This is a Work Order Change Form (Attachment J) for DEP Contract No. EXC 005, dated April 6, 2006. The contract involves the Florida Department of Environmental Protection and Mosaic Fertilizer, LLC, with Carey MacConnell serving as the contractor representative and Phil Coram as the DEP Contract Manager. The change order was approved by Richard W. Cantrell, Division Director, and has been distributed to the Contracts Office, Bureau of Finance & Accounting, and relevant stakeholders.
Change Order No. 5 reduces the total Work Order #1 amount by $300,000, decreasing the work order from $19,796,000 to $19,496,000. The original work order amount was $5,290,000, with the net decrease of $300,000 reflected in this change order. The available $300,000 has been transferred to Work Order #6, and all other parameters remain unchanged. The work order completion date remains June 30, 2006, with no extension to the original completion date of June 30, 2003. The revised total work order amount, including all change orders to date, is $19,496,000.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .