temporary Highway Lighting LS 1 0 0

23.7 Design Documentation LS 1 16 16

Calculated Hours

23.9 Cost Estimate LS 1 4 4

23.10 Technical Special Provisions and Modified Special Provisions

LS 1 0 0

23.11 Other Lighting Analysis LS 1 0 0

23.12 Field Reviews LS 1 16 16

23.13 Technical Meetings LS 1 7.5 8

23.14 Quality Assurance/Quality Control LS % 5% 7

23.15 Independent Peer Review LS % 0% 0

23.16 Supervision LS % 5% 7

23.17 Coordination LS % 3% 5

1 field reviews w/ 2 ppl @ 8hrs ea. = 16

Representing Print Name

FDOT District Ayman Mohamed

Consultant Name Patrick Hatton

4 hours preparation of cost estimate

23.8 Lighting Quantities for EQ Report N/A0

Lighting Analysis Technical Subtotal

Lighting Analysis Nontechnical Subtotal

23. Lighting Analysis Total

0Light Poles

60hrs midrange = 60

To Be Completed by Power Company

N/A

25 hours setup + 40hrs x 0.825 = 58

N/A

Signature / Date

Comments

N/A

TWO#8_A1A_StaffHour_Fee

23. Lighting Analysis Page 6 of 7 5/23/2024

Project Activity 23: Lighting Analysis

Units No of Units Hours/ Unit Total Hours Comments PM Attendance at

Meeting Required?

Number

EA 1 2 2 0

EA 0 0 0 0

EA 1 2 2 0

EA 1 2 2 0

EA 0 0 0 0

EA 0 0 0 0

EA 0 0 0 0

6 Subtotal Project Manager Meetings 0

EA 3 0.5 1.5 - -

EA 0 0 0 - -

7.5 Total Project Manager Meetings (carries to Tab 3) 0

Carries to 23.13 Carries to Tab 3

Phase Review Meetings

Total Meetings

Power Company (service point coordination)

Maintaining Agency (cities, counties)

FDEP Lighting (coast areas)

Other Meetings

Subtotal Technical Meetings

Airport authority

Progress Meetings (if required by FDOT)

FDOT Traffic Design

Technical Meetings

FDOT Lighting Design

PM attendance at Progress Meetings is manually entered on General Task 3

PM attendance at Phase Review Meetings is manually entered on General Task 3

TWO#8_A1A_StaffHour_Fee

23. Lighting Analysis Page 7 of 7 5/23/2024

File details come from the government source that posted it. Updated .