This document is a Task Work Order Amendment Form for Professional Services issued by the State of Florida Department of Transportation (FDOT). The amendment involves AECOM Technical Services, located at 150 North Orange Avenue in Orlando, FL, under Contract No. C9L75. The document is Amendment No. 1 to Task Work Order No. 11, with a Payment FM No. of 44067616201.

The amendment pertains to the Burns Building Boiler Replacement Post Design project, which is being closed out. The compensation method is a lump sum paid based on percentage of completion. The previous amount for this task work order was $5,281.37, with this amendment showing $0.00 in additional funds. The total authorizations to date, including this amendment, are $791,655.01. The document indicates that the work is completed, final payment has been made, and the task work order is being closed with no additional services or charges authorized beyond the date of execution.

View the file

Other files

File Type Posted
CN-550000-CAU01-00060000.pdf PDF
ContractBudgetExport.csv CSV file
CN-550000-CAU01-00020000.pdf PDF
CN-550000-CAU01-00040000.pdf PDF
CN-550000-CAU01-00030000.pdf PDF
CN-550000-CAU01-00050000.pdf PDF
CN-550000-CAU01.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION

TASK WORK ORDER AMENDMENT FORM

FOR PROFESSIONAL SERVICES

375-030-26

PROCUREMENT

09/18 recovered is $ .

Subtotal Estimate/L imit

$5,281.37 Estimate

$0.00

$0.00

$0.00

$0.00

$0.00

$5,281.37 $0.00

$5,281.37

Attachments:

Distribution:

Payment FM No. (must be the same as original Task Work Order):

44067616201

Check all applicable Terms:

Work is completed and final payment made for Burns Building Boiler Replacement Post Design. This Task Work Order is closed..

150 North Orange Avenue Orlando, FL 32801

AECOM Technical Services Address:

Consultant:

Date (To be entered upon execution of Task Work Order Amendment):Contract No.:

C9L75

Purpose of Amendment:

Amendment No.

to Task Work Order No.

$791,655.01

(Name) (Title) Signature Gretchen Z Miller, NCARB, LEED AP Senior Architect

Consultant Acceptance:

(Title) Randy Mejeur, M.S.

Signature Associate Vice President

(Name)

Compensation Element Description

This Amendment Amount

Burns Building Boiler Replacement Post Design $0.00

Previous Amount

$5,281.37

Method of Compensation

(LS2) Lump sum paid based on % of completion authorized against this task work order beyond the date of execution of this amendment. The following amount is the remaining work order balance to be recovered

The time for completion of services for the subject task work order is extended thru

The total amount for services performed under this task work order is increased by $

The total amount for services performed under this task work order is decreased by $ The decrease in funds will be allocated to the following compensation elements described below.

elements are described below.

from this task work order $ 0.00 . Note: for Prof. Serv. Task Work Order Amendments, the encumbrance line should never be closed

The subject task work order is hereby closed. Final payment for the task work order has been set to PAID status in CITS. No additional services or charges are

(Status 50) by Financial Services staff based on this selection. Additional Note: Please be sure you want to close out before marking. Premature close outs that must

The subject task work order is hereby canceled (no work has been performed and no payment is due). The total amount of the task work order which is

The additional funds will be allocated to the following compensation elements described below.

There is no increase/decrease in the task work order amount, funds are only redistributed between compensation elements. Revised compensation be corrected in CITS may require programmer time and costs borne by the program office.

$0.00 $0.00 $0.00

Departmental Approval:

Total authorizations to date (including this one):

Other Notes:

An independent assessment of the staff hours and quantities for the proposed services has been performed, and found to be fair, reasonable, and competitive.

Page 1 subtotal Page 2 thru 6 Subtotal

Total

6/16/2020 | 11:07 AM EDT