This document is a Task Assignment Change Order Form for Contract No. SP708 between the Florida Department of Environmental Protection (DEP) and Eclipse Construction Company. The change order is related to a specific task assignment for work at the Tenoroc site, involving debris removal and road improvement activities. The primary parties are the Florida DEP's Mining and Mitigation Program and Eclipse Construction Company, with Marisa Rhian serving as the DEP Contract Manager and Scott Petro as the Contractor Contract Manager.
The change order modifies the original task assignment by extending the completion date by 11 days, from June 12, 2015 to June 22, 2015, due to heavy rain conditions. The original task assignment value was $30,990, comprised of a $25,545 fee schedule and $5,445 in cost reimbursement. The change order includes a $1,200 additional cost for using a pump to dry the work area, bringing the total task amount to $32,190. The scope of work involves debris removal at the Sand Stock Pile Area, installing culverts, and improving maintenance roads in three separate areas, using bank run shell materials and various equipment such as front-end loaders, dump trucks, and rollers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-SP708-CO1.pdf | ||
| CN-370000-SP708-T3.pdf | ||
| CN-370000-SP708-T3CO2.pdf | ||
| CN-370000-SP708-TA1.pdf | ||
| CN-370000-CN223-T3.pdf | ||
| CN-370000-SP708-TA1CO1.pdf | ||
| CN-370000-SP708.pdf | ||
| CN-370000-SP708-CO2.pdf | ||
| CN-370000-SP708-T3CO1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT B
TASK ASSIGNMENT CHANGE ORDER FORM
DEP CONTRACT NO. SP708
Task Assignment Number. _2 ___ Date:_June 10, 2015. ____ Change Order No._1 __ _
Contractor Name:_ Eclipse Construction Company __________________ _
Contractor Contract Manager:_ Scott Petro ____ _ Phone:_ 863-648-9886 __ _
DEP Contract Manager: __ Marisa Rhian ____ _ Phone_863-534-7077 __ _
Description of Change (Use additional sheets if necessary):_Change in Task Completion Date due to heavy rain. _ _ The area will be dried by constructing a berm and use a pump. The cost of the pump is $1200.00 at an hourly rate of $20 per hour.
The work area will need to dry before work can be completed. ____ _
Item
Original task amount:
Task amount prior to this change order:
CHANGE IN TASK AMOUNT
Fee Cost
Schedule Reimbursement
_ 25,545 _ 5,445 __
_25,545 - 0
Total
_30,990 __
_O ____ _ Net increase/decrease in task amount:
Task amount with all change orders:
_1,200
_26,745 ___ _
_O
_5,445 __
_'6, I L 00 fl"<..
_-3fr,996- :3 '2. t \ ~ f(\<..
l2-3-15
CHANGE IN TASK TIME .
Original task completion date:_June 12, 2015 _________ _ Completion date prior to this change:_ June 12, 2015 ________ _ Net increase/decrease in task period:_11 day increase _______ _ Completion date with all change orders:_ June 22, 2015 _______ _
Task Assignment Funding:
Org. Code EO Object Fund Code
171',701 /)/)/)/) <;;r 131300 506002
ECLIPSE CONSTRUCTION COMPANY
Budget Entitv
Special Year Line# Project# Cateqorv
104070
FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
Amount
$1 200.00
~ t:UzB'?/r {; ~~/:a~!~~r~s:dR~~a~.a~~;I:~~; Department of
Mar ·1 sa Rh ·1 a n\E~~iro~mental Protection,ou=Miningand r •· Contract Manager . 7 ~ ' Date
GP~,~ d, /'t!!-.1 ~p
Ot,.,.N?~,,:.) A I' /t') ''I -ft,h-...-cc: I Ruth Heggen, Procurement Section (MS93) I Bureau of Finance & Accounting (MS78) - 2 copies i
Y' Mrt1gat1on Program, ~all;-Marisa.Rhian@dep.state.fl.us.c=US
------,~ Q;ilii d~>15061)11'17:14--' ' '----
Contract Manager Date
APPROVED:
Contractual Authority Date
DEP Contract No. SP708, Attachment B, Page 1 of 1
From:
To:
Cc:
Subject:
Date:
Jerry Petro Rhian Marisa Scott Petro RE: Tenerock Thursday, June 11, 2015 11:32:53 AM
Per our discussion, Eclipse wants to complete the work and we are willing to absorb half of the pump cost The new rate is$ 20 per hour and we anticipate using the pump 10 hours per day for a maximum 5 days. With a mob charge of$ 200 This comes to$ 1,200.00. We will hold this at this max, We will need the weekend to get the pump ready for the site and will begin pumping Mon morning if you approve ..
Thank you, Gerald A. Petro Owner's Representative Eclipse Construction Company Phone: (863) 648-9886 Fax: (863) 648-9817 gpetro@eclipseconstruct.com
From: Rhian, Marisa [mailto:Marisa.Rhian@dep.state.fl.us] Sent: Thursday, June 11, 2015 8:31 AM To: Jerry Petro Cc: Scott Petro Subject: RE: Tenerock
Gerald, After reviewing the $40/hour for the pump and the contract, I don't think we can use the pump. A pump hourly rate wasn't included in our contract. I'm not sure I can justify it as a material. Can someone call me today so we can discuss our options?
I'll be in the field this morning, please call my cell. 863-581-0838
Thanks, fV!'4'~ R~, PWS Environmental Administrator
Mining and Mitigation Program
2001 Homeland Garfield Road
Bartow, Florida 33830
863.534.7077 Ext. 1
Manso Rhian@deo.state fl us
From: Jerry Petro [mailto:gpetro@eclipseconstruct.com]
Sent: Thursday, June 11, 2015 8:06 AM
To: Rhian, Marisa
Cc: Scott Petro
Subject: Tenerock
Marisa, It is too wet to work today and I have called off the crew. It will probably be too wet tomorrow also, however Bryan tells me he can possibly bring in sand for a berm and pump starting on Friday.
How do you feel about weekend work?
Thank you, Gerald A. Petro Owner's Representative Eclipse Construction Company Phone:(863)648-9886 Fax: (863) 648-9817 gpetro@eclipseconstruct.com
ATTACHMENT A
TASK ASSIGNMENT NOTIFICATION FORM
DEP CONTRACT NO. SP708
Task Assignment Number: _2 ________________ Date _May 14, 2015 ___ _
Contractor Name: _Eclipse Construction Company ___________________ _
Contractor Contract Manager:_Scott Petro ___________ _ Phone:_863-648-9886_
DEP Contract Manager: _Marisa Rhian ____________ _ Phone_ 863-534-7077 __
Task Description (Use additional sheets if necessary): See next sheets_
Deliverables (including due dates for each): _Time sheets for all labor, equipment, and materials submitted by Friday of each week. Final inspection report certified by the contractor due by June 12, 2015. The final inspection report shall include the all weekly time sheets. receipts for the materials, and photos or the finished areas. _
Performance Measure:_ No payment will be made for deliverables deemed unsatisfactory by the Department. In the event that a deliverable is deemed unsatisfactory by the Department, Contractor shall re-perform the services needed for submittal or a satisfactory deliverable, at no additional cost to the Department, within thirty (30) days or being notified of the unsatisfactory deliverable.
Task Term: Date orTask Execution through _June 12. 2015 _____ _
Task Assignment Type:
Fee Schedule
Cost Reimbursement
Total Task Assignment Value
Task Assignment Funding:
Org. Code EO Object Fund Budget Code Entity
3735-7010- SC 131300 506002
cc: Ruth Heggen, Procurement Section (MS93)
Amount Not To Exceed:
$_25,545_
$_5,445_
$_30,990 __
Special Year Line# Project# Category 104070
FLORIDA DEPARTMENT OF
ENVIRONMENTAL PROTECTION
Contract Manager
APPROVED:
Amount
30,990
Date
Digitally signed by Megan Strohl vtr\.ret.~(1 S=ti ..,lj n •.~~~~~:::~:!~~~~.o=DEP, ou=Water Q CJ l-"tl\_J/ · elllait=megan.strohl@dep.state.fl.us, c=US
,. Date:2015.05.1812:48:0_o-o_,·oo_· __
Contractual Authority Date
DEP Contract No. SP708, Attachment A, Page 1 of 7
Bureau of Finance & Accounting (MS78) - 2 copies
Scope of Work:
Conduct debris removal activities at Tenoroc and complete earthwork and erosion repairs on the 2 road improvement areas (map attached). The following materials will be provided by Eclipse Construction Company: Bank Run Shell= 11 loads (approximately 28 yards) at the cost of $450 per load plus a 10% markup. DEP will only reimburse Eclipse Construction Company for the materials used durin the task. If less materials are used, then DEP will a onl for the ortion utilized.
Map of Tenoroc Office and areas of debris removal and road improvement.
DEP Contract No. SP708, Attachment A, Page 2 of 7
Area 1 (Debris Removal) Excavate and sort metal debris at the Sand Stock Pile Area and Material Staging Area. Place metal debris into recycle containers. Recycle containers will be placed onsite and removed by another vendor. At the Sand Stock Pile Area, the metal debris is to be excavated from the sand spoil and ground. If Eclipse determines that the metal debris is buried too deep for removal, then Eclipse must notify Marisa Rhian by email, send a photo of the debris, and request approval that the debris may remain in place. If the debris is approved to remain in place, the debris must be cut off at ground level with the chain saw/chop saw and covered over with sand. For safety reason, debris removal at the Sand Stock Pile Area should only occur on Tuesday and Wednesday. Equipment to be used at this Area include: Front End Loader with Operator (40 hours), Pickup with Working Foreman (40 hours), Chain Saw/Chop saw (40 hours)
Map of Area 1 Debris Removal
Photos of debris at Sand Stock Pile Area
DEP Contract No. SP708, Attachment A, Page 3 of 7
Photos of debris at Sand Stock Pile Area
Photo of debris at Sand Stock Pile Area
Photos of debris at Materials Staging Area
DEP Contract No. SP708, Attachment A, Page 4 of 7
Area 2 (Road Improvement) Improve a maintenance road by Installing two culverts using corregated metal pipe and laying sand covered by a 6 inch bank run shell road base to the finished grade. The road will be 282 feet long and 14 feet wide. The corregated metal pipe will be provided to Eclipse and cut to the appropriate length. The two culverts will be installed side-by-side at the agreed upon location between Eclipse and Marisa Rhian. The culverts will be installed at the same elevation and not placed to impede drainage. The culverts will be wrapped with filter fabric provided by Eclipse at no cost. The sand will be brought in from the stock-pile. The road across the entire length of the improvement area should have a consistent elevation upon completion; however the road will be slightly slightly slant to the south to allow drainage. Equipment to be used at this Area include: Dump Truck (48 hours), Roller (48 hours), Front End Loader with Operator (48 hours), and Pickup with Working Foreman (48 hours). 8 loads of Bank Shell Run shall be used.
Map of Area 2 Road lmprovment
Photo of corregated metal pile to be cut and installed as two culverts.
DEP Contract No. SP708, Attachment A, Page 5 of 7
Photo of Area 2 facing west.
Photo of Area 2 facing east.
Area 3 (Road Improvement) Improve a maintenance road by installing sand covered by a 6 inch bank run shell road base to the finished grade. The road will be 100 feet long and 14 feet wide. The road across the entire length of the improvement area should have a consistent elevation upon completion; however the road will be slightly slightly slant to the south to allow drainage. The sand will be brought in from the stock-pile. Equipment to be used at this Area include: Dump Truck (24 hours), Roller (24 hours), Front End Loader with Operator (24 hours), and Pickup with Working Foreman (24 hours). 3 loads of Bank Shell Run shall be used.
DEP Contract No. SP708, Attachment A, Page 6 of 7
Map of Area 3 Road lmprovment
Photo of Area 3 facing east.
DEP Contract No. SP708, Attachment A, Page 7 of 7
From: Scott Petro To:
Cc:
Rhian. Marisa; Jeni Trammell Jerry Petro; Steve Stan e
Subject: RE: Estimate - Teneroc
Date:
Attachments:
Marisa, Wednesday, May 13, 2015 1:25:31 PM
ShellOOl pdf
1. Attached is the last invoice for shell. The actual number per load is $462.00 and markup on top of that. We priced $450 per load before markup.
2. We will wrap the culvert with filter fabric using material left over from a previous job. There will be no cost for the material and labor has been included in the proposal. We have not included any costs associated with the material so we are not including submittals or proof of purchase. If those are required we will have to purchase material and add that to our quotation.
3. Chainsaw was included at $2 per hour. We will provide a chop saw in its place for the same price.
4. I have only eyed the elevation but it appears to me we are fine. If we have to increase the elevation of the fill over the culvert we will make it a gradual transition.
Thank you, Scott Petro
Vice President
Eclipse Construction Company
Phone: (863) 648-9886
Fax: {863) 648-9817
Email: scottpetro@eclipseconstruct.com
From: Rhian, Marisa [mailto:Marisa.Rhian@dep.state.fl.us] Sent: Tuesday, May 05, 2015 2: 10 PM To: Jeni Trammell Cc: Scott Petro; Jerry Petro; Steve Stone Subject: RE: Estimate - Teneroc
Jeni, I am currently working on the Task Assignment for this work. I have a few questions regarding the
Estimate:
Can you please confirm the cost of the 11 loads of bank run shell is $450 per load? Does this include the materials mark-up?
We had discussed wrapping the culverts on Area 2. Does Eclipse plan on wrapping the culvert? If so, please include in the estimate.
On Area 2, does Eclipse need to include a chain saw/chop saw to cut the culvert?
For Area 2, is there enough of a change in elevation for enough sand and bank shell to be placed over the culverts to allow an even elevation? I want to ensure that we are not left with a hump where the culverts are.
As I mentioned in the field I plan on June 12, 2015 to be the Task Execution Deadline.
I am attaching the Scope of Work, please review and let me know if you have any questions.
Thanks, J\llo.,yi,.s.a., R~, PWS Environmental Administrator
Mining and Mitigation Program
2001 Homeland Garfield Road
Bartow, Florida 33830
863.534.7077 Ext. 1
Marisa Rhian@dep state fl.us
From: Jeni Trammell [mailto:jeni@eclipseconstruct.com]
Sent: Monday, May 04, 2015 10:15 AM
To: Rhian, Marisa
Cc: Scott Petro; Jerry Petro; Steve Stone
Subject: RE: Estimate - Teneroc
Good morning Marisa, Attached, please find the proposal for the three areas at Teneroc. Let us know if you have any questions or concerns. Thank you!
Thank you, Jeni Trammell
Office Manager
Eclipse Construction Company
Phone: (863) 648-9886
Fax: (863) 648-9817 jeni@eclipseconstruct.com
From: Rhian, Marisa [maHto: Marisa.Rhjan@dep.state.fl.us] Sent: Monday, May 04, 2015 9:26 AM To: Jeni Trammell Cc: Scott Petro; Steve Stone Subject: RE: Estimate - Teneroc
Scott, Have you been able to complete the estimate for the Tenoroc work?
Thanks, Environmental Administrator
Mining and Mitigation Program
2001 Homeland Garfield Road
Bartow, Florida 33830
863.534.7077 Ext. 1
Marisa Rhian@deostate.fl.us
From: Jeni Trammell [mai!to:jenj@eclipseconstruct.com]
Sent: Tuesday, April 28, 2015 9:29 AM
To: Rhian, Marisa
Cc: Scott Petro
Subject: Estimate - Teneroc
Good morning Marisa, Scott Petro has been tied up in emergency meetings the last couple of days. He is requesting a couple of days' extension on submitting the pricing to you for the Teneroc work. We are hoping to get the pricing to you tomorrow! Please let us know if you have any questions or concerns.
Thank you, Jeni Trammell
Office Manager
Eclipse Construction Company
Phone: (863) 648-9886
Fax: (863) 648-9817 jeni@eclipseconstruct.com
Summary of Teneroc Areas
Equipment: Unit Rates: Total Cost:
Mobilization Front End Loader Each 375 $ 375.00
Dump Truck Each 50 $ 50.00
Roller Each 200 $ 200.00
Total Mobilization Cost: $ 625.00
Equipment: Hours: Rates: Total Cost:
Area 1: Debris Removal Front End Loader with Operator 40 65 $2,600.00
Scope: Excavate and sort metal debris in the Sand Stock Pile Area and the material staging area. ·Recycle containers to be provided by others. Pickup w/Working Foreman 40 70 $2,800.00
Chain Saw I Chop Saw 40 2 $80.00
Total Area 1 Cost: $5,480.00 l
Equipment: Hours: Rates: Total Cost:
Area 2: Road Improvement Dump Truck 48 60 $2,880.00
Scope: Install two culverts using customer provided corregated metal pipe. Deliver sand from stock-pile and provide 6" road base at finish grade. The road is 282' in length by 14' wide. Roller 48 75 $3,600.00
Pickup w/Working Foreman 48 70 $3,360.00
Front End Loader with Operator 48 65 $3,120.00
Total Area 2 Equipment: $12,960.00
Bank run shell - 8 loads: $3,600.00
Total Area 2 Cost: $16,560.00
Equipment: Hours: Rates: Total Cost:
Area 3: Road Improvement Dump Truck 24 60 $1,440.00
Scope: Deliver sand from stock-pile and provide 6" road base at finish grade. The road is 100' in length by 14' wide. Roller 24 75 $1,800.00
Pickup w/Working Foreman 24 70 $1,680.00
Front End Loader with Operator 24 65 $1,560.00
Total Area 2 Equipment: $6,480.00
Bank run shell - 3 loads: $1,350.00
Total Area 2 Cost: $7,830.00