This is a Task Assignment Change Order Form (Change Order No. 2) issued by the Florida Department of Environmental Protection for DEP Contract GC918-18. The contractor is Alachua County, represented by Steve Cullen, P.E., with Roger Ruiz serving as the DEP Contract Manager. The change order was dated April 21, 2026, and has been fully approved and executed by all required parties, including the Budget Representative and Contractual Authority.

The change order modifies Task Assignment #18, which requires the contractor to conduct routine compliance inspections for storage tank systems at 187 facilities within Marion County as identified in Exhibit #1. The primary modification extends the task completion deadline from May 31, 2026, to June 30, 2026. The task amount remains unchanged at $174,086.10, which is charged to Org. Code 37450100000 with Object Code 132500, Budget Entity 37450300, and Special Category 100029. No net increase or decrease in task amount resulted from this change order, as the cost was previously established at $174,086.10 prior to this amendment.

View the file

Other files

File Type Posted
CN-370000-GC918-T10.pdf PDF
CN-370000-GC918-T10CO1.pdf PDF
CN-370000-GC918-T12.pdf PDF
CN-370000-GC918-T13CO2.pdf PDF
CN-370000-GC918-T15CO2.pdf PDF
CN-370000-GC918-T18.pdf PDF
CN-370000-GC918-T2.pdf PDF
CN-370000-GC918-T201.pdf PDF
CN-370000-GC918-T2CO4.pdf PDF
CN-370000-GC918-T3.pdf PDF
CN-370000-GC918-T4.pdf PDF
CN-370000-GC918-T4CO2.pdf PDF
CN-370000-GC918-T4CO5.pdf PDF
CN-370000-GC918-T9.pdf PDF
CN-370000-GC918-T9CO1.pdf PDF
CN-370000-GC918-TACO 2.pdf PDF
CN-370000-GC918-CO1.pdf PDF
CN-370000-GC918-T1.pdf PDF
CN-370000-GC918-T11.pdf PDF
CN-370000-GC918-T11CO1.pdf PDF
CN-370000-GC918-T13.pdf PDF
CN-370000-GC918-T14CO1.pdf PDF
CN-370000-GC918-T15.pdf PDF
CN-370000-GC918-T16.pdf PDF
CN-370000-GC918-T17.pdf PDF
CN-370000-GC918-T17CO1.pdf PDF
CN-370000-GC918-T2CO2.pdf PDF
CN-370000-GC918-T2CO3.pdf PDF
CN-370000-GC918-T4CO6.pdf PDF
CN-370000-GC918-T6.pdf PDF
CN-370000-GC918-TACO 3.pdf PDF
CN-370000-GC918.pdf PDF
CN-370000-GC918-A2.pdf PDF
CN-370000-GC918-ARC1.pdf PDF
CN-370000-GC918-T15CO1.pdf PDF
CN-370000-GC918-T1CO2.pdf PDF
CN-370000-GC918-T1CO3.pdf PDF
CN-370000-GC918-T3CO3.pdf PDF
CN-370000-GC918-T4CO3.pdf PDF
CN-370000-GC918-T5.pdf PDF
CN-370000-GC918-T6CO1.pdf PDF
CN-370000-GC918-T6CO2.pdf PDF
CN-370000-GC918-T7.pdf PDF
CN-370000-GC918-T8.pdf PDF
CN-370000-GC918-TACO 1.pdf PDF
CN-370000-GC918-T10CO2.pdf PDF
CN-370000-GC918-T13CO1.pdf PDF
CN-370000-GC918-T14.pdf PDF
CN-370000-GC918-T14CO2.pdf PDF
CN-370000-GC918-T14CO3.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OOO-012 (Effective 09-14-2015) Page 1 of 2

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

Required Signatures: Adobe Signature

Task Assignment Number: __________________ Date: _______________ Change Order No.______________

Contractor Name: _________________________________________________________________

Contractor Representative: __________________________________________________________

DEP Contract Manager:

Description of Change (Use additional sheets if necessary):

Change in Task Amount

Item Cost Reimbursement Fee Schedule Total

Original Task Amount:

Task amount prior to this change order:

Net increase/decrease in task amount:

Task amount with all change orders:

Change in Task Time

Original task completion date:

Completion date prior to this change:

Net increase/decrease in task period:

Completion date with all change orders:

GC918-18 04/21/2026 2

ALACHUA COUNTY

Steve Cullen P.E.

Roger Ruiz

This change revises the sentence in Task Assignment #18 for DEP Contract GC918 reading:

"Conduct routine compliance inspections for storage tank systems at the 187 facilities within Marion County, identified in Exhibit #1, by May 31, 2026.", to read:

"Conduct routine compliance inspections for storage tank systems at the 187 facilities within , identified in Marion County, Exhibit #1, by June 30, 2026."

164,586.10 164,586.10

174,086.10 174,086.10

174,086.10 174,086.10

06/30/26 06/30/26

06/30/26

OOO-012 (Effective 09-14-2015) Page 2 of 2

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

Change in Funding Information

Org. Code E.O. Object Code Budget Entity

Special Category

Grant # Year Amount

CONTRACTOR FLORIDA DEPARTMENT OF

ENVIRONMENTAL PROTECTION

Contract Manager Date Contract Manager Date

APPROVED:

Budget Representative Date

Contractual Authority Date cc: Procurement Section (MS93) Bureau of Finance & Accounting (MS78) - 2 copies

37450100000 JD 132500 37450300 100029 00 $ 174,086.10

Steven Cullen Digitally signed by Steven Cullen Date: 2026.04.21 15:52:33 -04'00' 04/21/2026 Roger Ruiz

Digitally signed by Roger Ruiz Date: 2026.04.22 09:22:53 -04'00'

Tameshia N. Reid Digitally signed by Tameshia N.