CN-370000-SP708-T3CO2.pdf

PDF 54 KB Posted

Attached to
Master Agreement FL|SP708|590f9d28e26ba414344b5dc35f1cf8ea
Contract number
SP708
Issued by
Florida

About this file

This document is a Task Assignment Change Order Form for DEP Contract No. SP708, involving Eclipse Construction Company and the Florida Department of Environmental Protection (DEP). The change order is dated June 7, 2016, and pertains to Task Assignment Number 3, with Scott Petro listed as the Contractor Contract Manager and Marisa Rhian as the DEP Contract Manager.

The change order extends the task completion date by 14 days due to delays caused by Tropical Storm Colin. The original task amount was $14,540.00, with a reimbursement of $1,667.80, resulting in a total task amount of $16,207.60. The original task completion date of May 27, 2016, was extended to June 24, 2016. The document includes signatures from the Contract Manager of Eclipse Construction Company and approvals from the DEP Contract Manager and Contractual Authority, indicating the official nature of the task modification.

View the file

Other files

File Type Posted
CN-370000-SP708-CO1.pdf PDF
CN-370000-SP708-T3.pdf PDF
CN-370000-SP708-TA1.pdf PDF
CN-370000-CN223-T3.pdf PDF
CN-370000-SP708-T2CO1.pdf PDF
CN-370000-SP708-TA1CO1.pdf PDF
CN-370000-SP708.pdf PDF
CN-370000-SP708-CO2.pdf PDF
CN-370000-SP708-T3CO1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .