CN-370000-EX005-WO2CO1.pdf
PDF 50 KB Posted
- Contract number
- EX005
- Issued by
- Florida
About this file
This is a Work Order Change Form for DEP Contract No. EXC 005, issued by the Florida Department of Environmental Protection on August 12, 2003. The contracting parties are the Florida Department of Environmental Protection and Cargill Fertilizer Inc., represented by contractor representative Ozzie Morris and DEP Contract Manager Joseph Bakker. The change order modifies Work Order No. 2, identified as Change Order No. 1.
The change order extends the performance period for Work Order #2 by one additional year, through June 30, 2004. The original work order completion date was June 30, 2003, and this change maintains that date prior to the modification before revising it to June 30, 2004. The funding level for the work order increases from $110,000 to $180,000, representing a net increase of $70,000. The revised total work order amount, including all change orders to date, is $180,000. No change is made to the overall "not to exceed" amount of the contract. Both the contractor and the Florida Department of Environmental Protection, through its Contract Manager and Division Director or designee, have executed the document as of August 12, 2003.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .