- Contract number
- BEE76
- Issued by
- Florida
About this file
This document is a Task Work Order Amendment for a Master University Agreement between the State of Florida Department of Transportation (FDOT) and the University of Miami. The amendment involves Master Agreement #BEE76, specifically Task Work Order #977-02, Amendment #1, and is focused on a research project managed by the FDOT Research Center.
The research project involves the Extraction and Physio-Mechanical Testing of FRP Reinforcing Bars from 5-year-old Seawater Concrete Test Blocks on Halls River Bridge Bulkhead. The amendment extends the project timeline from the original end date to September 30, 2025, due to delays caused by the 2024 hurricane season. The project is led by Project Manager Alexander Lewis and Principal Investigator Dr. Francisco De Caso y Basalo, with a series of planned tasks including developing a project test plan, extracting test blocks, performing testing and analysis, creating recommendations for a Structures Manual, and producing a final report. The deliverables are scheduled between June 2024 and September 2025, with no changes to the project's funding noted in this amendment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-BEE76-00020000.pdf.crdownload | CRDOWNLOAD file | |
| CN-550000-BEE76-00020000.pdf | ||
| CN-550000-CAB33-00110000.pdf | ||
| CN-550000-BEE76-W0010000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
TASK WORK ORDER FOR
MASTER UNIVERSITY AGREEMENT
AMENDMENT
375-040-81
PROCUREMENT
OGC - 11/12
Master Agreement #:
BEE76
Cost Center # - Task Work Order #:
977 - 02
Amendment #:
University:
University of Miami
Task Work Order Description:
Extraction and Physio-Mechanical Testing of FRP Reinforcing Bars from 5-year-old Seawater Concrete Test Blocks on Halls River Bridge Bulkhead
The effective date of this amendment is the date the Department signs the amendment, unless otherwise stated within the amendment.
Check all applicable terms
The time for completion of services for the subject task work order is extended thru 9/30/2025 .
The subject task work order is hereby canceled (no work has been performed and no payment is due).
The total amount for services performed under this task work order is increased by $ .
The additional funds will be allocated as defined in the attached revised Exhibit B, Method of Compensation.
The total amount for services performed under this task work order is decreased by $ .
The decrease in funds will be allocated as defined in the attached revised Exhibit B, Method of Compensation.
There is no increase/decrease in the task work order amount. Funds are only redistributed between compensation elements as defined in the attached revised Exhibit B, Method of Compensation.
The Scope of Service is hereby amended, attached hereto, and incorporated herein.
Other:
Department Contact:
Name: Jennifer Clark Phone: (850) 414-4614
Office: Research Center Email: jennifer.clark@dot.state.fl.us
Departmental Approval:
J. Darryll Dockstader Manager, Research Center
(Name) (Title) (Signature) (Date)
University Acceptance:
(Name) (Title) (Signature) (Date)
Legal Review:
Holly Kasem-Beg Associate Director 05/02/2025
Docusign Envelope ID: EC7917F3-AA40-43BA-8919-8175112ADC00
05/07/2025 | 3:15 PM EDT
Master University Agreement Task Work Order Amendment Request
Contract-TWO # BEE76-TWO-977-02 Amendment # 1
Title: Extraction and Physio-Mechanical Testing of FRP Reinforcing Bars from 5-year-old Seawater Concrete Test Blocks on Halls River Bridge Bulkhead Start Date: 05/08/2024 End Date: 05/31/2025
Project Manager: Alexander Lewis Principal Investigator: Dr. Francisco De Caso y Basalo
Additional Time
Request for additional time for completion of services to 09/30/2025.
Justification:
Due to the impact of the 2024 hurricane season, the extraction of specimens from the Halls River Bridge had to be postponed.
Originally scheduled for August 2024, the extraction was instead completed in December 2024, which in turn caused delays in subsequent tasks that were dependent on the completion of Task 2.
Change to funding:
_____ increase project amount by $_ _ _____ decrease project amount by $__________ _____ rebudget
Justification:
Attach a budget sheet for the request change.
Change in scope
Describe the change being requested:
Justification:
Attach a revised scope of service and a revised project schedule.
Other modifications:
_____ Change of principal investigator to ________________________________________________ _____ Change of title to ______________________________________________________________
Dr. Francisco De Caso y Basalo (305)-284-6150 fdecaso@miami.edu Requestor (provide contact information):
Note: Requests will not be processed without written FDOT project manager approval. Requested modifications must officially be processed as an amendment signed by the Research Center manager and the authorized party for the contractor in order to be reimbursable.
Deliverables Schedule
Deliverable # / Description of Deliverable as provided in the scope (included associated task #)
Anticipated
Date of
Deliverable
Submittal
(month/year)
TO BE
COMPLETED
BY RESEARCH
CENTER
(performance monitoring)
Kick-off Meeting 6/2024
Task 1. Development of the Preliminary Project Test Plan 9/2024
Task 2. Perform Extraction of Test Blocks 12/2024
Task 3. Perform Testing and Analysis of Characterization and Performance
5/2025
Task 4. Recommendations and Proposed Language for
Structures Manual
6/2025
Task 5. Draft Final and Closeout Teleconference 8/2025
Task 6. Final Report 9/2025