This Task Assignment (TA) is a contract between the State of Florida Department of Environmental Protection (DEP) and Wood Environment and Infrastructure Solutions, Inc. (Wood), a consulting firm. The agreement is entered under Contract Number WQ173 and represents a state-level indefinite delivery vehicle for environmental consulting services related to groundwater monitoring projects within Florida's Suwannee River Basin.
Wood will provide technical support and consulting services for the siting, design, and permitting of up to 20 groundwater monitoring wells through June 1, 2022. The scope of work includes four primary tasks: (1) project kick-off and coordination meetings with regulatory entities and stakeholders; (2) monitoring well site selection through background data compilation, review of existing wells, and data gap analysis; (3) permitting coordination with federal, state, and county governments, including field reconnaissance, right-of-way applications, and maintenance of traffic plans; and (4) design specifications for well drilling, construction, and development procedures. The total fixed price for this task assignment is $76,652, consisting of $75,932 in personnel costs and $720 in vehicle expenses. Deliverables include meeting notes, technical memoranda, permits documentation, and well design specifications, with specific timeframes established for document submission (three days for presentations, fourteen days for technical documents). Monthly invoicing occurs upon partial completion of deliverables, with invoice approval contingent upon reconciliation of charges with tasks assigned by DEP staff. The contract is funded through Florida's fiscal year 2021 budget (Appropriation Category 103259, Project Number WQ173).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-WQ173.pdf | ||
| PC-370000-WQ173.pdf | ||
| CN-370000-WQ173-GMC1.pdf | ||
| CN-370000-WQ173-T5.pdf | ||
| CN-370000-WQ173-T2.pdf | ||
| CN-370000-WQ173-T3.pdf | ||
| CN-370000-WQ173-T5CO1.pdf | ||
| CN-370000-WQ173-T5CO2.pdf | ||
| CN-370000-WQ173-T4.pdf | ||
| CN-370000-WQ173-T4CO1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
WQ173
#1 Completion June 1, 2022
Provide technical support and follow-up assistance to develop services to carry out the project objectives as related to siting, design and permitting for up to 20 groundwater monitoring wells located within the Suwannee River Basin (SRB), or other basins, as applicable.
Michael Dalsis 850-245-8023 Consultant Wood Consultant
Consultant Mary Szafraniec Consultant 813-748-3625 W173
Suwanee River Basin
Groundwater Monitoring Wells
Consultant Consultant
✔ $ 76,652.00
$ 76,652.00
Scope of Work
Wood Consultant Christine Mehle
Service Line Lead christine.mehle Digitally signed by christine.mehle Date: 2021.06.22 09:12:44 -07'00' Julie Espy, Director Digitally signed by Julie Espy, Director
Date: 2021.06.22 09:27:31 -04'00'
3701010000 AF 139900 37200100 103259 WQ173 2021 $ 76,652.00
Rev. 7/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment (TA) No.: 1
Groundwater Monitoring Wells Siting, Design and Permitting
Scope of Work
ATTACHMENT 1
1. Scope of Work.
Execution of Task Assignment 1 through June 1, 2022.
The following scope of work details the services that Wood Environment and Infrastructure Solutions, Inc. (Wood), will provide to the
Florida Department of Environmental Protection (DEP) when requested. It includes the provision of basin-specific planning, project evaluation and design, technical document development, and meeting support and coordination associated with the technical aspects of groundwater related projects located in surface waters and springs Basin Management Action Plans (BMAPs), both adopted and pending. This estimate covers support needed from execution through June 1, 2022.
The BMAP Program uses Total Maximum Daily Loads (TMDLs) as its starting point and brings together local, regional, and state representatives with an interest in reducing the pollutant loads to an impaired water body and restoring the water quality. Together, these entities work with the BMAP Program to develop a BMAP that is implemented by the stakeholders in order to meet the TMDLs.
Wood will provide technical support and follow-up assistance to DEP to develop a technical approach and services to carry out the project objectives as related to siting, design and permitting for up to 20 groundwater monitoring wells located within the Suwannee
River Basin (SRB), or another basin, as applicable. These tasks include participation in meetings and conference calls, scientific analyses, technical designs, or other consultations/contacts with DEP staff, and when necessary, outreach to project representatives and/or stakeholders. These activities will be conducted at the request of DEP and in coordination with DEP staff. Objectives to complete the task assignment include the following work activities:
1) Well siting
a. Review of existing data
b. Data gap analysis
c. Maps showing the location of existing and proposed monitoring wells.
2) Design and permitting
a. Field reconnaissance for utility locates, mapping/staking/flagging, and permit coordination.
b. Coordination with Federal, State, County governments, or other entity (e.g. private) for access authorizations.
c. Obtaining site access for monitoring well construction through public roadway Right-Of-Way (ROW) or other access authorization.
d. Develop Maintenance of Traffic (MOT) plans as required.
e. Preparation of ROW utilization/underground utility permit application for agency signature and subsequent submittal to the respective county.
f. Design, drilling technique, installation methodology, surface completion, well abandonments as required.
This task assignment will not include the installation or monitoring of the recommended monitoring wells. Tasks to be carried out as part of this task assignment are provided below:
Task 1: Kick off and coordination meetings
Wood will participate in a project kick off meeting and up to eight coordination meetings with DEP, regulatory entities, and/or with affected stakeholders. Wood will prepare up to two presentations for technical meetings, as needed.
Task 2: Monitoring well site selection
This task will be accomplished by gathering background data on existing (active and inactive, as applicable) monitoring wells (e.g.
depths, water quality, location along groundwater flow paths, and proximity to springs in springsheds) and other pertinent information for the SRB. Existing data will be evaluated for its suitability to document nutrient trends throughout the SRB based on current policy requirements. Identification of and filling in major data gaps will be considered when recommending the installation of additional groundwater monitoring locations.
Background Data Compilation / Review
As part of the groundwater monitoring well siting and design component, Wood will compile readily available data, assess the existing groundwater quality data (from data availability and spatial distribution perspective), assess the existing flow data, and identify additional data needs and recommendations to identify and fill data gaps.
Wood will review the SRB BMAP, Minimum Flows and Levels (MFL) reports, etc. and other pertinent regulatory documents associated with the SRB (e.g. TMDLs, Park Management Plans, etc.) to assist in the identification of current policies that may affect groundwater and to review other pertinent technical information. Spatial data, such as the Upper Floridan Aquifer (UFA) recharge layer and potentiometric maps will be incorporated in the spatial analyses to develop a conceptual hydrogeologic framework to identify potential flow paths, high recharge areas where groundwater is most vulnerable, and target monitoring zones. This information will be compiled to assist with siting and designing the monitoring wells in an effort to fill existing data gaps.
Data Gaps and Recommendations
Wood will conduct a detailed review of the existing Suwannee Basin groundwater monitoring network to identify critical data gaps.
This subtask will include spatial analysis of water quality trends and active monitoring wells to determine where additional monitoring efforts are needed. Consideration will be given to expanding the network to include existing wells in parts of groundwater contributing areas that are not well represented. State Park management plans will also be reviewed to determine if there are any data needs that could be addressed as part of this task assignment.
There are currently numerous active monitoring wells sampled by the Suwannee River Water Management District (SRWMD) and DEP in the Suwannee BMAP area. Existing active and inactive well locations and data will be reviewed as part of this task. A reconnaissance of inactive SRWMD wells may be needed to assess their suitability for use with this project. Recommendations to fill monitoring data gaps will be based on ensuring that DEP’s above objectives are met as part of BMAP requirements.
Proposed groundwater well locations will be selected based on the ability to capture underrepresented land uses (i.e. agriculture and low to medium density residential) served by the existing monitoring network. Land use represented by existing monitoring wells will be evaluated and compared with surrounding nitrogen sources previously identified by the NSILT. This assessment will help determine if existing wells are capturing the impacts to groundwater from surface activities based on land use type. Wood will evaluate the potentiometric surface for UFA to establish a UFA elevation gradient to assist with identifying depths for the proposed monitoring wells.
This information will be used in conjunction with the depth of existing wells in the area.
The final siting of groundwater wells will be based on land use, potential sources, location along groundwater flow paths, existing (active and inactive) monitoring wells, and recharge rates to identify the conditions most likely to influence water quality. Well siting will prioritize the installation of wells that capture land use types related to agriculture and low-density residential, along with selecting areas where wells can capture multiple pollutant sources. Wood will discuss with DEP the potential to monitor agricultural BMPs and other
BMAP projects that are being implemented to help track progress for restoration of water-quality impaired springs. Water quality data during pre- and post- project implementation can be used to identify and implement the most effective nutrient reduction strategies.
Task 3: Permitting of proposed monitoring wells
Wood will coordinate with Federal, State, County governments, or other entities to identify all applicable permits, licenses, professional registration, rights-of-entry, and applicable state and local regulatory procedures for drilling, well installation, and well abandonment.
Sub-tasks include:
• Conducting field reconnaissance for utility locates, mapping/staking/flagging, and permit coordination.
• Obtaining site access for monitoring well construction through public roadway ROW or other access authorization. Develop
MOT plans as required.
• Preparation of ROW utilization/underground utility permit application for agency signature and subsequent submittal to the respective entity.
• Coordinating with the driller to prepare and submit the required WMD well permits based on the design specifications provided by Wood.
Task 4: Design of monitoring wells
Wood will provide a description of well drilling, construction, and development procedures for all proposed groundwater monitoring wells, which will include the design, drilling technique, installation methodology, surface completion, and well abandonments as required.
• Well design
• Well installation procedures (drilling technique)
Well Design
Based on a review of data from Task 2, which will include available lithologic information and potentiometric data from DEP and the
SRWMD, Wood will provide design specification recommendations for monitoring wells, which may be installed at a range of total depths. The depth ranges allow for the natural variation in topography and potentiometric surface in the areas that have been selected for monitoring well siting and considers the presence/absence of confining layers and proximity to the spring of interest. Wood will provide a well design protocol that is based on the available information and Wood’s existing knowledge of the SRB area. However, the final design will require discussions with DEP and affected stakeholders (i.e., SRWMD and/or FDOT) and will be designed to meet multiple objectives for long-term use by DEP and/or stakeholders. Final design protocols will include diameter size, well screen depths, materials to be used for installation, boring and mounting specifications, etc. Wood understands that there may be inactive wells that may be brought back online, and/or well abandonments may be needed for existing or proposed wells as requested by FDEP and/or as required by the SRWMD.
2. Contractor Responsibilities.
Deliverables. The Contractor shall provide the following deliverables:
Under this task assignment, Wood will provide technical support and follow-up assistance to the DEP for groundwater-related services.
These tasks include participation in meetings and conference calls, scientific analyses, technical designs, or other consultations/contacts with DEP staff, and when necessary, coordination with FDOT and County permitting staff, outreach to project representatives and stakeholders. These activities will be conducted at the request of DEP and in coordination with DEP staff. Specific deliverables by task include the following:
Task 1 Deliverables:
• Kick off meeting and coordination meeting notes
Task 2 Deliverables:
• Brief technical memorandum summarizing data and literature review, methods and results for well siting and data gap analysis;
maps with proposed monitoring well locations
Task 3 Deliverables:
• MOT plan (as needed)
• Copies of all permit applications to all required entities
• Proof of authorizations and permits issued for well construction
Task 4 Deliverables:
• Monitoring well design specifications and construction details
Wood will invoice the DEP monthly for partial completion of task deliverables as discussed below. Invoices must be accompanied by logs documenting hours spent on each subtask for the personnel categories being invoiced. Staff hours have been estimated based on as-needed support. Tasks are due as specified by the DEP's Contract Manager or by a person authorized in Exhibit I. Invoice approval process will include reconciling individual charges by the contractor with tasks assigned by DEP staff.
Deliverable timeframes are stated below. The DEP may establish timeframes from deliverables differing from those established below
(e.g., draft agendas and meeting notes). As necessary, more specific deliverable dates may be established by the DEP for all activities defined under this Task Assignment.
• Draft Meeting Notes, Presentations - Due at least three (3) days prior to meetings or conference calls unless the meeting or conference call is scheduled less than ten (10) days from meetings. Hours for the development of a meeting presentation shall not exceed 45 hours.
• Draft Technical Memorandums, Permitting Documents, and Design Plans - Due at least fourteen (14) days prior to a meeting or conference call unless the meeting or conference call is scheduled less than ten (10) days from its occurrence. Hours for the production of a technical document shall not exceed 150 hours.
Performance Measures: Department staff will review technical documents and provide comment/revision as needed to ensure work is performed in accordance with the scope and all listed tasks above.
Maximum Budget for TA 1:
Summary Budget for TA 1:
$_76,652__
Personnel $ 75,932
Subcontractor Handling Fee $NA
Reimbursable
Travel
$ NA
Other Expenses $ 720
Schedule: Execution through June 1, 2022
3. Department Responsibilities.
Specific work assignments shall be completed by the lowest labor cost category best suited for completing the work to be performed
(based on rates provided in Exhibit II). Task costs are based on the Contractor's estimate of hours and rates (see attached budget).
However, the Contractor has the ability to modify the estimated number of hours for the positions listed in the task budget as long as the hourly rate per position is not exceeded and the total cost per task is not exceeded.
4. Enforcement.
No payment shall be made for unsatisfactory services or deliverables. In the event that services rendered are deemed unsatisfactory, the
Contractor shall re-perform the work needed to ensure satisfactory service, at no additional cost to the Department. Failure to provide all services/deliverables, or failure to provide services/deliverables which are unsatisfactory, shall result in non-payment or termination of the Contract.
EXHIBIT I
TA 1:
The individuals in the following positions, or their successors, are authorized to specify work assignments under this Task. Changes in individuals, including additional positions who may be required to specify work assignments, will be communicated in writing to the DEP Contract Manager and Contractor.
Staff Positions
Project Manager
Senior Scientist
Professional Engineer (PE)
Engineer (EI)
Professional Geologist (PG)
Hydrogeologist
Chemist
Scientist
Senior Technician
Technician
Well Driller
Laborer
Certified Diver
GIS/Drafting
Secretary
Project Accountant
Modeler
Technical Advisor
Principal
Program Manager
Senior Project Manager
Associate Engineer
Senior Engineer I
Engineer II
Engineer III
Senior Scientist II
Scientist III
Scientist II
Technician II
EXHIBIT II
Estimated Budget for Task Assignment #1
Responsible Staff
Sr. Project
Manager Principal
Senior
Scientist
Senior
Engineer PG
Engineer
III
Scientist
III Scientist II
GIS/
Drafting
Senior
Technician
Technician
II Technician Secretary
Labor Rate ($/Hr) $165 $200 $135 $139 $155 $105 $110 $90 $113 $77 $61 $56 $60
Task # Task Description
1 Kick off and coordination meetings 8 8 2 2 4 12 16 2 2 2 1 59 $7,296
2 Well Siting 8 4 4 2 6 4 24 16 4 0 0 0 2 74 $8,940
2A Background Data Compilation / Review 4 2 2 4 2 12 8 1 35 $4,260
2B Data gaps and recommendations 4 2 2 2 2 2 12 8 4 1 39 $4,680
3 Permitting 72 8 2 50 50 10 60 124 4 24 16 16 3 439 $51,612
3A Field Reconnaissance 2 2 16 16 2 8 36 4 24 16 16 142 $13,936
3B Site access and MOT development 30 2 2 16 16 2 24 40 1 133 $16,834
3C Preparation of ROW application 30 2 16 16 4 24 40 1 133 $16,774
3D Coordination with driller to obtain permits 10 2 2 2 2 4 8 1 31 $4,068
4 Well design 16 2 2 8 8 8 12 4 2 2 64 $8,084
104 22 8 56 68 22 104 168 12 28 18 18 8 636 $75,932
EXPENSES # units $/unit Cost
Expenses
Subtotal
Wood Vehicle 8 90$ 720$ $720
$76,652
Total hours
TOTAL COST
Total