CN-550000-CAE77-W0010000.pdf
PDF 96 KB Posted
- Contract number
- CAN13
- Issued by
- Florida
About this file
This document is a Task Work Order for Professional Services issued by the State of Florida Department of Transportation, involving RS&H, Inc. as the consultant and Colliers Engineering & Design as the project design firm. The task work order is for Contract Number CAE77, specifically for the University Drive Mobility Project located in Broward County, spanning from SR 834/Sample Road to NW 40th Street (Cardinal Road).
The scope of services includes design work for a 6-lane divided urban roadway with substandard ADA infrastructure. Key tasks involve attending meetings with the City of Coral Springs, FDOT, and FPL, reviving and updating project plans, coordinating roadway and drainage plan changes, and managing utility coordination. The total compensation for these services is $42,068.13, with services to be completed by 7/14/2026. The project will address sidewalk width improvements, drainage structure modifications, and utility reconfigurations along University Drive.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CAN13-S0030000.pdf | ||
| CN-550000-CAN13.pdf | ||
| CN-550000-CAN13-S0020000.pdf | ||
| CN-550000-CAN13-00020000.pdf | ||
| ContractBudgetExport.csv | CSV file | |
| CN-550000-CAN13-S0010000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT A
TASK WORK ORDER SCOPE OF SERVICES
DISTRICTWIDE CONTINUING SERVICES MINOR PROJECT DESIGN
Contract Number: CAE77
Task Work Order No.: 1
Construction Project FPID: 431756-2-52-01
Project Description: University Drive
Project Limits: from SR 834 / Sample Rd to NW 40th St (Cardinal Rd.)
County: Broward
Project Manager: Anson Sonnett, P.E.
CED Project Manager: Anthony Sfameni, P.E.
BACKGROUND
SR-817 / University Drive within the project limits consists of a 6-lane divided urban typical section with a 40 MPH posted speed limit. Americans with Disabilities Act (ADA) infrastructure is substandard within the project limits. The existing sidewalks, which are adjacent to curb and gutter, are of a substandard width (less than 6 feet). The existing raised median is 19.5 feet wide. There is an existing lighting system located in the median and an overhead transmission power line along the west side right of way line.
DESIGN SERVICES
Colliers Engineering & Design will perform the following:
Project General Tasks � Attend meetings with City of Coral Springs, FDOT and FPL. Delivery of Biddability and
Production submittals.
Roadway Analysis/Plans � Revival of plans and update for a strung project. Coordinate plan changes with DRMP (FPID:
431756-1).
Drainage Analysis/Plans � Removal of trench drain and revise to include additional drainage structures.
Utilities � Reestablish initial contact to redo second contact � Redo second contact which requires additional coordination efforts including reviewing documents and individual meetings with UAOs � Obtain new UWS or No Conflict Letters � Re-certify Utilities
File details come from the government source that posted it. Updated .