This document is a Railroad Change Order No. 1 between the State of Florida Department of Transportation and CSX Transportation, Inc., involving a master agreement originally dated September 15, 1998. The change order is specifically related to a financial project for SR 583 (N 56th Street) in Hillsborough County, Florida, and focuses on preliminary engineering review of design build plans for a lighting corridor involving a rail crossing at Milepost 862.28.
The change order authorizes CSX Transportation to perform preliminary engineering work, with an estimated cost of $1,300.00, to be reimbursed by the Florida Department of Transportation using District Dedicated Revenue (DDR) state funds. The work is to be completed under the force account method, and the contract is set to run from September 15, 2021, to December 31, 2050. The project involves reviewing design build plans for a lighting corridor, and the change order includes provisions for compliance with procurement restrictions, Buy America requirements, and Title VI nondiscrimination assurances.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-550000-CAA23-00050000.pdf | ||
| CN-550000-CAA23-S0020000.pdf | ||
| CN-550000-CAA23-00040000.pdf | ||
| CN-550000-CAA23-S0010000.pdf | ||
| CN-550000-CAA23-00030000.pdf | ||
| CN-550000-CAA23-00020000.pdf | ||
| CN-550000-CAA23-00060000.pdf | ||
| CN-550000-CAA23-00070000.pdf | ||
| CN-550000-CAA23-00080000.pdf | ||
| ContractBudgetExport.csv | CSV file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
RAILROAD CHANGE ORDER NO. 1
725-090-04B
RAIL
OGC – 1/21
Financial Project Number Road Name or Number County Name Parcel & R/W Number
FAP
Number
254677-2-57-93 SR 583 (N 56th STREET) HILLSBOROUGH 10640-2602 N/A
A. 1. The CSX Transportation Company is hereby authorized to observe the following changes in the plans and or specifications to the subject Railroad Agreement, and to perform such work accordingly, further described as:
Preliminary Engineering Review of Design Build Plans for a Lighting Corridor Involving Rail
Crossing # 624849V - Milepost 862.28
2. Exhibit A, Exhibit B, and Exhibit C are attached to the Railroad Change Order and made part of the Original Railroad Agreement.
3. The items of work covered by this Change Order are referenced to an Master Agreement of record dated 09/15/1998 and no supplemental Agreement is required.
Master Type: Crossing Surface Signals Preliminary Engineering
B. 1. The Railroad Relocation Work is to conform to that shown by the railroad adjustment plans as:
a. ATTACHED
b. X INCLUDED IN THE HIGHWAY CONTRACT PLANS
2. Reimbursement for the cost of this Railroad Work is to be in accord with the provisions set forth in Administrative Rule Chapter 14-57 as:
a. NONREIMBURSABLE – Section .011(2)
b. X REIMBURSABLE – Section .011(2)
(1) X Force Account Method
(2) Lump Sum Method
(3) Third Party Contract Method
C. ESTIMATED COST OF WORK DUE TO THIS CHANGE ORDER
ITEM
NO.
ITEM UNIT UNIT
PRICE
WORK ELIMINATED (-)
QTY AMOUNT
ADDITIONAL WORK (+)
QTY AMOUNT
1 Preliminary Engineering 1 1,300.00
Sub-Totals ………………………………………………………………… $ $1,300.00 Net Cost of Construction Changes, this order ………………………... $ $1,300.00 Cost of Construction Changes, previously ordered ………………….. $ $ Net Total Cost of Construction Changes, to date…………………………………………….. $1,300.00 Contract Amount ………………………………………………………………………………… $ Estimated Cost of Work Authorized, to date………………………………………………….. $1,300.00
Examined as to provisions and participating items of cost:
Recommended: Approved: Approved:
Date Date Date
George Boyle Multi-Modal Systems Administrator
Richard Moss PE Director of Transportation
Development
Division Administrator N/A
Federal Highway Administration
725-090-04B
RAIL
OGC – 1/21
EXHIBIT A
The Company shall:
1. utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the Company during the term of the contract; and
2. include an express requirement in any subcontract that subcontractors performing work or providing services pursuant to the state contract utilize the U.S. Department of Homeland Security’s E-Verify system to verify the employment eligibility of all new employees hired by the subcontractor during the contract term.
EXHIBIT B
The Company shall:
1. adhere to all Buy America requirements (23 CFR 635.410) to ensure that all manufacturing processes of steel and iron occur in the United States; and
2. ensure that prefabricated items that contain steel must also comply with Buy America; and
3. provide Buy America certifications that include correct language, project information, and the material’s delivery date.
EXHIBIT C
The Company understands:
1. that while FHWA1273 does not apply to force account work performed by rail companies, FHWA-assistance is subject to Title VI (42 U.S.C. § 2000d et seq); and
2. requires appropriate assurances by providing an executed Title VI / Nondiscrimination Assurance, including Appendices A and E.
FLORIDA DEPARTMENT OF TRANSPORTATION
FUNDS APPROVAL
ASP94
9/23/2021
CONTRACT INFORMATION
FUNDS APPROVAL INFORMATION
FUNDS APPROVED/REVIEWED FOR ROBIN M. NAITOVE, CPA, COMPTROLLER ON 9/23/2021
Action: Task Work Order
Reviewed or Approved: APPROVED
Organization Code: 55074010706
Expansion Option: A5
Object Code: 563000
Amount: $1,300.00
Financial Project: 25467725793
Work Activity (FCT): 127
CFDA:
Fiscal Year: 2022
Budget Entity: 55150200
Category/Category Year: 088716/22
Amendment ID: W001
Sequence: 00
User Assigned ID: CO#1
Enc Line (6s)/Status: 0001/04
Total Amount: $1,300.00
Contract: ASP94
Contract Type: AC - RR CROSSING-PE/INSTAL (RR-XING/PE)
Vendor Name: CSX TRANSPORTATION, INC.
Vendor ID: F546000720022
Beginning Date of This Agreement: 09/15/2021
Ending Date of This Agreement: 12/31/2050
Contract Total/Budgetary Ceiling:
Method of Procurement: R - RAILROAD/UTILITIES AGREEMENT
Description: PE Review of Design Build Plans for Lighting Corridor
Page1 of 1
To: David.Grillo@dot.state.fl.us
C S
X T
S P
U R
KNPBAGD
Highlight
If ther please describe here:
Not Applicable _____ Florida Single Audit _____ CSX is not subject to the Single Audit.
Federal Audit _____ (Florida Statute 215.97)
Single Audit Status ¹ ² :
CSFA # ³
5) Agency
*Phone:
Date:
Recipient. The Federal Sub-Recipient and Vendor Determination Checklist is enclosed for reference.
² CFDA Number: If CSX is subject to the Federal Single Audit, please provide the Catalog of Federal Domestic Assistance (CFDA) number.
³ CSFA Number: If CSX is subject to the Florida Single Audit, please provide the Catalog of State Financial Assistance (CSFA) number.
*Please Note: Per 2 CFR 200.425(a), CSXT can recover Federal Audit costs directly through this project.
For Audit related questions, contact GBCompliance@csx.com.
*4) Single Audit Type: Please advise if the project is subject to single audit requirements by completing the appropriate box below (complete only one box).
CSX TRANSPORTATION – GOVERNMENT BILLING DEPT
NEW PROJECT FORM
To ensure compliance with Federal requirements, please provide the following information so that CSXT may accurately and appropriately setup and handle the necessary accounting associated with the proposed project.
*1) Is the project Federally Funded?
*2) Funding Source: If the project is funded by multiple sources please provide the approximate anticipated percentage of the total project cost to be paid by each source.
*3) Project Requirements
Note: This audit is not related to the project specific audit performed by your agency.
Vendor (CFDA # Not Required)
Recipient (CFDA # )
Sub-Recipient (CFDA # )
Signature of Applicant:
Signature of Applicant Please sign, print , and e-mail this form to the authorized CSX representative
*Legal Address (1):
*Name: Federal Award #:
Date of Award:
Page of