This document is a Notice to Proceed and Utility Work Order Change issued by the Florida Department of Transportation (FDOT) to Florida Power & Light (FP&L) for a utility relocation project in Palm Beach County. The document involves a federal-funded transportation infrastructure project, specifically related to the widening of the Glades Road bridge over Military Trail, with FDOT District 4 overseeing the work.
The utility work order authorizes FP&L to de-energize an overhead power line to facilitate the road infrastructure project, with a total authorized cost of $530,321.00. The work is reimbursable under the force account method and is referenced to an original agreement dated 02/28/1972. The project has a contract end date of December 31, 2024, and utilizes federal funds, which means additional "Appendix A of Assurances" provisions apply. The work is to be performed under the direction of FDOT's District Construction/Maintenance Engineer, with the utility adjustment plans included in the highway contract plans.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-C9Q02-00110000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Transportation
RON DESANTIS
GOVERNOR
3400 West Commercial Boulevard
Fort Lauderdale, FL 33309
KEVIN J. THIBAULT, P.E.
SECRETARY
Improve Safety, Enhance Mobility, Inspire Innovation www.fdot.gov
January 7, 2022
Mr. Beau Bentley
FP&L – Transmission Relocation 6195 NW 82nd Ave.
Miami, FL 33166
Re: Notice to Proceed — Reimbursable Adjustment of Utilities — Florida Statue 337.403
County: Palm Beach State Road: 9 Financial No: 412420-4-56-02 Federal Project ID: D418 011 B Agreement No: ASR16 Description: SR-9/I-95 @ SR-808/Glades Road
Dear Mr. Bentley:
The Department has approved the enclosed Utility Work Order Change #1 for $530,321.00, bill actual.
The total cost authorized to date for the above agreement is $530,321.00. This is for de-energizing of overhead (OH) line to allow for the widening of Glades Rd. bridge over Military Trail for the above project, outlined on your Utility Work Estimate (UWE) attached. This project utilizes federal funds, and
"Appendix A of Assurances" provisions apply.
You may consider this your authorization to proceed with the work under the direction of our District Construction Engineer/Maintenance Engineer. Please note the contract end date is December 31, 2024.
Sincerely, Kelly Armstrong Utility Project Manager cc: Financial Services FDOT Project Manager File
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
710-010-04
UTILITIES
04/10
UTILITY WORK ORDER CHANGE NO. One
Financial Project ID: 412420-4-56-02 Federal Project ID: D418 011 B
County: Palm Beach State Road No.: 9
District Document No: ASR16
Utility Agency/Owner (UAO): Florida Power & Light, Co.
A.
1. The Agency is hereby authorized to observe the following changes in the plans and/or specifications to the subject Utility Agreement, and to perform such work accordingly, further described as:
For de-energizing of overhead (OH) line to allow for the widening of Glades Rd. bridge over Military Trail.
2. The items of work covered by this Work Order Change are referenced to an Agreement of record dated 02/28/1972, and no Supplemental Agreement is required.
B.
1. The Utility Relocation Work is to conform to that shown by the utility adjustment plans as:
a. ATTACHED.
b. INCLUDED IN THE HIGHWAY CONTRACT PLANS.
2. The cost of this Utility Work is:
a. NONREIMBURSABLE
b. REIMBURSABLE
(1) Force Account Method
(2) Lump Sum Method
(3) Third Party Contract Method
C.
ESTIMATED COST OF WORK DUE TO THIS CHANGE:
ITEM NO. ITEM UNIT UNIT
PRICE
WORK ELIMINATED (-) ADDITIONAL WORK (+)
QUANTITY AMOUNT QUANTITY AMOUNT
Const.& Labor $530,321.00
Sub-Totals............................................................................................... $530,321.00
Net Cost of Construction Changes, this order......................................... $0.00 $0.00
Cost of Construction Changes, previously ordered................................. $0.00
Net Total Cost Construction Changes to Date........................................ $530,321.00
Contract Amount...................................................................................... $530,321.00
Estimated Cost of Work Authorized to Date............................................ $530,321.00
Recommended: Approved: Approved:
Date Date Date
District Utility Coordinator District Utility Engineer/Administrator Division Administrator
Federal Highway Administration
Kelly Armstrong Kadian McLean
Typed Name Typed Name Typed Name