This document is Amendment No. 8 to Agency Term Contract No. GC831, executed between the Florida Department of Environmental Protection (FDEP) and Water & Air Research, Inc. (WAR, Inc.). The contract, originally awarded on February 26, 2014, provides petroleum contamination site response action services in the North Region of Florida. The amendment was processed and became effective on May 25, 2022.
Amendment No. 8 implements rate increases and decreases across multiple pay items in the contractor's rate schedule. The revised Rate Schedule (Attachment D, V3.2) applies to all new work assignments offered on or after the Rate Change Date of May 25, 2022, while pre-existing and previously offered work assignments continue to apply the prior rate schedule. The amendment modifies rates for approximately 280 pay items, with rate changes primarily ranging from +5.00% to +15.00%, with some items experiencing decreases (including two product analysis items reduced to $250.00). Key service categories affected include mobilization costs, drilling and boring operations, well installation and abandonment, sample collection and field testing, laboratory analysis for soil and water samples, debris and waste removal, equipment rental, remedial action construction, pilot testing, system operation and maintenance, professional engineering and geology services, and administrative reports. The rate changes were justified under provision 11.C of the contract and do not modify any line items, only their associated pricing.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1.
2.
3.
4.
All pre-Rate Change Date work assignments and previously offered work assignments will continue to apply Contractor’s applicable prior Rate Schedule.
Contractor’s Rate Schedule is hereby changed for the Pay Items indicated on Table 1 below, effective for New Work assignments unless and until further modified by a subsequent amendment to the Contract.
Attachment D, Rate Schedule (V3.2) is hereby added to the Contract and attached hereto and made a part hereof. For all work assignments offered on or after the Rate Change Date established in this Amendment, Attachment D, Rate Schedule (V3.2) shall apply.
WHEREAS, the rate changes authorized will be applicable only for new work assignments offered on or after the Rate Change Date (“New Work” assignments).
WHEREAS, the Department and Contractor wish to establish a date certain for the rate changes specified herein to be effective, following the execution of this Amendment and the Department’s data processing of the rate changes (hereinafter “Rate Change Date”); and, WHEREAS, the Contractor has requested that rate reductions be made to Attachment D (V3.1) entitled "Rate Schedule"; and, WHEREAS, the Contractor has requested that rate increases be made to Attachment D (V3.1) entitled "Rate Schedule" in accordance with provision 11.C of the Contract; and, WHEREAS, the Department has reviewed this justification and agrees with the requested increase(s); and, The Agency Term Contract No. GC831 (hereinafter "Contract") between the FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION (hereinafter "Department") and WATER &
AIR RESEARCH, INC. (hereinafter "Contractor") executed on February 26, 2014, to provide petroleum contamination site response action services in the North Region, is hereby amended.
PETROLEUM RESTORATION PROGRAM
AGENCY TERM CONTRACT NO. GC831
RATE INCREASE AND DECREASE
AMENDMENT NO. 8
Amendment No. 8
DEP Agency Term Contract No. GC831
This amendment only changes the rates as specified on Table 1, and does not add, delete or otherwise modify any of the line items contained in the Contract.
NOW THEREFORE, the parties agree as follows:
Amendment No. 8
DEP Agency Term Contract No. GC831
5.
6.
The Rate Change Date is the date shown at the bottom of this Amendment for the Department’s
Data Processing Information. Prior to the Rate Change Date, the Department shall provide
Contractor a copy of the tabulated rate changes herein and showing the effective Rate Change
Date, within five (5) business days from the data entry date.
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK
All other terms and conditions of the Contract remain in effect. If and to the extent that any inconsistency may appear between the Contract and this Amendment, the provisions of this
Amendment shall control.
Pre-existing
Rate
Agreed
New Rate (1)
400.00$ $ 460.00
345.00$ $ 362.25
400.00$ $ 460.00
400.00$ $ 460.00
800.00$ $ 840.00
367.50$ $ 422.62
525.00$ $ 603.75
420.00$ $ 483.00
735.00$ $ 845.25
200.00$ $ 220.00
250.00$ $ 275.00
400.00$ $ 460.00
700.00$ $ 805.00
750.00$ $ 862.50
1,000.00$ $ 1,150.00
525.00$ $ 603.75
735.00$ $ 845.25
315.00$ $ 362.25
525.00$ $ 603.75
315.00$ $ 362.25
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
Pay
Item
No.
1-1.
1-2.
3-5.
3-6.
3-7.a.
3-8.a.
3-9.a.
3-10.a.
3-11.
File Review
Site Health & Safety Plan
Receptor Survey and Exposure Pathway
Identification (excludes report)
Site Reconnaissance/Field Measurement Visit
Mini Excavator/Loader (Bobcat
TM
) Mobilization - ≤
100 miles each way
Loader/Backhoe Mobilization - > 100 miles each way
Loader/Backhoe Mobilization - ≤ 100 miles each way
Drill Rig and Support Vehicles Mobilization (hollow stem auger, mud rotary or sonic) - ≤ 100 miles each way
DPT Rig and Support Vehicles Mobilization - > 100 miles each way
DPT Rig and Support Vehicles Mobilization - ≤ 100 miles each way
Work Trailer - > 100 miles each way
Work Trailer - ≤ 100 miles each way
Heavy Duty/Stakebed Truck (3/4 ton +) - > 100 miles each way
Heavy Duty/Stakebed Truck (3/4 ton +) - ≤ 100 miles each way
Mobilization, Light Duty Vehicle (car or 1/2 ton truck) - > 100 miles each way
Mobilization, Light Duty Vehicle (car or 1/2 ton truck) - ≤ 100 miles each way
Contractor Oversight for Non-Price Schedule
Activities
Excavator Mobilization - > 100 miles each way
Excavator Mobilization - ≤ 100 miles each way
Drill Rig and Support Vehicles Mobilization (hollow stem auger, mud rotary or sonic) - > 100 miles each way
Description
3-12.
Table 1. Listed Schedule of Pay Items with Rate Changes
2-1.
2-2.
2-4.
3-1.
3-2.
3-3.
3-4.
3-15.
3-16.
3-17.
Est %
Rate
Change (2)
+15.00%
+5.00%
+15.00%
+15.00%
+5.00%
+15.00%
+15.00%
+15.00%
+15.00%
+10.00%
+10.00%
+15.00%
+15.00%
500.00$ $ 575.00
500.00$ $ 575.00
600.00$ $ 690.00
30.00$ $ 33.00
35.00$ $ 38.50
100.00$ $ 115.00
2,100.00$ $ 2,415.00
3,000.00$ $ 3,300.00
25.00$ $ 27.50
29.50$ $ 32.45
35.00$ $ 38.50
29.50$ $ 32.45
31.50$ $ 34.65
36.75$ $ 40.43
36.75$ $ 40.43
42.00$ $ 46.20
47.25$ $ 51.97
31.50$ $ 34.65
35.00$ $ 38.50
41.00$ $ 45.10
38.00$ $ 41.80
+10.00%
+10.00%
+10.00%
+10.00%
+15.00%
+15.00%
+10.00%
+10.00%
+10.00%
+10.00%
+10.00%
+10.00%
+15.00%
+15.00%
+15.00%
+10.00%
+10.00%
5-2.
5-3.a.
5-5.a.
5-6.
5-7.
5-17.
5-18.
5-12.
5-13.
5-14.
5-15.
5-16.
5-8.
5-1.a.1.
5-1.a.2.
Split Spoon Sampling – 2 foot (during boring) 50 to
100 feet
Split Spoon Sampling – 2 foot (during boring) < 50 feet
Drum Compactor mobilization - > 100 miles each way
Drum Compactor mobilization - ≤ 100 miles each way
Mini Excavator/Loader (Bobcat
TM
) Mobilization - >
100 miles each way
Sonic Boring, > 6 to 10 inch diameter, < 50 foot total depth
Sonic Boring, ≤ 6 inch diameter, > 100 foot total depth
Sonic Boring, ≤ 6 inch diameter, 50 to 100 foot total depth
Sonic Boring, ≤ 6 inch diameter, < 50 foot total depth
HSA or MR Boring, > 10 to 14 inch diameter, > 100 foot total depth
HSA or MR Boring, > 10 to 14 inch diameter, 50 to
100 foot total depth
HSA or MR Boring, > 10 to 14 inch diameter, < 50 foot total depth
HSA or MR Boring, > 6 to 10 inch diameter, > 100 foot total depth
HSA or MR Boring, > 6 to 10 inch diameter, 50 to
100 foot total depth
HSA or MR Boring, > 6 to 10 inch diameter, < 50 foot total depth
HSA or MR Boring, ≤ 6 inch diameter, > 100 foot total depth
HSA or MR Boring, ≤ 6 inch diameter, 50 to 100 foot total depth
HSA or MR Boring, ≤ 6 inch diameter, < 50 foot total depth
DPT Membrane Interface Probe (MIP) Equipped with PID and ECD (add-on cost to DPT base rate)
Direct Push Technology (DPT) Rig and Equipment
Hand Auger Boring ≤ 10 foot total depth
3-18.
3-19.
3-20.
5-9.
5-10.
5-11. +10.01%
+10.01%
+10.00%
+9.99%
42.00$ $ 46.20
52.50$ $ 57.75
63.00$ $ 69.30
70.00$ $ 77.00
89.00$ $ 97.90
28.00$ $ 30.80
30.00$ $ 33.00
100.00$ $ 110.00
38.00$ $ 39.90
125.00$ $ 137.50
50.00$ $ 52.50
35.00$ $ 36.75
42.00$ $ 44.10
52.00$ $ 54.60
62.00$ $ 65.10
6.00$ $ 6.90
600.00$ $ 690.00
1,200.00$ $ 1,380.00
150.00$ $ 172.50
250.00$ $ 262.50
300.00$ $ 315.00
15.00$ $ 17.25
17.00$ $ 19.55
21.00$ $ 24.15
28.00$ $ 32.20
150.00$ $ 157.50
180.00$ $ 189.00
+5.00%
+5.00%
+15.00%
+15.00%
+15.00%
+15.00%
+5.00%
+5.00%
+15.00%
+15.00%
+15.00%
+10.00%
+10.00%
+10.00%
+10.00%
+10.00%
+10.00%
+10.00%
+10.00%
+5.00%
+10.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+15.00%
6-2.b.
5-19.
5-20.
5-21.
5-22.
5-23.
6-1.
6-2.a.
6-4.
6-3.a.
6-3.b.
Well Installation - 4 inch diameter (horizontal, by trenching, not directional drilling)
Well Installation - 4 inch diameter (vertical)
Well Installation - 2 inch diameter (horizontal, by trenching, not directional drilling)
Sonic Boring, > 10 to 14 inch diameter, > 100 foot total depth
Sonic Boring, > 10 to 14 inch diameter, 50 to 100 foot total depth
Sonic Boring, > 10 to 14 inch diameter, < 50 foot total depth
Well Installation - 2 inch diameter (vertical)
Grout and Abandon Well, > 6 inch diameter
Grout and Abandon Well, > 4 to 6 inch diameter
Grout and Abandon Well, > 2 to 4 inch diameter
Grout and Abandon Well, 1 to 2 inch diameter
Additional Well Screen > 20 feet - 1 inch diameter
Surface Casing - 12 inch diameter
Surface Casing - 10 inch diameter
Well Installation - 6 inch diameter
Surface Casing - 8 inch diameter
Surface Casing - 6 inch diameter
Sonic Boring, > 6 to 10 inch diameter, > 100 foot total depth
Sonic Boring, > 6 to 10 inch diameter, 50 to 100 foot total depth
Well Installation - 1 inch diameter
6-11.
6-12.
6-13.
6-14.
6-15.
7-7.
8-1.
6-6.
6-7.
6-8.
Well Redevelopment
Installation of Well Vault - 4 x 4 x 2 foot
Installation of Well Vault - 2 x 2 x 2 foot
6-9.a.
7-2.
7-3.
7-4.
7-1.
Removal and Reinstallation of 12-inch Manhole and
Well Pad (well pad/manhole has been damaged or destroyed)
Monitoring Well Sampling with Water Level, ≤ 100 foot depth
Removal of Well Pad and Manhole
Removal and Reinstallation of 8-inch Manhole and
Well Pad (well pad/manhole has been damaged or destroyed)
6-5.
200.00$ $ 210.00
75.00$ $ 78.75
75.00$ $ 78.75
75.00$ $ 78.75
52.50$ $ 60.37
20.00$ $ 21.00
100.00$ $ 105.00
50.00$ $ 57.50
25.00$ $ 26.25
25.00$ $ 26.25
17.50$ $ 18.37
412.50$ $ 474.37
44.00$ $ 46.20
60.61$ $ 63.64
75.00$ $ 78.75
85.00$ $ 89.25
85.50$ $ 89.77
205.00$ $ 215.25
70.71$ $ 74.24
227.00$ $ 238.35
60.00$ $ 69.00
+4.97%
+15.00%
+5.00%
+5.00%
+5.00%
+5.00%
+4.99%
+5.00%
+4.99%
+5.00%
+15.00%
+5.00%
+5.00%
+5.00%
+5.00%
+14.99%
+5.00%
+5.00%
+15.00%
Soil, PCBs [or Aroclors] (EPA 8082)
Soil, Priority Pollutant Volatile Organics (EPA 8260)
Soil, Polycyclic Aromatic Hydrocarbons (EPA 8270 or EPA 8310)
Soil, BTEX + MTBE + VOHs (EPA 8021 or EPA
8260)
Soil, TRPH Fractionation (MADEP-EPH/VPH
Method or TPHCWG Direct Method)
Soil, Total Recoverable Petroleum Hydrocarbons (FL-
PRO)
Soil, Priority Pollutant Extractable Organics-Base
Neutral and Acid Extractables (EPA 8270 list [e.g., EPA 8081/8082 + EPA 8270])
Survey Latitude/Longitude of New Monitor Wells
Survey Latitude/Longitude of Existing Monitor Wells
Vapor/Ambient Air Sample Collection -
SUMMATM Canister (or equivalent)
Free Product Gauging & Bailing
Water Level or Free Product Gauging
Soil/Sediment Sample Collection
Soil, Volatile Organic Halocarbons (EPA 8021 or
EPA 8260)
Soil, BTEX + MTBE (EPA 8021 or EPA 8260)
Soil, Used Oil/Unknown Product Group-Table D of
Ch. 62-780, F.A.C., except for non-Priority Pollutant
Organics (multiple methods)
Encore (25 gram) for SPLP Soil Sample Collection:
[Per Encore]. The cost will include the 25 gram
Encore samples submitted to the laboratory for SPLP testing and the 25 gram Encore samples collected in the field but not submitted to the laboratory for testing (discarded).
8-2.
8-13.
Free Product Sample Collection
Other Water Sampling
Domestic Water Well Sampling
Monitoring Well Sampling with Water Level, > 100 foot depth
8-14.
9-1.
9-2.
9-3.
9-4.
9-5.
9-6.
8-12.
8-3.
8-4.
8-5.
8-6.
8-7.
8-8.
8-10.
9-7.
9-8.
9-8.a.
9-9.
+5.00%
+5.00%
75.00$ $ 78.75
12.12$ $ 12.72
12.12$ $ 12.72
12.12$ $ 12.72
12.12$ $ 12.72
51.00$ $ 53.55
51.00$ $ 53.55
35.00$ $ 40.25
30.00$ $ 34.50
12.00$ $ 13.80
100.00$ $ 105.00
72.00$ $ 75.60
297.98$ $ 312.87
500.00$ $ 525.00
45.45$ $ 47.72
56.57$ $ 59.39
75.00$ $ 78.75
85.00$ $ 89.25
41.00$ $ 45.10
51.00$ $ 56.10
+5.00%
9-23.
9-25.
9-26.
9-27.
9-28.
9-29.
9-30.
9-31.
9-31.a.
Soil, Arsenic (EPA 6010 or EPA 6020)
Soil, 8 RCRA Metals (EPA 6010 or EPA 6020
[Arsenic, Barium, Cadmium, Chromium, Lead, Selenium, Silver] and EPA 6020 or EPA 7471
[Mercury])
Water, EDB [1,2-dibromoethane or ethylene dibromide] (EPA 8260 SIM)
Water, EDB [1,2-dibromoethane or ethylene dibromide] (EPA 504.1 or EPA 8011)
Water, Polycyclic Aromatic Hydrocarbons, including
1-methylnaphthalene + 2-methylnaphthalene (EPA
610 [HPLC], EPA 625, EPA 8270 or EPA 8310)
Water, BTEX + MTBE + VOHs (EPA 601/602, EPA
624, EPA 6021 or EPA 8260)
Water, Volatile Organic Halocarbons, except EDB
(EPA 8021 or EPA 8260)
Water, BTEX + MTBE (EPA 602, EPA 624, EPA
8021 or EPA 8260)
Soil, Moisture Content (ASTM D2216-10)
Soil, Dry Bulk Density (ASTM D1556-07, ASTM
D2167-08, ASTM D2922-01, -04, -04e, -96e1 or
ASTM D2937-10)
Soil, Organic Carbon, Total (EPA 9060 or Walkey-
Black)
Soil, Synthetic Precipitation Leaching Procedure-
Extraction Only (EPA1312)
Soil, Toxicity Characteristic Leaching Procedure-
Extraction Only (EPA 1311)
Water, Used Oil/Unknown Product Group-Table D of Ch. 62-780, F.A.C., except for non-Priority
Pollutant Organics (multiple methods)
Water, Gasoline/Kerosene Analytical Group-Table C of Ch. 62-780, F.A.C. (multiple methods)
Soil, 5 Fuel Oxygenates, MTBE, DIPE, TAME, ETBE and TBA (EPA 8260Mod, High Resolution
GC/MS)
Soil, Lead (EPA 6010 or EPA 6020)
Soil, Chromium (EPA 6010 or EPA 6020)
Soil, Cadmium (EPA 6010 or EPA 6020)
Soil, Texture, (See Gee 7 Bauder [1966])
9-16.
9-17.
9-18.
9-19.
9-20.
9-15.
9-10.
9-11.
9-12.
9-13.
9-14.
+15.00%
+15.00%
+5.00%
+5.00%
+5.00%
+5.00%
+4.99%
+4.98%
+5.00%
+5.00%
+10.00%
+10.00%
+4.95%
+4.95%
+4.95%
+4.95%
+5.00%
+5.00%
77.50$ $ 81.37
84.00$ $ 88.20
219.00$ $ 251.85
262.00$ $ 301.30
69.70$ $ 73.18
52.00$ $ 59.80
11.11$ $ 11.66
11.11$ $ 11.66
11.11$ $ 11.66
11.11$ $ 11.66
12.10$ $ 12.70
20.20$ $ 22.22
11.11$ $ 11.66
11.11$ $ 11.66
12.10$ $ 12.70
11.11$ $ 11.66
11.11$ $ 11.66
11.11$ $ 11.66 +4.95%
+15.00%
+15.00%
+4.99%
+15.00%
+4.95%
+4.95%
+4.95%
+4.95%
+4.96%
+10.00%
+4.99%
+5.00%
+4.95%
+4.95%
+4.96%
+4.95%
+4.95%
9-33.
9-34.
9-35.
9-36.
9-37.
9-38.
9-32.
9-41.
9-41.a.
9-42.
9-43.
9-44.
9-44.a.
9-45.
9-46.
9-47.
9-39.
9-40.
Water, Cadmium, Total (EPA 200.7, EPA 200.8, EPA 6010 or EPA 6020)
Water, Arsenic, Total (EPA 200.7, EPA 200.8, EPA
6010 or EPA 6020)
Water, Potassium, Total (EPA 200.7, EPA 6010 or
EPA 6020)
Water, Manganese, Total (EPA 200.7, EPA 200.8, EPA 6010 or EPA 6020)
Water, Magnesium, Total (EPA 200.7, EPA 6010 or
EPA 6020)
Water, Dissolved Iron (includes filter appropriate to sample method - EPA 200.7, 200.9, 6010B, or 7380)
Water, Iron, Total (EPA 200.7, EPA 6010 or EPA
6020)
Water, Calcium, Total (EPA 200.7, EPA 6010 or
EPA 6020)
Water, Mercury, Total (EPA 245.1, EPA 6020 or
EPA 7470)
Water, Dissolved Lead (includes filter appropriate to sample method - EPA 200.7, 200.9, 6010B, or 7380)
Water, Lead, Total (EPA 200.7, EPA 200.8, EPA
6010 or EPA 6020)
Water, Chromium, Total (EPA 200.7, EPA 200.8, EPA 6010 or EPA 6020)
Water, Priority Pollutant Volatile Organics [for
NPDES purposes only] (EPA 624)
Water, PCBs [or Aroclors] (EPA 608 or EPA 8082)
Water, Total Recoverable Petroleum Hydrocarbons
(FL-PRO)
Water, Priority Pollutant Extractable Organics-Base
Neutral and Acid Extractables (EPA 8270 list [e.g., EPA 8081/8082 + EPA 8270 or EPA 608 + EPA
8270)
Water, Priority Pollutant Extractable Organics-Base
Neutral and Acid Extractables [for NPDES purposes only] (EPA 625 list [e.g., EPA 608 + EPA 625])
Water, Priority Pollutant Volatile Organics (EPA
8260)
11.11$ $ 11.66
11.11$ $ 12.77
11.11$ $ 12.77
11.11$ $ 12.77
14.14$ $ 16.26
14.14$ $ 14.84
14.14$ $ 16.26
14.14$ $ 14.84
22.22$ $ 25.55
15.15$ $ 15.90
12.12$ $ 13.93
12.12$ $ 13.93
14.14$ $ 14.84
40.00$ $ 44.00
909.09$ $ 1,045.45
945.00$ $ 1,086.75
+4.95%
+14.94%
+14.94%
+14.94%
+14.99%
+4.95%
+14.99%
+4.95%
+14.99%
+4.95%
+14.93%
+14.93%
+4.95%
+10.00%
+15.00%
+15.00%
9-48.
Water, Sulfate (ASTM D516-02, ASTM D516-90, EPA 300.0, EPA 300.1, EPA 375.2, EPA 9038, EPA
9056 or SM 4500-SO4 C)
Water, Acute Bioassay-96 Hour, Estuarine + Marine, Vertebrate/Invertebrate [Vertebrate: Menidia beryllina, Meridia menidia or Menida peninsulae/Invertebrate: Mysidopsis bahia] (EPA
2006.0/2007.0)
Water, Acute Bioassay-96 Hour, Freshwater, Vertebrate/Invertebrate [Vertebrate: Pimephales promelas or Cyprinella leedsi/Invertebrate:
Ceriodaphnia dubia] (EPA 2000.0/2002.0)
Water, Heterotrophic Plate Count (SM 9215 B)
Water, Residue-nonfilterable [Total Suspended
Solids] (SM 2540 D)
Water, Residue-filterable [Total Dissolved Solids]
(SM 2540 C)
Water, Orthophosphate [as P] (EPA 300.0, EPA
300.1, EPA 365.1, EPA 365.3, EPA 9056, SM 4500-
PE or SM 4500-PF)
Water, Organic Carbon, Total (SM 5310 B, SM 5310
C or EPA 9060)
Water, Nitrite [as N] (EPA 300.0, EPA 300.1, SM
4500-NO2 B or SM 4500-NO3 F)
Water, Nitrate-Nitrite [as N] (EPA 300.0, EPA 353.2, SM 4500-NO3 E or SM 4500-NO3 F)
Water, Nitrate [as N] (EPA 300.0 or EPA 353.2)
Water, Hardness, Total [as CaCO3] (SM 2340 B or
SM 2340 C)
Water, Chloride (EPA 300.0, EPA 9056, EPA 9251, EPA 9053, SM 4500CI B, SM 4500CI C or SM
4500CI E)
Water, Ammonia [as N] (EPA 350.1, SM 4500-NH3
C, SM 4500-NH3 D, SM 4500-NH3 G or SM 4500-
NH3 H)
Water, Alkalinity [as CaCO3] (EPA 310.2 or SM
2320 B)
Water, Sodium, Total (EPA 200.7, EPA 6010 or
EPA 6020)
9-49.
9-50.
9-51.
9-52.
9-53.
9-54.
9-55.
9-56.
9-57.
9-58.
9-59.
9-60.
9-61.
9-62.
9-63.
77.00$ $ 80.85
230.00$ $ 241.50
66.00$ $ 69.30
45.00$ $ 47.25
101.00$ $ 106.05
90.91$ $ 95.45
242.42$ $ 254.54
242.42$ $ 278.78
247.47$ $ 284.59
353.54$ $ 250.00
654.55$ $ 250.00
20.00$ $ 23.00
12.00$ $ 13.20
30.00$ $ 34.50
36.00$ $ 39.60
32.00$ $ 33.60
33.00$ $ 36.30
30.00$ $ 33.00
+5.00%
+5.00%
+5.00%
+4.99%
+5.00%
+15.00%
+15.00%
-29.29%
+5.00%
+5.00%
10-15.
10-14.
Clean Backfill Material, Compaction and Testing
(includes transport) > 300 cubic yards
Clean Backfill Material, Compaction and Testing
(includes transport) ≤ 300 cubic yards
Sheet Piling Rental for ≤ 20 feet deep Excavation
Conventional Soil Excavation and Loading > 300 cubic yards
Conventional Soil Excavation and Loading ≤ 300 cubic yards
Sheet Piling Installation for > 20 feet deep
Excavation
Air, Polycyclic Aromatic Hydrocarbons (EPA
Method TO-13)
Air, Volatile Organic Aromatics (EPA Method TO-
15)
Product, GC/MS Full Scan, alkanes, isoalkanes, cycloalkanes, aromatics, bicyclane, sterane, and terpane biomarkers (ASTM D5739 High Resolution
GC/MS)
Product, C3-C44 Hydrocarbon Fingerprint, Gasoline
PIANO [paraffins, isoparaffins, aromatics, naphthenes and olefins], alkanes and isoalkanes
(ASTM D3328 High Resolution GC/FID)
Air, Volatile Organic Compounds (EPA Method TO-
17)
Sheet Piling Installation for ≤ 20 feet deep
Excavation
Air, Total Petroleum Hydrocarbons (EPA Method 18 or TO-3)
Water, Methane (EPA SOP RSK-175)
Water, EDC [1,2-dichloroethane] (EPA Method 8021 or 8260)
Water, BTEX/MTBE + Naphthalene (EPA 8260)
Water, C10-C40 Alkane Fingerprint, N-Alkanes and
Isoalkanes (ASTM D3328 GC/MS)
Water, 5 Fuel Oxygenates, MTBE, DIPE, TAME, ETBE and TBA (EPA 8260Mod, High Resolution
GC/MS)
9-67.
9-78.
9-79.
9-80.
9-68.
9-69.
9-70.
9-71.
10-7.
10-8.
9-66.
10-2.a.
9-72.
9-73.
10-1.a.
10-1.d.
+10.00%
+5.00%
+10.00%
+10.00%
-61.81%
+15.00%
+10.00%
16.00$ $ 17.60
16.00$ $ 17.60
60.00$ $ 66.00
46.00$ $ 50.60
2,730.00$ $ 3,139.50
210.00$ $ 241.50
7,350.00$ $ 8,452.50
315.00$ $ 362.25
3.65$ $ 4.01
2.50$ $ 2.87
40.00$ $ 42.00
38.00$ $ 39.90
50.00$ $ 52.50
147.00$ $ 169.05
25.20$ $ 27.72
38.00$ $ 41.80
30.80$ $ 33.88
30.00$ $ 33.00
32.00$ $ 36.80
30.00$ $ 34.50
147.00$ $ 169.05
1.10$ $ 1.21
175.00$ $ 201.25
+10.00%
+10.00%
+10.00%
+10.00%
+15.00%
+15.00%
+15.00%
+10.00%
+15.00%
+15.00%
+15.00%
+15.00%
+10.00%
+15.00%
+9.86%
+14.80%
+5.00%
+5.00%
+5.00%
+15.00%
10-15.a.
10-15.b.
10-16.
12-8.
12-1.
12-2.
12-9.
12-10.
12-11.
12-12.
12-13.
12-14.
12-15.
10-18.
10-19.
10-20.
10-21.
10-17.
Disposal of Petroleum Impacted Soil at a Landfill
(bulk) ≤ 450 tons
Transport Petroleum Impacted Soil (bulk) > 100 miles
Transport and Disposal of Petroleum Product
(includes drum)
Transport and Disposal of Petroleum Contact Water
(bulk)
Transport and Disposal of Petroleum Contact Water
(includes drum)
Disposal of Petroleum Impacted Soil at a Thermal
Treatment Facility (bulk) > 450 tons
Disposal of Petroleum Impacted Soil at a Thermal
Treatment Facility (bulk) ≤ 450 tons
Disposal of Petroleum Impacted Soil at a Landfill
(bulk) > 450 tons
Transport Petroleum Impacted Soil (bulk) ≤ 100 miles
Transport and Disposal of Petroleum Impacted Soil
(includes drum)
Transport and Disposal of Mixed Debris
Transport and Disposal of Clean Concrete
Loading, Transport and Disposal/Recycle Clean
Overburden
Additional Removal/Loading Cost for Concrete - > 4 inch thickness
Removal and Loading of Asphalt and/or Concrete -up to 4 inch thickness
#57 Stone
Pea Gravel
Clean Overburden Used As Backfill, Compaction and Testing > 300 cubic yards
Clean Overburden Used As Backfill, Compaction and Testing ≤ 300 cubic yards
Additional Dewatering System Well Points (2)
(includes installation)
Dewatering System, up to 12 well points (includes installation)
Additional Dewatering System Well Points (2)
(includes installation)
Dewatering System, up to 12 well points (includes installation)
12-3.
12-4.
12-5.
12-6.
12-7.
+10.00%
+10.00%
+10.00%
1.10$ $ 1.21
750.00$ $ 862.50
200.00$ $ 230.00
7.00$ $ 8.05
2.00$ $ 2.30
8.00$ $ 9.20
2.00$ $ 2.30
1.75$ $ 2.01
1.20$ $ 1.38
0.50$ $ 0.57
3,460.00$ $ 3,979.00
8,000.00$ $ 9,200.00
75.00$ $ 78.75
75.00$ $ 78.75
75.00$ $ 78.75
15.00$ $ 15.75
3,150.00$ $ 3,622.50
6,300.00$ $ 7,245.00
7,350.00$ $ 8,452.50
1,050.00$ $ 1,207.50
2,500.00$ $ 2,875.00
4,000.00$ $ 4,200.00
+15.00%
+5.00%
+10.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+14.86%
+15.00%
+14.00%
+15.00%
15-4.a.
15-4.b.
15-4.c.
15-4.d.
15-5.
15-1.d.
12-16.
14-2.a.
12-17.
12-18.
13-1.
13-2.
13-3.
13-4.
13-5.
13-6.
13-7.
Groundwater Recovery System Pilot Test - 8 hours
Concrete Paving - additional 1 inch thickness
Concrete Paving - 4 inch thickness (includes sub-base)
Asphalt Paving - additional 1 inch thickness
Trenching and Installation of 21 - 30 Lines
Trenching and Installation of 11 - 20 Lines
System Installation/Integration/Startup – Addition of
1 Technology Component
System Installation/Integration/Startup - 1
Technology Component - 1-10 Additional
Recovery/Treatment Points greater Than 30 (This item is used in conjunction with 15.4.c when needed)
System Installation/Integration/Startup - 1
Technology Component - 21-30 Recovery/Treatment
Points
System Installation/Integration/Startup - 1
Technology Component - 11-20 Recovery/Treatment
Points
System Installation/Integration/Startup - 1
Technology Component - 1-10 Recovery/Treatment
Points
Trenching and Installation of Additional 1-10 Lines
Greater Than 30 Lines
Trenching and Installation of 1-10 Plumbing (and
Electrical) Lines in Trench
Groundwater Injection System (not by direct push)
In-Situ Injection Into Existing Well/Treatment Point
Grass - Seed and Mulch
Grass - Sod
Crushed Lime Rock Cover - 2 inch thickness
Asphalt Paving - 2 inch thickness (includes sub-base)
Additional Rental of 20 Cubic Yard Roll-Off
Container
Delivery, Pick Up and Rental of 20 Cubic Yard Roll-
Off Container
Transport and Disposal of Petroleum Product (bulk)
14-5.
15-1.a.
15-1.b.
15-1.c.
16-1. +5.00%
+5.00%
+5.00%
+5.00%
+15.00%
+15.00%
+15.00%
+15.00%
500.00$ $ 525.00
3,000.00$ $ 3,150.00
500.00$ $ 525.00
3,200.00$ $ 3,360.00
500.00$ $ 525.00
3,500.00$ $ 3,675.00
500.00$ $ 525.00
3,500.00$ $ 3,675.00
500.00$ $ 525.00
4,000.00$ $ 4,200.00
500.00$ $ 525.00
4,500.00$ $ 4,724.00
500.00$ $ 525.00
3,150.00$ $ 3,622.50
8,400.00$ $ 9,660.00
1,575.00$ $ 1,811.25
5,250.00$ $ 6,037.50
3,000.00$ $ 3,450.00
3,000.00$ $ 3,450.00
7,500.00$ $ 8,625.00
3,500.00$ $ 4,025.00
8,000.00$ $ 9,200.00
3,000.00$ $ 3,450.00
5,000.00$ $ 5,750.00
7,000.00$ $ 8,050.00
2,520.00$ $ 2,898.00
1,890.00$ $ 2,173.50
2,940.00$ $ 3,381.00
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
Air Sparge System - Medium - Short Term ≤ 6 mos.
Air Sparge System - Small - Long Term > 6 mos.
Air Sparge System - Small - Short Term ≤ 6 mos.
Groundwater Treatment System - Stand Alone Large -
Long Term > 6 mos.
Multi-Phase Pilot Test - 8 hours
Air Sparging/Vapor Extraction Pilot Test -
Additional Time
Air Sparging/Vapor Extraction Pilot Test - 8 hours
SVE System Package - Medium
SVE System Package - Medium
AS/MPE System Package - Medium
AS/MPE System Package - Medium
MPE System Package - Medium
MPE System Package - Medium
AS/SVE System Package - Medium
Air Sparge System Package - Medium
Air Sparge System Package - Medium
Groundwater Treatment System Package - Medium
Groundwater Treatment System Package - Medium
Air Sparging/Multiphase Extraction Pilot Test -
Additional Time
Air Sparging/Multiphase Extraction Pilot Test - 8 hours
Multi-Phase Pilot Test - Additional Time
Vapor Extraction/Aquifer Pumping Test - Additional
Time
Vapor Extraction/Aquifer Pumping Test - 8 hours
Vapor Extraction Pilot Test - Additional Time
Vapor Extraction Pilot Test - 8 hours
Air Sparging or Biosparging Pilot Test - Additional
Time
Air Sparging or Biosparging Pilot Test - 8 hours
Groundwater Recovery System Pilot Test -
Additional Time 16-2.
16-3.
16-4.
16-5.
16-18.
16-17.
16-6.
16-7.
16-8.
16-9.
16-10.
16-11.
16-12.
16-13.
16-14.
16-19.
16-20.
16-21.
16-23.
16-24.
16-25.
18-10.
16-26.
16-27.
16-28.
18-11.
18-12.
18-13.
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+4.98%
2,100.00$ $ 2,415.00
4,200.00$ $ 4,830.00
3,150.00$ $ 3,622.50
5,000.00$ $ 5,500.00
3,150.00$ $ 3,622.50
5,500.00$ $ 6,050.00
4,000.00$ $ 4,600.00
6,300.00$ $ 7,245.00
4,200.00$ $ 4,830.00
3,675.00$ $ 4,226.25
2,835.00$ $ 3,260.25
5,250.00$ $ 5,775.00
4,200.00$ $ 4,620.00
6,300.00$ $ 6,930.00
5,299.00$ $ 5,828.90
4,000.00$ $ 4,400.00
3,500.00$ $ 3,850.00
6,500.00$ $ 7,150.00
3,000.00$ $ 3,450.00
4,500.00$ $ 4,950.00
4,725.00$ $ 5,433.75
500.00$ $ 575.00
600.00$ $ 690.00
840.00$ $ 966.00
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+10.00%
+10.00%
+10.00%
+10.00%
+10.00%
+10.00%
+10.00%
+15.00%
+10.00%
+15.00%
+15.00%
+15.00%
+15.00%
+10.00%
+15.00%
+10.00%
18-29.
18-30.
18-31.
18-32.
18-33.
18-34.
18-35.
18-36.
18-37.
18-23.
18-24.
18-25.
18-26.
18-27.
18-28.
Carbon Off Gas Treatment - Add On - Large - Short
Term ≤ 6 mos.
Carbon Off Gas Treatment - Add On - Medium -
Short Term ≤ 6 mos.
Carbon Off Gas Treatment - Add On - Small - Short
Term ≤ 6 mos.
Groundwater Treatment - Add On - Large - Long
Term > 6 mos.
Groundwater Treatment - Add On - Medium - Long
Term > 6 mos.
Groundwater Treatment - Add On - Small - Long
Term > 6 mos.
Groundwater Treatment - Add On - Large - Short
Term ≤ 6 mos.
Groundwater Treatment - Add On - Medium - Short
Term ≤ 6 mos.
Groundwater Treatment - Add On - Small - Short
Term ≤ 6 mos.
MPE System - Large - Long Term > 6 mos.
MPE System - Large - Short Term ≤ 6 mos.
MPE System - Medium - Long Term > 6 mos.
MPE System - Medium - Short Term ≤ 6 mos.
MPE System - Small - Long Term > 6 mos.
MPE System - Small - Short Term ≤ 6 mos.
AS/SVE System - Large - Long Term > 6 mos.
AS/SVE System - Large - Short Term ≤ 6 mos.
AS/SVE System - Medium - Long Term > 6 mos.
AS/SVE System - Medium - Short Term ≤ 6 mos.
AS/SVE System - Small - Long Term > 6 mos.
AS/SVE System - Small - Short Term ≤ 6 mos.
Air Sparge System - Large - Long Term > 6 mos.
Air Sparge System - Large - Short Term ≤ 6 mos.
Air Sparge System - Medium - Long Term > 6 mos.
18-21.
18-22.
18-20.
18-14.
18-15.
18-16.
18-17.
18-18.
18-19.
+15.00%
250.00$ $ 287.50
300.00$ $ 345.00
420.00$ $ 483.00
3,400.00$ $ 3,910.00
3,700.00$ $ 4,255.00
5,500.00$ $ 6,325.00
3,000.00$ $ 3,450.00
3,500.00$ $ 4,025.00
5,000.00$ $ 5,750.00
3,000.00$ $ 3,450.00
3,200.00$ $ 3,680.00
3,500.00$ $ 4,025.00
5,500.00$ $ 6,325.00
3,700.00$ $ 4,255.00
6,500.00$ $ 7,475.00
4,300.00$ $ 4,945.00
8,000.00$ $ 9,200.00
5,500.00$ $ 6,325.00
1,500.00$ $ 1,650.00
3,150.00$ $ 3,465.00
1,575.00$ $ 1,732.50
1,000.00$ $ 1,050.00
1,000.00$ $ 1,050.00
600.00$ $ 630.00
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+15.00%
+10.00%
+10.00%
+10.00%
+5.00%
+5.00%
+5.00%
18-40.
18-41.
18-42.
18-38.
18-39.
Natural Attenuation or Post RA Monitoring Report, Quarterly or Non-Annual
Level 2 Natural Attenuation Monitoring Plan
Receptor and Exposure Pathway Report
Soil Vapor Extraction (SVE) System - Medium -
Long Term > 6 Months
Supplemental Site Assessment Report
General Site Assessment Report
Soil Source Removal Report
Air Sparge/Multiphase Extraction (AS/MPE) System -
Large - Long Term > 6 Months
Air Sparge/Multiphase Extraction (AS/MPE) System -
Large - Short Term ≤ 6 Months
Air Sparge/Multiphase Extraction (AS/MPE) System -
Medium - Long Term > 6 Months
Air Sparge/Multiphase Extraction (AS/MPE) System -
Medium - Short Term ≤ 6 Months
Air Sparge/Multiphase Extraction (AS/MPE) System -
Small - Long Term > 6 Months
Air Sparge/Multiphase Extraction (AS/MPE) System -
Small - Short Term ≤ 6 Months
Soil Vapor Extraction (SVE) System - Large - Long
Term > 6 Months
Soil Vapor Extraction (SVE) System - Small - Long
Term > 6 Months
Thermox/Catox Off Gas Treatment - Add On - Large -
Long Term > 6 mos.
Thermox/Catox Off Gas Treatment - Add On -
Medium - Long Term > 6 mos.
Thermox/Catox Off Gas Treatment - Add On - Small -
Long Term > 6 mos.
Thermox/Catox Off Gas Treatment - Add On - Large -
Short Term ≤ 6 mos.
Thermox/Catox Off Gas Treatment - Add On -
Medium - Short Term ≤ 6 mos.
Thermox/Catox Off Gas Treatment - Add On - Small -
Short Term ≤ 6 mos.
Carbon Off Gas Treatment - Add On - Large - Long
Term > 6 mos.
Carbon Off Gas Treatment - Add On - Medium -
Long Term > 6 mos.
Carbon Off Gas Treatment - Add On - Small- Long
Term > 6 mos.
18-43.
18-44.
18-45.
18-46.
18-57.
18-58.
19-1.
19-3.
19-4.
19-5.
19-6.
19-7.
18-56.
18.48.
18-50.
18-52.
18-53.
18-54.
18-55.
+15.00%
1,100.00$ $ 1,210.00
836.50$ $ 878.32
1,365.00$ $ 1,433.25
10,000.00$ $ 11,000.00
14,000.00$ $ 14,700.00
1,500.00$ $ 1,575.00
2,800.00$ $ 2,940.00
4,500.00$ $ 4,950.00
8,000.00$ $ 8,400.00
3,300.00$ $ 3,465.00
650.00$ $ 682.50
2,500.00$ $ 2,625.00
305.00$ $ 320.25
1,575.00$ $ 1,732.50
2,100.00$ $ 2,415.00
1,100.00$ $ 1,155.00
500.00$ $ 575.00
480.00$ $ 504.00
286.65$ $ 300.98
1,500.00$ $ 1,575.00
140.00$ $ 147.00
110.00$ $ 115.50
100.00$ $ 105.00
95.00$ $ 99.75
95.00$ $ 99.75
80.00$ $ 84.00
72.00$ $ 75.60
75.00$ $ 78.75
55.00$ $ 57.75
48.00$ $ 50.40
45.00$ $ 47.25
130.00$ $ 136.50
125.00$ $ 131.25
120.00$ $ 126.00
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+10.00%
+10.00%
+5.00%
+5.00%
+10.00%
21-2.
21-3.
Level 4 Limited Scope Remedial Action Plan or RAP
Modification Plan
Level 3 Limited Scope Remedial Action Plan or RAP
Modification Plan
Level 2 Limited Scope Remedial Action Plan or RAP
Modification Plan
Level 1 Limited Scope Remedial Action Plan or RAP
Modification Plan
Level 2 Remedial Action Plan
Assistant Scientist/Technical Specialist
Scientist/Technical Specialist (Key)
Hydrogeologist/Modeler (Key)
Geologist/Geoscientist (Key)
Engineer (Key)
Project Manager (Key)
Program Manager (Key)
Interim Assessment Report
Well Abandonment/Site Restoration Report
Free Product Recovery Report
Remedial Action Interim Report
Remedial Action General Report
Operation & Maintenance Annual Report
Operation & Maintenance Report, Quarterly or Non-
Annual
Letter/NPDES Report
Level 1 Remedial Action Plan
Pilot Test Report
Pilot Test Plan
Natural Attenuation or Post RA Monitoring Report, Annual
Construction Drawings and Specs Report
P.G. Field Oversight of Drilling and Boring and Soil-
Boring Logging (Use hourly rate on site specific basis)
Remedial Action Startup Report
As-Built Drawings (P.E. Sealed red lined modifications)
Professional Geologist (Key)
Professional Engineer (Key)
Laborers and Security Guards
Administrative
Draftsperson
Field Technician (Key)
19-18.
19-19.
19-20.
19-21.
19-22.
19-23.
19-24.
19-25.
20-9.
20-10.
20-11.
21-1.
19-17.
19-8.
19-9.
19-10.
19-11.
19-12.
19-13.
19-14.
19-15.
19-16.
20-8.
19-26.
19-27.
20-1.
20-2.
20-3.
20-4.
20-5.
20-6.
20-7.
+5.00%
+10.00%
+15.00%
+5.00%
+15.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
120.00$ $ 126.00
682.50$ $ 716.62
1,092.00$ $ 1,146.60
273.00$ $ 286.65
682.50$ $ 716.62
546.00$ $ 573.30
1,040.00$ $ 1,196.00
845.00$ $ 887.25
260.00$ $ 299.00
130.00$ $ 136.50
130.00$ $ 136.50
130.00$ $ 136.50
260.00$ $ 273.00
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+5.00%
+15.00%
+5.00%
21-4.
21-11.
21-12.
21-16.
21-17.
21-18.
21-19.
21-20.
21-6.a.
21-6.b.
21-7.a.
21-7.b.
21-8.
P.G. or Qualified P.E. Review, Evaluation and
Certification of a Supplemental Site Assessment
Report
P.G. Review, Evaluation and Certification of Plans and Project Oversight for Installation of Engineering
Controls Limited to Permanent, Impermeable Surface or Top Two Feet of Clean Fill Required for a
Conditional NFA
P.E. Design and Certification of Plans and Project
Oversight of Installation for Engineering Controls
(other than permanent, impermeable surface or top two feet of clean fill) required for a conditional NFA
P.E. Review, Evaluation and Certification of a Non-
Annual Natural Attenuation or Post RA Monitoring
Report That Includes a Recommendation for NFA or a Recommendation to Modify the Approved
Monitoring Plan
P.E. Review, Evaluation and Certification of a Level
2 Natural Attenuation Monitoring Plan
P.G. or P.E. Review, Evaluation and Certification of a Receptor and Exposure Pathway Report
P.E. Project Oversight for Remediation System
Operation and Maintenance
P.E. Project Oversight for Short Term or Episodic
Remediation System Operation - Weekly Basis
P.E. Project Oversight for Short Term or Episodic
Remediation System Operation - Daily Basis
P.E. Project Oversight for Remediation System
Integration and Startup - Medium System
P.E. Project Oversight for Remediation System
Integration and Startup - Small System
P.G. Field Oversight of Well Installation (Use hourly rate on site specific basis)
P.G or P.E. Review, Evaluation and Certification of an Annual Natural Attenuation Monitoring Report
+15.00%
+5.00%
+5.00%
+5.00%
500.00$ $ 525.00
273.00$ $ 286.65
1,820.00$ $ 1,911.00
2,080.00$ $ 2,184.00
273.00$ $ 286.65
260.00$ $ 273.00
500.00$ $ 550.00
260.00$ $ 299.00
+5.00%
+5.00%
+10.00%
+15.00%
21-21.
21-22.
21-23.
21-24.
P.E. Review, Evaluation and Certification of a Level
2 Remedial Action Plan
P.G or P.E. Review, Evaluation and Certification of a
Remedial Action General Report
P.E. Review, Evaluation and Certification of an
Annual Operation and Maintenance Report
Notes:
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK
(1)
The Agreed New Rate(s) shall be effective on and after the Rate Change Date as indicated for table labeled Department Data Processing Information below.
(2)
The column indicating estimated Percentage Rate Change is for informational purposes only and shall not supersede the actual Agreed New Rate. The Agreed New Rate is the maximum rate authorized for payment.
P.E. Review, Evaluation and Certification of a Level
1 Remedial Action Plan
P.E. Review, Evaluation and Certification of a Pilot
Test Report
P.E. Review, Evaluation and Certification of a Pilot
Test Plan
P.E. Review, Evaluation, and Certification of Annual
PARM Report
P.E. Review, Evaluation, and Certification of
Construction Drawings
21-32.
21-33.
21-35.
21-36.
+5.00%
+5.00%
+5.00%
5/25/2022
John Truitt Digitally signed by John Truitt Date: 2022.05.18 09:53:25 -04'00'
Jamie Luten Lopez
Digitally signed by Jamie Luten Lopez Date: 2022.05.25 13:54:11 -04'00'
PAY
ITEM
UNIT OF MEASURE
ORIGINAL
CONTRACTED
ITEM PRICE 2014
PREVIOUS
CONTRACTED ITEM
PRICE (V3.1)
REVISED
CONTRACTED
ITEM PRICE (V3.2)
1.
1-1. Per Review $ 400.00 $ 400.00 $ 460.00
1-2. Per Site $ 345.00 $ 345.00 $ 362.25
1-2.a. Per Site Not Applicable $ - $ -
1-3. Per Package $ 290.00 $ 290.00 $ 290.00
1-4. Reimbursable* $ 1.00 $ 1.00 $ 1.00
1-5. Per Agreement $ 350.00 $ 350.00 $ 350.00
1-5.a. Per Agreement Not Applicable $ - $ -
1-6. Reimbursable* $ 1.00 $ 1.00 $ 1.00
1-7. % Surcharge Not Applicable $ 0.06 $ 0.06
2.
2-1. Per Visit $ 400.00 $ 400.00 $ 460.00
2-2. Per Survey $ 400.00 $ 400.00 $ 460.00
2-3. Reimbursable* $ 1.00 $ 1.00 $ 1.00
2-4. Per Day $ 800.00 $ 800.00 $ 840.00
3.
3-1. Per Round Trip $ 350.00 $ 367.50 $ 422.62
3-2. Per Round Trip $ 500.00 $ 525.00 $ 603.75
3-3. Per Round Trip $ 400.00 $ 420.00 $ 483.00
3-4. Per Round Trip $ 700.00 $ 735.00 $ 845.25
3-5. Per Round Trip $ 200.00 $ 200.00 $ 220.00
3-6. Per Round Trip $ 250.00 $ 250.00 $ 275.00
DESCRIPTION
OFFICE ACTIVITIES
File Review
Site Health & Safety Plan
Site Health & Safety Plan for Continued Work at no cost to FDEP
Notice of Discovery of Contamination Package (Initial or TPOC)
Site Reconnaissance/Field Measurement Visit
Receptor Survey and Exposure Pathway Identification (Excludes report)
Professional Land Survey (If FDEP authorizes, submit quote(s) with Change Order)
Contractor Oversight for Non-Price Schedule Activities
MOBILIZATION
Mobilization, Light Duty Vehicle (car or 1/2 ton truck) - ≤ 100 miles each way
Permit Fees - actual fee only, cost to obtain permit is included in applicable pay items
Off-Site Property Access Agreement
Site Property Access Agreement for Source Property at no cost to FDEP
Project Specific Financial Guarantee Bond (if required by DEP)
6% Handling Fee for Cost Reimbursable Items
FIELD ACTIVITIES - GENERAL
Mobilization, Light Duty Vehicle (car or 1/2 ton truck) - > 100 miles each way
Heavy Duty/Stakebed Truck (3/4 ton +) - ≤ 100 miles each way
Heavy Duty/Stakebed Truck (3/4 ton +) - > 100 miles each way
Work Trailer - ≤ 100 miles each way
Work Trailer - > 100 miles each way
Region:
Contractor:
Contract #:
North
WATER & AIR RESEARCH, INC.
GC831
DEP Restated Agency Term Contract No. GC831
Amendment No. 8
Attachment D (V3.2) - Rate Schedule
UNIT OF MEASURE
ORIGINAL
CONTRACTED
ITEM PRICE 2014
PREVIOUS
CONTRACTED ITEM
PRICE (V3.1)
REVISED
CONTRACTED
ITEM PRICE (V3.2)
DESCRIPTION
Region:
Contractor:
Contract #:
North
WATER & AIR RESEARCH, INC.
GC831
DEP Restated Agency Term Contract No. GC831
Amendment No. 8
Attachment D (V3.2) - Rate Schedule
3-7. Per Round Trip $ 505.05 Not Applicable Not Applicable
3-7.a. Per Round Trip Not Applicable $ 400.00 $ 460.00
3-8. Per Round Trip $ 800.00 Not Applicable Not Applicable
3-8.a. Per Round Trip Not Applicable $ 700.00 $ 805.00
3-9. Per Round Trip $ 606.06 Not Applicable Not Applicable
3-9.a. Per Round Trip Not Applicable $ 750.00 $ 862.50
3-10. Per Round Trip $ 707.00 Not Applicable Not Applicable
3-10.a. Per Round Trip Not Applicable $ 1,000.00 $ 1,150.00
3-11. Per Round Trip $ 500.00 $ 525.00 $ 603.75
3-12. Per Round Trip $ 700.00 $ 735.00 $ 845.25
3-13. Per Round Trip $ 8,250.00 Not Applicable Not Applicable
3-13.a. Per Round Trip Not Applicable $ 18,000.00 $ 18,000.00
3-14. Per Round Trip $ 11,000.00 Not Applicable Not Applicable
3-14.a. Per Round Trip Not Applicable $ 24,000.00 $ 24,000.00
3-15. Per Round Trip $ 300.00 $ 315.00 $ 362.25
3-16. Per Round Trip $ 500.00 $ 525.00 $ 603.75
3-17. Per Round Trip $ 300.00 $ 315.00 $ 362.25
3-18. Per Round Trip $ 500.00 $ 500.00 $ 575.00
3-19. Per Round Trip Not Applicable $ 500.00 $ 575.00
3-20. Per Round Trip Not Applicable $ 600.00 $ 690.00
DPT Rig and Support Vehicles Mobilization - ≤ 100 miles each way
DPT Rig Mobilization - > 100 miles each way
DPT Rig and Support Vehicles Mobilization - > 100 miles each way
Drill Rig Mobilization - ≤ 100 miles each way
Drill Rig and Support Vehicles Mobilization (hollow stem auger, mud rotary or sonic) - ≤
100 miles each way
Drill Rig Mobilization - > 100 miles each way
DPT Rig Mobilization - ≤ 100 miles each way
LDA Rig and Support Vehicles Mobilization - > 100 miles each way
Loader/Backhoe Mobilization - ≤ 100 miles each way
Loader/Backhoe Mobilization - > 100 miles each way
Mini Excavator/Loader (Bobcat
TM
) Mobilization - ≤ 100 miles each way
Mini Excavator/Loader (Bobcat
TM
) Mobilization - > 100 miles each way
Drum Compactor mobilization - ≤ 100 miles each way
Drill Rig and Support Vehicles Mobilization (hollow stem auger, mud rotary or sonic) - >
100 miles each way
Excavator Mobilization - ≤ 100 miles each way
Excavator Mobilization - > 100 miles each way
LDA Rig Mobilization - ≤ 100 miles each way
LDA Rig and Support Vehicles Mobilization - ≤ 100 miles each way
LDA Rig Mobilization - > 100 miles each way
Drum Compactor mobilization - > 100 miles each way
UNIT OF MEASURE
ORIGINAL
CONTRACTED
ITEM PRICE 2014
PREVIOUS
CONTRACTED ITEM
PRICE (V3.1)
REVISED
CONTRACTED
ITEM PRICE (V3.2)
DESCRIPTION
Region:
Contractor:
Contract #:
North
WATER & AIR RESEARCH, INC.
GC831
DEP Restated Agency Term Contract No. GC831
Amendment No. 8
Attachment D (V3.2) - Rate Schedule
4.
4-1.a.
Per Person, Per Day $ 80.00 $ 80.00 $ 80.00
4-1.b. Reimbursable* $ 1.00 $ 1.00 $ 1.00
5.
5-1.a. Per Spoon $ 32.00 Not Applicable Not Applicable
5-1.a.1. Per Spoon Not Applicable $ 30.00 $ 33.00
5-1.a.2. Per Spoon Not Applicable $ 35.00 $ 38.50
5-1.a.3. Per Spoon Not Applicable $ 50.00 $ 50.00
5-1.b. Per Core $ 125.00 $ 125.00 $ 125.00
5-1.c. Per Core $ 18.35 Not Applicable Not Applicable
5-2. Per Boring $ 100.00 $ 100.00 $ 115.00
5-3. Per Foot $ 16.00 Not Applicable Not Applicable
5-3.a. Full Day Not Applicable $ 2,100.00 $ 2,415.00
5-4. Per Foot $ 27.00 Not Applicable Not Applicable
5-5. Per Foot $ 34.50 Not Applicable Not Applicable
5-5.a. Full Day Not Applicable $ 3,000.00 $ 3,300.00
5-6. Per Foot $ 25.00 $ 25.00 $ 27.50
Split Spoon Sampling – 2 foot (during boring) < 50 feet
Split Spoon Sampling – 2 foot (during boring) 50 to 100 feet
Split Spoon Sampling – 2 foot (during boring) > 100 feet
Sonic Core Sampling - 5 or 10 foot (during boring)
DPT Core Sampling - 4 or 5 foot (during boring)
Hand Auger Boring ≤ 10 foot total depth
MEALS AND LODGING
Per Diem - For Travel > 1 Consecutive day (prorated in quarter day increments)-Current
State Rate 112.061, F.S. Travel Voucher required and quoted rate should be per person per day.
Meals, Lodging and Transportation - For Contractor travel for specific meetings or legal proceedings required by Department, hotel and meals may be paid in accordance with
Section 112.061, F.S.
DRILLING AND BORING
Split Spoon Sampling - 2 foot (during boring)
Direct Push Boring
Direct Push Technology (DPT) Rig and Equipment
Direct Push Boring with Cone Penetrometer Test Probe (CPT)
Direct Push Boring with Membrane Interface Probe (MIP)
DPT Membrane Interface Probe (MIP) Equipped with PID and ECD (Add-on Cost to DPT
Base Rate)
HSA or MR Boring, ≤ 6 inch diameter, < 50 foot total depth
UNIT OF MEASURE
ORIGINAL
CONTRACTED
ITEM PRICE 2014
PREVIOUS
CONTRACTED ITEM
PRICE (V3.1)
REVISED
CONTRACTED
ITEM PRICE (V3.2)
DESCRIPTION
Region:
Contractor:
Contract #:
North
WATER & AIR RESEARCH, INC.
GC831
DEP Restated Agency Term Contract No. GC831
Amendment No. 8
Attachment D (V3.2) - Rate Schedule
5-7. Per Foot $ 29.50 $ 29.50 $ 32.45
5-8. Per Foot $ 35.00 $ 35.00 $ 38.50
5-9. Per Foot $ 29.50 $ 29.50 $ 32.45
5-10. Per Foot $ 30.00 $ 31.50 $ 34.65
5-11. Per Foot $ 35.00 $ 36.75 $ 40.43
5-12. Per Foot $ 35.00 $ 36.75 $ 40.43
5-13. Per Foot $ 40.00 $ 42.00 $ 46.20
5-14. Per Foot $ 45.00 $ 47.25 $ 51.97
5-15. Per Foot $ 30.00 $ 31.50 $ 34.65
5-16. Per Foot $ 35.00 $ 35.00 $ 38.50
5-17. Per Foot $ 41.00 $ 41.00 $ 45.10
5-18. Per Foot $ 38.00 $ 38.00 $ 41.80
5-19. Per Foot $ 40.00 $ 42.00 $ 46.20
5-20. Per Foot $ 50.00 $ 52.50 $ 57.75
5-21. Per Foot $ 60.00 $ 63.00 $ 69.30
5-22. Per Foot $ 70.00 $ 70.00 $ 77.00
5-23. Per Foot $ 89.00 $ 89.00 $ 97.90
6.
6-1. Per Foot $ 28.00 $ 28.00 $ 30.80
6-2. Per Foot $ 32.25 Not Applicable Not Applicable
6-2.a. Per Foot Not Applicable $ 30.00 $ 33.00
6-2.b. Per Foot Not Applicable $ 100.00 $ 110.00
HSA or MR Boring, ≤ 6 inch diameter, 50 to 100 foot total depth
HSA or MR Boring, ≤ 6 inch diameter, > 100 foot total depth
HSA or MR Boring, > 6 to 10 inch diameter, < 50 foot total depth
HSA or MR Boring, > 6 to 10 inch diameter, 50 to 100 foot total depth
HSA or MR Boring, > 6 to 10 inch diameter, > 100 foot total depth
HSA or MR Boring, > 10 to 14 inch diameter, < 50 foot total depth
Sonic Boring, > 6 to 10 inch diameter, 50 to 100 foot total depth
Sonic Boring, > 6 to 10 inch diameter, > 100 foot total depth
Sonic Boring, > 10 to 14 inch diameter, < 50 foot total depth
Sonic Boring, > 10 to 14 inch diameter, 50 to 100 foot total depth
Sonic Boring, > 10 to 14 inch diameter, > 100 foot total depth
WELL INSTALLATION
HSA or MR Boring, > 10 to 14 inch diameter, 50 to 100 foot total depth
HSA or MR Boring, > 10 to 14 inch diameter, > 100 foot total depth
Sonic Boring, ≤ 6 inch diameter, < 50 foot total depth
Sonic Boring, ≤ 6 inch diameter, 50 to 100 foot total depth
Sonic Boring, ≤ 6 inch diameter, > 100 foot total depth
Sonic Boring, > 6 to 10 inch diameter, < 50 foot total depth
Well Installation - 1 inch diameter
Well Installation - 2 inch diameter
Well Installation - 2 inch diameter (Vertical)
Well Installation - 2 inch diameter (Horizontal, by trenching, not directional drilling)
UNIT OF MEASURE
ORIGINAL
CONTRACTED
ITEM PRICE 2014
PREVIOUS
CONTRACTED ITEM
PRICE (V3.1)
REVISED
CONTRACTED
ITEM PRICE (V3.2)
DESCRIPTION
Region:
Contractor:
Contract #:
North
WATER & AIR RESEARCH, INC.
GC831
DEP Restated Agency Term Contract No. GC831
Amendment No. 8
Attachment D (V3.2) - Rate Schedule
6-3. Per Foot $ 39.00 Not Applicable Not Applicable
6-3.a. Per Foot Not Applicable $ 38.00 $ 39.90
6-3.b. Per Foot Not Applicable $ 125.00 $ 137.50
6-4. Per Foot $ 50.00 $ 50.00 $ 52.50
6-5. Per Foot $ 35.00 $ 35.00 $ 36.75
6-6. Per Foot $ 42.00 $ 42.00 $ 44.10
6-7. Per Foot $ 52.00 $ 52.00 $ 54.60
6-8. Per Foot $ 62.00 $ 62.00 $ 65.10
6-9.a. Per Foot $ 6.00 $ 6.00 $ 6.90
6-9.b. Per Foot $ 9.00 $ 9.00 $ 9.00
6-9.c. Per Foot $ 13.80 $ 13.80 $ 13.80
6-9.d. Per Foot $ 17.75 $ 17.75 $ 17.75
6-10. Per Well $ 450.00 $ 450.00 $ 450.00
6-11. Per Vault $ 600.00 $ 600.00 $ 690.00
6-12. Per Vault $ 1,200.00 $ 1,200.00 $ 1,380.00
6-13. Per Well Not Applicable $ 150.00 $ 172.50
6-14. Per Well Not Applicable $ 250.00 $ 262.50
6-15. Per Well Not Applicable $ 300.00 $ 315.00
7.
7-1. Per Foot $ 15.00 $ 15.00 $ 17.25
Well Installation - 4 inch diameter (Horizontal, by trenching, not directional drilling)
Well Installation - 6 inch diameter
Surface Casing - 6 inch diameter
Surface Casing - 8 inch diameter
Surface Casing - 10 inch diameter
Surface Casing - 12 inch diameter
Well Installation - 4 inch diameter
Well Installation - 4 inch diameter (Vertical)
Installation of Well Vault - 4 x 4 x 2 foot
Well Redevelopment
Removal and Reinstallation of 8-inch Manhole and well pad when a well pad/manhole has been damaged or destroyed
Removal and Reinstallation of 12-inch Manhole and well pad when a well pad/manhole has been damaged or destroyed
WELL ABANDONMENT
Grout and Abandon Well, 1 to 2 inch diameter
Additional Well Screen > 20 feet - 1 inch diameter
Additional Well Screen > 20 feet - 2 inch diameter
Additional Well Screen > 20 feet - 4 inch diameter
Additional Well Screen > 20 feet - 6 inch diameter
Above Grade Well Completion
Installation of Well Vault - 2 x 2 x 2 foot
UNIT OF MEASURE
ORIGINAL
CONTRACTED
ITEM PRICE 2014
PREVIOUS
CONTRACTED ITEM
PRICE (V3.1)
REVISED
CONTRACTED
ITEM PRICE (V3.2)
DESCRIPTION
Region:
Contractor:
Contract #:
North
WATER & AIR RESEARCH, INC.
GC831
DEP Restated Agency Term Contract No. GC831
Amendment No. 8
Attachment D (V3.2) - Rate Schedule
7-2. Per Foot $ 17.00 $ 17.00 $ 19.55
7-3. Per Foot $ 21.00 $ 21.00 $ 24.15
7-4. Per Foot $ 28.00 $ 28.00 $ 32.20
7-5. Per Vault $ 380.00 $ 380.00 $ 380.00
7-6. Per Vault $ 695.00 $ 695.00 $ 695.00
7-7. Per Well Not Applicable $ 150.00 $ 157.50
8.
8-1. Per Well $ 180.00 $ 180.00 $ 189.00
8-2. Per Well $ 200.00 $ 200.00 $ 210.00
8-3. Per Well $ 75.00 $ 75.00 $ 78.75
8-4. Per Sample $ 75.00 $ 75.00 $ 78.75
8-5. Per Sample $ 75.00 $ 75.00 $ 78.75
8-6. Per Sample $ 50.00 $ 52.50 $ 60.37
8-7. Per Well $ 20.00 $ 20.00 $ 21.00
8-8. Per Well $ 100.00 $ 100.00 $ 105.00
8-9. Per Sample $ 50.00 $ 50.00 $ 50.00
8-10. Per Sample $ 50.00 $ 50.00 $ 57.50
8-11. Per Sampling Event Not Applicable $ 150.00 $ 150.00
8-12. Per Well Not Applicable $ 25.00 $ 26.25
8-13. Per Well Not Applicable $ 25.00 $ 26.25
SAMPLE COLLECTION AND FIELD TESTING
Monitoring Well Sampling with Water Level, ≤ 100 foot depth
Monitoring Well Sampling with Water Level, > 100 foot depth
Domestic Water Well Sampling
Other Water Sampling
Free Product Sample Collection
Grout and Abandon Well, > 2 to 4 inch diameter
Grout and Abandon Well, > 4 to 6 inch diameter
Grout and Abandon Well, > 6 inch diameter
Removal of Well Vault - 2 x 2 x 2 foot
Removal of Well Vault - 4 x 4 x 2 foot
Removal of Well Pad and Manhole
Survey Latitude/Longitude of Existing Monitor Wells
Survey Latitude/Longitude of New Monitor Wells
Soil/Sediment Sample Collection
Water Level or Free Product Gauging
Free Product Gauging & Bailing
Vapor/Ambient Air Sample Collection - Passive Dosimeter, Sorbent Tube, Tedlar
TM
Bag
(or Equivalent)
Vapor/Ambient Air Sample Collection - SUMMA
TM
Canister (or Equivalent)
Electronic Data Deliverables (EDD)
UNIT OF MEASURE
ORIGINAL
CONTRACTED
ITEM PRICE 2014
PREVIOUS
CONTRACTED ITEM
PRICE (V3.1)
REVISED
CONTRACTED
ITEM PRICE (V3.2)
DESCRIPTION
Region:
Contractor:
Contract #:
North
WATER & AIR RESEARCH, INC.
GC831
DEP Restated Agency Term Contract No. GC831
Amendment No. 8
Attachment D (V3.2) - Rate Schedule
8-14. Per Sample Not Applicable $ 17.50 $ 18.37
9.
9.A.
9-1. Per Sample $ 412.50 $ 412.50 $ 474.37
9-2. Per Sample $ 44.00 $ 44.00 $ 46.20
9-3. Per Sample $ 60.61 $ 60.61 $ 63.64
9-4. Per Sample $ 75.00 $ 75.00 $ 78.75
9-5. Per Sample $ 85.00 $ 85.00 $ 89.25
9-6. Per Sample $ 85.50 $ 85.50 $ 89.77
9-7. Per Sample $ 205.00 $ 205.00 $ 215.25
9-8. Per Sample $ 70.71 $ 70.71 $ 74.24
9-8.a. Per Sample Not Applicable $ 227.00 $ 238.35
9-9. Per Sample $ 60.00 $ 60.00 $ 69.00
9-10. Per Sample $ 75.00 $ 75.00 $ 78.75
9-11. Per Sample $ 12.12 $ 12.12 $ 12.72
9-12. Per Sample $ 12.12 $ 12.12 $ 12.72
Encore (25 gram) for SPLP Soil Sample Collection: [Per Encore]. The cost will include the 25 gram Encore samples submitted to the laboratory for SPLP testing and the 25 gram Encore samples collected in the field but not submitted to the laboratory for testing
(discarded).
LABORATORY ANALYSIS
SOIL/SEDIMENT ANALYSIS
Soil, Used Oil/Unknown Product Group-Table D of Ch. 62-780, F.A.C., except for non-
Priority Pollutant Organics (Multiple Methods)
Soil, Total Recoverable Petroleum Hydrocarbons (FL-PRO)
Soil, TRPH Fractionation (MADEP-EPH/VPH Method or TPHCWG Direct Method)
Soil, PCBs [or Aroclors] (EPA 8082)
Soil, 8 RCRA Metals (EPA 6010 or EPA 6020 [Arsenic, Barium, Cadmium, Chromium, Lead, Selenium, Silver] and EPA 6020 or EPA 7471 [Mercury])
Soil, Arsenic (EPA 6010 or EPA 6020)
Soil, Cadmium (EPA 6010 or EPA 6020)
Soil, BTEX + MTBE (EPA 8021 or EPA 8260)
Soil, Volatile Organic Halocarbons (EPA 8021 or EPA 8260)
Soil, BTEX + MTBE + VOHs (EPA 8021 or EPA 8260)
Soil, Polycyclic Aromatic Hydrocarbons (EPA 8270 or EPA 8310)
Soil, Priority Pollutant Volatile Organics (EPA 8260)
Soil, Priority Pollutant Extractable Organics-Base Neutral and Acid Extractables (EPA
8270 list [e.g., EPA 8081/8082 + EPA 8270])
UNIT OF MEASURE
ORIGINAL
CONTRACTED
ITEM PRICE 2014
PREVIOUS
CONTRACTED ITEM
PRICE (V3.1)
REVISED
CONTRACTED
ITEM PRICE (V3.2)
DESCRIPTION
Region:
Contractor:
Contract #:
North
WATER & AIR RESEARCH, INC.
GC831
DEP Restated Agency Term Contract No. GC831
Amendment No. 8
Attachment D (V3.2) - Rate Schedule
9-13. Per Sample $ 12.12 $ 12.12 $ 12.72
9-14. Per Sample $ 12.12 $ 12.12 $ 12.72
9-15. Per Sample $ 51.00 $ 51.00 $ 53.55
9-16. Per Sample $ 51.00 $ 51.00 $ 53.55
9-17. Per Sample $ 35.00 $ 35.00 $ 40.25
9-18. Per Sample $ 30.00 $ 30.00 $ 34.50
9-19. Per Sample $ 12.00 $ 12.00 $ 13.80
9-20. Per Sample $ 100.00 $ 100.00 $ 105.00
9-21. Per Sample $ 320.00 $ 320.00 $ 320.00
9-22. Per Sample $ 489.90 $ 489.90 $ 489.90
9-23. Per Sample $ 72.00 $ 72.00 $ 75.60
9-24. Per Sample $ 230.00 $ 230.00 $ 230.00
9.B.
9-25. Per Sample $ 297.98 $ 297.98 $ 312.87
9-26. Per Sample $ 500.00 $ 500.00 $ 525.00
9-27. Per Sample $ 45.45 $ 45.45 $ 47.72
Soil, Moisture Content (ASTM D2216-10)
Soil, Texture, (See Gee 7 Bauder [1966])
Soil, GC/MS Full Scan, Alkanes, Isoalkanes, Cycloalkanes, Aromatics, Bicyclane, Sterane, and Terpane Biomarkers (ASTM D5739 High Resolution GC/MS)
Soil, Gasoline Hydrocarbon Composition, Gasoline PIANO (paraffins, isoparaffins, aromatics, naphthenes and olefins) (EPA 8260Mod, High Resolution GC/MS)
Soil, 5 Fuel Oxygenates, MTBE, DIPE, TAME, ETBE and TBA (EPA 8260Mod, High
Resolutio…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .