This document is a Task Work Order for Professional Services issued by the Florida Department of Transportation (FDOT) to SRD Engineers, a consulting firm located in Tampa, Florida. The task work order is specifically for Contract No. CAI72, with a Payment FM No. of 439167-1-32-01, and is designated as Task Work Order No. 8.
The task work order authorizes SRD Engineers to provide design services for districtwide lighting along SR A1A from 35th Street to Crescent Beach Drive in Brevard County. The total compensation for these services is $30,562.50, which will be paid on a lump sum basis according to percentage of completion. The project involves conducting lighting analysis, field reviews, coordination with local power companies and electric utility agencies, and developing lighting designs that meet FDOT standards. The services are to be completed by April 1, 2027, and will primarily focus on replacing existing lighting with LED fixtures and ensuring compatibility with local electric utility systems. The work will encompass 181 total staff hours, with a breakdown of hours across different engineering classification levels.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-ASS19-00020000.pdf | ||
| CN-550000-ASS19-00030000.pdf | ||
| CN-550000-ASS19-00010000.pdf | ||
| CN-550000-ASS19-W0010000.pdf | ||
| CN-550000-ASS19-W0020000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
TASK WORK ORDER FOR PROFESSIONAL SERVICES
375-030-25
PROCUREMENT
08/21
Consultant:
Address:
Date:
4/1/2027
*Limiting or Estimating/Budgeted Amount.
Distribution:
Task Work Order No.:
Contract No.: Payment FM No.:
CAI72 439167-1-32-01
$357,195.07
(name) (title) Signature
Ayman Mohamed, P.E. District Traffic Design Engineer
Other Notes:
An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.
(LS2) Lump sum paid based on % of completion
Page 1 Total
Page 2 thru 6 Subtotal
Total
Basic Design Services - SRD
SRD Engineers 17425 Bridge Hill Court Suite 200 Tampa, FL 33647
(To be entered upon execution of T.W.O.)
Brief Task Description:
In accordance with the above referenced contract, you are authorized to perform the tasks detailed in attached Exhibit A (Scope of Services).
Compensation elements are as follows:
Element Description Amount Estimate/LimitMethod of Compensation
The total amount or the limiting amount of the compensation will be:
All services required under this Task Work Order will be completed on or before:
$30,562.50
$30,562.50 Limit
The Consultant shall provide Design Services for Districtwide Lighting for SR A1A 35th Street to Crescent Beach Drive as stated in the attached Scope of Services.
FDOT PM: Ayman Mohamed FDOT CM: Diana Turner
Signature
FDOT / SRD, Inc.
Vice President
$30,562.50
$0.00
(name) (title)
Patrick Hatton, P.E.
$30,562.50
Total authorizations to date (including this one):
Departmental Approval:
Consultant Acceptance:
DocuSign Envelope ID: E7F0786C-16AE-4CF2-9E36-16DCE83F1A1F
05/29/2024 | 8:21 AM EDT
ATTACHMENT A
SCOPE OF SERVICES
D/W Lighting Financial Project ID No.:
TBD
SR A1A, From 35th Street to Crescent Beach Dr.
District Five
Work Order No. 8
A. DESCRIPTION OF SERVICES
SRD, Inc. has been contracted by the Florida Department of Transportation District Five to assist the District with the design and preparation of a complete set of lighting construction contract documents and incidental engineering services; plan reviews; preparation of design calculations;
preparation of lighting concept drawing and other miscellaneous services. These services shall be provided on an as needed basis to the District for the tasks outlined below.
B. SERVICES TO BE PERFORMED
The following tasks shall be performed in this Task Work Order.
The Consultant is to provide engineering services at the following:
SR A1A corridor lighting, from 35th Street to Crescent Beach Dr.
All efforts are to assist the Local Power Company’s efforts to light the corridor per latest standards. SRD will provide lighting analysis at the previously listed intersections, calculations, plans, and other technical documents in accordance with FDOT policy, procedures, and requirements.
Consultant is to conduct field reviews to confirm current field conditions for Compatibility with proposed lighting request.
Consultant is to replace the any existing lighting with LED fixtures.
Consultant is to coordinate with local electric utility agencies when it is determined that the electric utility will be the ones to install and maintain lighting using their own electric utility facilities. Consultant will develop designs for the electric utility agencies using existing lighting/electric features where possible and adding additional lighting components when required. Designs will need to be coordinated with local electric utility agency to ensure compatibility with their electric system components both existing and proposed and will need to meet the electric utility design standards in addition to FDOT requirements.
Consultant is to work with Engineer of Record on roadway projects where lighting is to be installed in conjunction with a roadway project to develop a compatible lighting design with the proposed roadway projects and to ensure inclusion of lighting project information into roadway plans.
Utilities: Notify the DEPARTMENT of any utility conflicts and coordinate with the Department on all relocation efforts.
SERVICES TO BE PROVIDED BY THE DEPARTMENT
The following services will be provided by the Department to assist SRD, Inc., in the completion of the assigned tasks:
1. Review and acceptance of completed scoping documents.
2. Attendance at project meetings.
3. Providing existing survey and AGI files.
4. Identification of specific meetings to attend.
C. LENGTH OF SERVICE
The beginning date of the services shall be the date of authorization for this work order. The services shall be completed by April 1, 2027.
D. FEE ESTIMATE
The fee estimates for this work are based on the anticipated project management effort needed to coordinate with stakeholders.
The estimated Lump Sum fee is attached.
Name of Consultant Project Information Sheet
Financial Project Identification Number: TBD N/A
Name of Prime / Subconsultant: SRD, Inc. County: Brevard
Project Description: TWO 8 - SR A1A, 35th Street to Crescent Beach Dr.
Begin Milepost: 0.825 Miles
Number of Lanes: (Urban / Rural / Int.) Lane Configuration: Divided (Divided / Undivided)
Project Type: Roadway Classification: (NHS/FIHS/Off Sys.)
CAP Level:
Design Variations:
Proposed Design Contract Time: months/days Date of Negotiation: Context Classification:
3. Project Common & Project General Tasks
4. Roadway Analysis
5. Roadway Plans
6a. Drainage Analysis
6b. Drainage Plans
6c. Selective C&G
7. Utilities
8. Environmental Permits and Env. Clearances
9. Structures Summary
10. Structures - Bridge Development Report
11. Structures - Temporary Bridge
12. Structures - Short Span Concrete
13. Structures - Medium Span Concrete
14. Structures - Structural Steel
15. Structures - Segmental Concrete
16. Structures - Movable Span
17. Structures - Retaining Walls
18. Structures - Miscellaneous
19. Signing and Pavement Marking Analysis
20. Signing and Pavement Marking Plans
21. Signalization Analysis
22. Signalization Plans
23. Lighting Analysis
24. Lighting Plans
25. Landscape Analysis
26. Landscape Plans
27. Survey
28. Photogrammetry
29. Mapping
30. Terrestrial Mobile LiDAR
31. Architecture Development
32. Noise Barriers Impact Design Assessment
33. Intelligent Transportation Systems Analysis
34. Intelligent Transportation Systems Plans
35. Geotechnical
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Access Management Classification:
TTCP Level: Survey Level:
1. Design Exceptions: 1.
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Federal Aid Project Identification Number:
30.153 End Milepost: 30.978 Project Length:
4 Typical Section: Urban
Project Activity:
Estimated By: Negotiated By: (name - firm)
Consultant FDOT Consultant FDOT
2. 2.
3. 3.
4. 4.
5. 5.
(Minor / Major)
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Patrick Hatton/SRD, Inc. Ayman Mohamed/FDOT Patrick Hatton/SRD, Inc. Ayman Mohamed/FDOT
Patrick Hatton/SRD, Inc. Ayman Mohamed/FDOT Patrick Hatton/SRD, Inc. Ayman Mohamed/FDOT
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
Enter name & firm Enter name & office Enter name & firm Enter name & office
TWO#8_A1A_StaffHour_Fee
Project Information Page 1 of 7 5/23/2024
Project Staff Hour Summary
Name of Consultant: SRD, Inc.
Activity
No.
Activity SRD, Inc.
Enter Name
Sub 1 Sub 2 Sub 3 Sub 4 Sub 5 Sub 6 Sub 7 Sub 8 Sub 9 Sub 10 Sub 11 Sub 12 Total Hours
3 Project Common and General Tasks 0 0
4 Roadway Analysis 0 0
5 Roadway Plans 0 0
6a Drainage Analysis 0 0
6b Drainage Plans 0 0
6c Selective C&G 0 0
7 Utilities 0 0
8 Env. Permits and Env. Clearances 0 0
9 Structures - Summary, Misc. Tasks, Dwgs. 0 0
10 BDR 0 0
11 Temporary Bridge 0 0
12 Short Span Concrete Bridge 0 0
13 Medium Span Concrete Bridge 0 0
14 Structural Steel Bridge 0 0
15 Segmental Concrete Bridge 0 0
16 Movable Span 0 0
17 Retaining Walls 0 0
18 Miscellaneous Structures 0 0
19 Signing & Pavement Marking Analysis 0 0
20 Signing & Pavement Marking Plans 0 0
21 Signalization Analysis 0 0
22 Signalization Plans 0 0
23 Lighting Analysis 181 181
24 Lighting Plans 0 0
25 Landscape Analysis 0 0
26 Landscape Plans 0 0
27 Survey - Field and Office Support 0 0
28 Photogrammetry 0 0
29 Mapping 0 0
30 Terrestrial Mobile LiDAR 0 0
31 Architecture Development 0 0
32 Noise Barriers Impact Design Assessment 0 0
33 ITS Analysis 0 0
34 ITS Plans 0 0
35 Geotechnical 0 0
181 0 0 0 0 0 0 0 0 0 0 0 0 181
27 Survey Field Crew Days 0 0
Notes: 1. Staff hours for prime consultant come directly from each discipline's worksheet.
2. Staff hours for subconsultants are to be entered manually into columns D through O.
3. For workbooks prepared by subconsultants, their project hours will be totaled in column C.
TWO 8 - SR A1A, 35th Street to Crescent Beach Dr.
Project Total
TBD
Project Staff Hours
TWO#8_A1A_StaffHour_Fee
Summary Page 2 of 7 5/23/2024
Financial Project Number: TBD Project Name: TWO 8 - SR A1A, 35th Street to Crescent Beach Dr.
FAP Number: N/A Date: 5/23/2024 Name of Consultant: SRD, Inc.
WORK EMPLOYEE CLASSIFICATION
ACTIVITY ON CADD
Firm Total
Project Manager 2
Chief Engineer 2
Senior Engineer 1
Engineer 1 Engineering
Intern Secretary /
Clarical
SUR
Secretary
SUR SUE
Tech I
SUE SUE
Tech 2 Staff Classi-fication 10
Staff Classi-fication 11
Staff Classi-fication 12
Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours Hours PERCENT
3. Project Common and Project General Tasks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
4. Roadway Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5. Roadway Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7. Utilities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8. Environmental Permits,and Env. Clearances 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
23. Lighting Analysis 181 27 13 36 45 60 0 0 0 0 0 0 0 181 199
24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
TOTALS 181 27 13 36 45 60 0 0 0 0 0 0 0 181 199
Hours from "Summary" sheet
ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL
STAFF HOURS
TOTAL
RANGE
TWO#8_A1A_StaffHour_Fee Staff Hour Summary - SRD Page 3 of 7 5/23/2024 9:24 AM
Field Survey Estimate:
Notes: 0 4-person crew days 181 199
1. This worksheet provides the distribution of a firm's total staff hours for a project.
2. Percentages for staff hour distribution by classification are entered below in rows 64 to 98 of this sheet.
3. Total Staff Hours (column O) may not match staff hours from Summary worksheet (column B) due to rounding. Staff hours calculated for employee classifications are to be adjusted so totals in columns B and O match.
4. Formulas under "Total Staff Hours Range" (columns O & P) may be adjusted to provide desired range.
Financial Project Number: TBD Project Name:TWO 8 - SR A1A, 35th Street to Crescent Beach Dr.
FAP Number: N/A Date: 5/23/2024 Name of Consultant: SRD, Inc.
Hours from "Summary" sheet
Firm Total Project
Manager 2 Chief
Engineer 2 Senior
Engineer 1 Engineer 1 Engineering
Intern Secretary /
Clarical
SUR
Secretary
SUR SUE
Tech I
SUE SUE
Tech 2 Staff Classi-fication 10
Staff Classi-fication 11
Staff Classi-fication 12 Total
3. Project Common and Project General Tasks 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
4. Roadway Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
5. Roadway Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
6a. Drainage Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
6b. Drainage Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
6c. Selective C&G 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
7. Utilities 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
8. Environmental Permits,and Env. Clearances 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
10. Structures - Bridge Development Report 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
11. Structures - Temporary Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
12. Structures - Short Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
13. Structures - Medium Span Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
14. Structures - Structural Steel Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
15. Structures - Segmental Concrete Bridge 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
16. Structures - Movable Span 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
17. Structures - Retaining Walls 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
18. Structures - Miscellaneous 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
19. Signing & Pavement Marking Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
20. Signing & Pavement Marking Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
21. Signalization Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
22. Signalization Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
23. Lighting Analysis 181 15.0% 7.0% 20.0% 25.0% 33.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 100.00%
24. Lighting Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
25. Landscape Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
26. Landscape Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
27. Survey (Field & Office Support) 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
28. Photogrammetry 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
29. Mapping 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
30. Terrestrial Mobile LiDAR 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
31. Architecture Development 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
32. Noise Barriers Impact Design Assessment 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
33. Intelligent Transportation Systems Analysis 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
34. Intelligent Transportation Systems Plans 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
35. Geotechnical 0 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.00%
ESTIMATE OF WORK EFFORT FOR TECHNICAL PROPOSALS - FIRM TOTAL
Staff Hour Distribution Percentages - Firm Total
FIRM TOTAL
TWO#8_A1A_StaffHour_Fee Staff Hour Summary - SRD Page 4 of 7 5/23/2024 9:24 AM
ESTIMATE OF WORK EFFORT AND COST - PRIME CONSULTANT
Name of Project: TWO 8 - SR A1A, 35th Street to Crescent Beach Dr. Consultant Name: SRD, Inc.
County: Brevard Consultant No.: enter consultants proj. number FPN: TBD Date: 5/23/2024 FAP No.: N/A Estimator: insert name
SH Salary Average
By Cost By Rate Per
$217.38 $301.74 $223.87 $141.66 $105.61 $77.87 $95.49 $53.53 $64.89 $0.00 $0.00 $0.00 Activity Activity Task
3. Project Common and Project General Tasks 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
4. Roadway Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
5. Roadway Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
6a. Drainage Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
6b. Drainage Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
6c. Selective C&G 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
7. Utilities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
8. Environmental Permits,and Env. Clearances 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
9. Structures - Misc. Tasks, Dwgs, Non-Tech. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
10. Structures - Bridge Development Report 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
11. Structures - Temporary Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
12. Structures - Short Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
13. Structures - Medium Span Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
14. Structures - Structural Steel Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
15. Structures - Segmental Concrete Bridge 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
16. Structures - Movable Span 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
17. Structures - Retaining Walls 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
18. Structures - Miscellaneous 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
19. Signing & Pavement Marking Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
20. Signing & Pavement Marking Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
21. Signalization Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
22. Signalization Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
23. Lighting Analysis 181 27 13 36 45 60 0 0 0 0 0 0 0 181 $30,563 $168.85
24. Lighting Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
25. Landscape Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
26. Landscape Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
27. Survey (Field & Office Support) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
28. Photogrammetry 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
29. Mapping 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
30. Terrestrial Mobile LiDAR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
31. Architecture Development 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
32. Noise Barriers Impact Design Assessment 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
33. Intelligent Transportation Systems Analysis 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
34. Intelligent Transportation Systems Plans 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
35. Geotechnical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 $0 #DIV/0!
Total Staff Hours 181 27 13 36 45 60 0 0 0 0 0 0 0 181
Total Staff Cost $5,869.26 $3,922.62 $8,059.32 $6,374.70 $6,336.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $30,562.50 $168.85
Check = $30,562.50
Survey Field Days by Subconsultant SALARY RELATED COSTS: $30,562.50
4 - Person Crew: OVERHEAD: 0% $0.00
OPERATING MARGIN: 0% $0.00
Notes: FCCM (Facilities Capital Cost Money): 0.00% $0.00
1. This sheet to be used by Prime Consultant to calculate the Grand Total fee. EXPENSES: 0.00% $0.00
2. Manually enter fee from each subconsultant. Unused subconsultant rows may be hidden. Survey (Field - if by Prime) 0 4-person crew days @ -$ / day $0.00
SUBTOTAL ESTIMATED FEE: $30,562.50
Subconsultant: Enter Name Sub 1 $0.00
Subconsultant: Sub 2 $0.00
Subconsultant: Sub 3 $0.00
Subconsultant: Sub 4 $0.00
Subconsultant: Sub 5 $0.00
Subconsultant: Sub 6 $0.00
Subconsultant: Sub 7 $0.00
Subconsultant: Sub 8 $0.00
Subconsultant: Sub 9 $0.00
Subconsultant: Sub 10 $0.00
Subconsultant: Sub 11 $0.00
Subconsultant: Sub 12 $0.00
SUBTOTAL ESTIMATED FEE: $30,562.50
Geotechnical Field and Lab Testing $0.00
SUBTOTAL ESTIMATED FEE: $30,562.50
Optional Services $0.00
GRAND TOTAL ESTIMATED FEE: $30,562.50
Chief Engineer
Senior
Engineer 1 Engineer 1
Engineering
Intern Staff Classification
Total Staff Hours From
"SH
Summary -
Firm"
Project
Manager 2
Staff Classi-fication 12
SUE SUE Tech
Staff Classi-fication 10
Staff Classi-fication 11
Secretary /
Clarical SUR Secretary
SUR SUE Tech
I
TWO#8_A1A_StaffHour_Fee Fee Sheet - SRD Page 7 of 5 5/23/2024 9:24 AM
Project Activity 23: Lighting Analysis
Estimator: Patrick Hatton TWO 8 - SR A1A, 35th Street to Crescent Beach Dr.
TBD
NOTE: Signature Block is optional, per District preference
Task
No.
Task Units No. of Units
Hours/
Units Total Hours
23.1 Lighting Justification Report LS 1 0 0
23.2 Lighting Design Analysis Report (LDAR) LS 1 60 60
23.3 Voltage Drop Calculations EA 0 0 0
23.4 FDEP Coordination and Report LS 1 0 0
23.5 Reference and Master Design Files LS 1 58 58
23.6 Temporary Highway Lighting LS 1 0 0
23.7 Design Documentation LS 1 16 16
Calculated Hours
23.9 Cost Estimate LS 1 4 4
23.10 Technical Special Provisions and Modified Special Provisions
LS 1 0 0
23.11 Other Lighting Analysis LS 1 0 0
23.12 Field Reviews LS 1 16 16
23.13 Technical Meetings LS 1 7.5 8
23.14 Quality Assurance/Quality Control LS % 5% 7
23.15 Independent Peer Review LS % 0% 0
23.16 Supervision LS % 5% 7
23.17 Coordination LS % 3% 5
1 field reviews w/ 2 ppl @ 8hrs ea. = 16
Representing Print Name
FDOT District Ayman Mohamed
Consultant Name Patrick Hatton
4 hours preparation of cost estimate
23.8 Lighting Quantities for EQ Report N/A0
Lighting Analysis Technical Subtotal
Lighting Analysis Nontechnical Subtotal
23. Lighting Analysis Total
0Light Poles
60hrs midrange = 60
To Be Completed by Power Company
N/A
25 hours setup + 40hrs x 0.825 = 58
N/A
Signature / Date
Comments
N/A
TWO#8_A1A_StaffHour_Fee
23. Lighting Analysis Page 6 of 7 5/23/2024
Project Activity 23: Lighting Analysis
Units No of Units Hours/ Unit Total Hours Comments PM Attendance at
Meeting Required?
Number
EA 1 2 2 0
EA 0 0 0 0
EA 1 2 2 0
EA 1 2 2 0
EA 0 0 0 0
EA 0 0 0 0
EA 0 0 0 0
6 Subtotal Project Manager Meetings 0
EA 3 0.5 1.5 - -
EA 0 0 0 - -
7.5 Total Project Manager Meetings (carries to Tab 3) 0
Carries to 23.13 Carries to Tab 3
Phase Review Meetings
Total Meetings
Power Company (service point coordination)
Maintaining Agency (cities, counties)
FDEP Lighting (coast areas)
Other Meetings
Subtotal Technical Meetings
Airport authority
Progress Meetings (if required by FDOT)
FDOT Traffic Design
Technical Meetings
FDOT Lighting Design
PM attendance at Progress Meetings is manually entered on General Task 3
PM attendance at Phase Review Meetings is manually entered on General Task 3
TWO#8_A1A_StaffHour_Fee
23. Lighting Analysis Page 7 of 7 5/23/2024