This is a Consultant's Task Assignment Notification from the Florida Department of Environmental Protection's Division of Recreation and Parks, involving Hydra Engineering & Construction, LLC as the primary consultant. The project is specifically for the Madison Blue Spring State Park Retaining Wall repair, with additional subcontractors including GS Preble, O'Neal Surveying & Mapping, Inc., Environmental and Geotechnical Specialist, Inc., Florida Environmental and Land Services, Inc. (FELSI), and Chronicle Heritage.
The contract, numbered CN815 with project number 6H208, is for repairing a retaining wall damaged by Hurricane Helene, with services including design, permitting, construction administration, survey, geotechnical investigation, environmental assessments, and cultural resource investigations. The total contract value is $63,534.44, comprised of $63,434.44 in fixed price costs and $100 in reimbursable expenses. The project is scheduled to be completed by December 31, 2026, with multiple subtasks including site visits, topographic survey, geotechnical investigation, plan development, environmental permitting, bidding assistance, and construction administration. The work will involve detailed technical assessments, including soil borings, wetland delineation, cultural resource surveys, and comprehensive reporting to the Florida Department of Environmental Protection.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN815-T2.pdf | ||
| CN-370000-CN815.pdf | ||
| CN-370000-PL521-T4.pdf | ||
| CN-370000-CN815.pdf.crdownload | CRDOWNLOAD file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DDivision oof RRecreation aand PParks
CConsultant’s TTask AAssignment NNotification
FFLORIDA DEPARTMENT OF
EENVIRONMENTAL PPROTECTION
DRP-084
Rev. 0 /2025 of 2
FDEP Contract No: Project Number: Task Assignment No:
Project Location Project
Consultant’s Name:
Consultant’s Representative:
Phone: Email:
FDEP Contract Manager:
Phone: Email:
Task Description:
Project Manager:
Schedule:
Start Date: Completion Date:
Fixed Price Cost: Cost Reimbursement (Not to Exceed):
Total Task Amount:
Signatures and Date:
1.
Budget Representative, FDEP Signature Date
2.
Project Manager, FDEP Signature Date
3.
Signature Date
4.
Signature Date
5.
Contract Authority, FDEP Signature Date
CN815 6H208 TA1
Madison Blue Spring State Park Retaining Wall
Hydra Engineering & Construction, LLC Leslie Weiss
(850) 926-2593 lahope@hydraengineering.com
Vu Nguyen
(850) 245-2630 Vu.Nguyen@FloridaDEP.gov
Repair of retaining wall damaged by Hurricane Helene at Madison Blue Spring State Park, services include design, permit and construction administration, per proposal dated 04/29/2025.
Meenakshi Senthilkumar or successor
Upon Execution 12/31/2026
$63,434.44 $100.00 $63,534.44
Tamika Bass
Meenakshi Senthilkumar
Leslie Weiss
Vu Nguyen
Michael W. Foster Jr., P.E.
Tamika Bass Digitally signed by Tamika Bass Date: 2025.05.20 14:46:50 -04'00'
Meenakshi Senthilkumar Digitally signed by Meenakshi Senthilkumar Date: 2025.05.21 08:45:51 -04'00'
Leslie Weiss Digitally signed by Leslie Weiss Date: 2025.05.22 11:54:57 -04'00'
Vu Nguyen Digitally signed by Vu Nguyen Date: 2025.05.22 16:23:10 -04'00'
Michael W. Foster Jr., P.E.
Digitally signed by Michael W. Foster Jr., P.E.
Date: 2025.05.29 09:35:33 -04'00'
DDivision oof RRecreation aand PParks
CConsultant’s TTask AAssignment NNotification
FFLORIDA DEPARTMENT OF
EENVIRONMENTAL PPROTECTION
DRP-084
Rev. /2025 2 of 2
Encumbrance Information:
Project # Grant # Organization Code Category/Yr Fund Module Object EO Amount
Total:
6H208 FD096 37502000268 088040/25 675002 U3200 131500 XR $63,534.44
$63,534.44
HYDRA ENGINEERING & CONSTRUCTION, LLC
36 Jasper Thomas Road, Crawfordville, Florida 32327 (850) 926-2593 www.hydraec.com
Rev. April 29, 2025
April 8, 2025 March 28, 2025
Meena Senthil Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399
RE: CN815, BDC Project No. XX TA XX Madison Blue Springs State Park – Retaining Wall
Dear Ms. Senthil:
Hydra Engineering & Construction, LLC is pleased to provide the attached proposal summary and man-hour documentation for the Retaining Wall at Madison Blue Springs State Park.
Please see the attached proposal summary and deliverables.
Sincerely, Leslie Weiss, P.E., C.G.C.
Hydra Engineering & Construction, LLC
Project No.: 6H208
TA1
CN815 TA XX
Retaining Wall
Madison Blue Springs State Park Subtask 1: Scoping Site Visit Description: A representative from Hydra and a representative from GS Preble will attend a site visit for scoping site visit.
Deliverable: Site visit notes transmitted electronically in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 1 Scoping Site Visit
Firm Name Position Classification Hourly Rate Hours
Total Fixed Price Cost
GS Preble Structural Engineer $158.04 4.5 $711.18 Hydra Engineering &
Construction, LLC Principal Engineer $227.41 5 $1,137.05
Hydra Engineering & Construction, LLC Project Engineer $129.22 2 $258.44
Hydra Engineering & Construction, LLC Office Administrator $77.53 0.5 $38.77
Fixed Price Cost Total $2,145.44
Total for Subtask 1: (Fixed Price Cost + Reimbursable) =$2,145.44
Subtask 2: Survey Description: O’Neal Surveying & Mapping, Inc. shall conduct a topographic survey for design of failing retaining wall. Location extending from top of ravine to edge of water between the existing stairs to the end of the existing retaining wall. Data collected sufficient to produce 1-foot contours, supplemented by spot elevations, as needed. The survey will include, but is not limited to boulders, walls, walks, fences, signs, stairs, edge of water, grade breaks and any other improvements within limits of survey. This survey will include any trees 6 inches and up within the limits of survey, if present.
Deliverable: Consultant will provide electronic copies (AutoCAD and pdf) digitally signed and sealed of the topographic survey.
TA1
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Fixed Price Cost:
Subtask 2 Survey
Firm Name Position Classification Hourly Rate Hours
Total Fixed Price Cost
O'Neal Surveying & Mapping, INC. Survey Crew Chief $103.68 23.5 $2,436.48
O'Neal Surveying & Mapping, INC. Instrument Person $88.66 23.5 $2,083.51
O'Neal Surveying & Mapping, INC Chief Surveyor $200.92 1.5 $301.38
O'Neal Surveying & Mapping, INC Senior Survey Tech $123.75 13 $1,608.75
Hydra Engineering & Construction, LLC Principal Engineer $227.41 1 $227.41
Hydra Engineering & Construction, LLC Project Engineer $129.22 1 $129.22
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Price Cost Total: $6,864.28
Total for Subtask 2: (Fixed Price Cost + Reimbursable) = $6,864.28
Subtask 3: Geotechnical Investigation Description: Due to site access constraints, the presence of the adjacent first-magnitude Blue Spring, and the highly karstic geology of the site, drilling of SPT soil borings would require an extensive work effort. Due to the anticipated high cost of such an effort, EGS proposes to conduct a Limited Evaluation using hand-auger soil borings to characterize the near-surface soils immediately below and behind the wall. This evaluation does not include any wall design, foundation design, slope or global stability, or any other design-related efforts.
Scope of Services:
Field:
o Mobilize on Site o Install 3, +/-10-ft Deep Hand Auger Soil Borings: 1 at walkway grade near south end of wall; 1 near top of wall within the slope near south end of full height section; and 1 within the slope above the tie-in to the intact wall.
o Install 1-20 Ft SPT Boring at Top of Slope (20 Ft/1 Day)
Laboratory o Grainsize Test, 3 at Each Hand Auger Soil Boring + Every 5 Ft of SPT Boring: 16
Tests o Atterberg Limits at Every Hand Auger Soil Boring + Every 20 Ft Of STP Boring: 4
Tests o Organic Content, 2 at Each Hand Auger Soil Boring + Every 20 Ft of SPT Boring: 7
Tests Report o Prepare a geotechnical report, including:
Subsurface Materials Encountered Measured Groundwater Levels Provide the following parameters: soil stratification with unit densities, friction angle & earth pressure coefficients Provide general foundation preparation guidelines Provide Preliminary External Stability of the Existing Wall and Summary of
Options for Reconstruction of Wall Provide Plan Sheet of Report of Soil Borings
Deliverable: Consultant will provide geotechnical report transmitted electronically in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 3 Geotech
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost Environmental and Geotechnical
Specialist, Inc. Chief Engineer $234.00 16 $3,744.00
Environmental and Geotechnical Specialist, Inc. Engineering Intern $110.01 33 $3,630.33
Environmental and Geotechnical Specialist, Inc.
Senior Engineering Tech $166.20 21 $3,490.20
Environmental and Geotechnical Specialist, Inc.
Drill Rig - Truck Mounted $945.00 1 $945.00
Environmental and Geotechnical Specialist, Inc.
Hand Auger With Static Cone Penetrometer
(SCP)
$34.65 11 $381.15
Environmental and Geotechnical Specialist, Inc.
Drill Crew Support Vehicle $472.50 1 $472.50
Environmental and Geotechnical Specialist, Inc.
SPT Truck/Mud Bug 50-100 Ft $34.65 12 $415.80
Environmental and Geotechnical Specialist, Inc.
Grout Boreholes - Truck/Mud Bug 50-100
Ft $15.75 10 $157.50
Environmental and Geotechnical Specialist, Inc.
Extra SPT Samples - Truck/Mud Bug 0-50 Ft $107.10 4 $428.40
Environmental and Geotechnical Specialist, Inc.
Hand Clearing - Chainsaw (Sr. Eng.
Tech & Eng. Tech)
$236.25 6 $1,417.50
Environmental and Geotechnical Specialist, Inc.
Particle Size Anlys AASHTO T88 (No
Hydrometer) $148.05 5 $740.25
Environmental and Geotechnical Specialist, Inc.
Liquid Limit AASHTO T89 $118.13 3 $354.39
Environmental and Geotechnical Specialist, Inc.
Plastic Limit & Plasticity Index
AASHTO T90
$118.13 1 $118.13
Environmental and Geotechnical Specialist, Inc.
Organic Content Ignition FM 1 T-267 $91.35 3 $274.05
Hydra Engineering & Construction, LLC Principal Engineer $227.41 1 $227.41
Hydra Engineering & Construction, LLC Project Engineer $129.22 2 $258.44
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Price Cost Total: $17,132.58
Total for Subtask 3: (Fixed Price Cost + Reimbursable) = $17,132.58
Subtask 4: 60% Documents Description: 60% Civil Plans consisting of a cover sheet, general notes, existing conditions, erosion control measures, site plan, grading plan and details for the retaining wall replacement. 60% Structural Plans for the construction of a new rock retaining wall to tie into the remaining existing rock retaining wall. It includes providing an Opinion of Probable Construction Cost.
Deliverable: Consultant will provide 24”x36” sheet size drawings and Opinion of Probable Construction Cost transmitted electronically in PDF format to the project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 4
Rate Hours Total Fixed
Price Cost GS Preble Structural Engineer $158.04 22.5 $3,555.90
Hydra Engineering & Construction, LLC Project Engineer $129.22 26 $3,359.72
Hydra Engineering & Construction, LLC Principal Engineer $227.41 3 $682.23
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Price Cost Total: $7,675.38
Total for Subtask 4: (Fixed Price Cost + Reimbursable) = $7,675.38
Subtask 5A: Wetland Delineation and Environmental Survey Report Description: Florida Environmental and Land Services, Inc. (FELSI) will conduct a site visit to survey the environmental features present on the property and perform a wetland delineation based upon state and federal guidelines. The wetland line will be flagged using numbered flagging tape marked with ‘Wetland Delineation’. The wetland flag locations will be collected concurrently via
GPS.
Deliverable: Consultant will provide an environmental report summarizing the field findings will be provided along with an aerial map depicting the wetlands in PDF format to the FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 5A Wetland Delineation and Report
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
FELSI Senior Environmental Consultant 3 $150.00 2 $300.00
FELSI Environmental Project Manager 2 $108.00 18 $1,944.00
FELSI Environmental Field Technician $75.00 6 $450.00
FELSI Administrative Assistant 2 $90.00 1 $90.00
Hydra Engineering & Construction, LLC Principal Engineer $227.41 1 $227.41
Hydra Engineering & Construction, LLC Project Engineer $129.22 2 $258.44
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Cost Price Total: $3,347.38
Total for Subtask 5A: (Fixed Price Cost + Reimbursable) = $3,347.38
Subtask 5B: Preparation of Environmental Resource Exemption Application Description: A state permit for the project does not appear to be required. FELSI will prepare an exemption verification request for submittal to the state for the project. Hydra will provide the project plans to include in the submittal. Also, included is response to one Request for Additional Information (RAI) during the application review process, if needed. If a different permit becomes necessary for the project, a change order will be required.
Deliverable: Consultant will provide the exemption application in PDF format to the FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 5B Preparation of Environmental Resource Exemption Application
Price Cost
FELSI Senior Environmental Consultant 3 $150.00 2 $300.00
FELSI Environmental Project Manager 2 $108.00 5 $540.00
FELSI Environmental Field Technician $75.00 3 $225.00
Hydra Engineering & Construction, LLC Principal Engineer $227.41 2 $454.82
Hydra Engineering & Construction, LLC Project Engineer $129.22 4 $516.88
LLC Office Administrator $77.53 1 $77.53
Fixed Cost Price Total: $2,114.23
Reimbursable Cost:
Permit Fees $100.00 Printing N/A Electronic submittals Overnight Travel (if applicable)
N/A
Mileage (@ $0.445 per mile) 0 miles * trip * 0.445 = $0.00 Reimbursable Total Cost $100.00
Total for Subtask 5B: (Fixed Price Cost + Reimbursable) = $2,214.23
Subtask 5C: Preparation of Request for a No Permit Required Determination Description: Florida Environmental and Land Services, Inc. (FELSI) will prepare a request for a No Permit Required determination from the Army Corps of Engineers. The information required for the Army Corps submittal will be similar to that required for the state request. There is no associated application fee. This task includes a response to one RAI from the agency reviewer.
Deliverable: Consultant will provide the request in PDF format to the FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 5C Corps Exemption
Price Cost
FELSI Senior Environmental Consultant 3 $150.00 1 $150.00
FELSI Environmental Project Manager 2 $108.00 3 $324.00
FELSI Environmental Field Tech $75.00 4 $300.00 Hydra Engineering & Construction, LLC Principal Engineer $227.41 2 $454.82
Hydra Engineering & Construction, LLC Project Engineer $129.22 4 $516.88
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Cost Price Total: $1,823.23
Total for Subtask 5C: (Fixed Price Cost + Reimbursable) = $1,823.23
Subtask 6: 100% Plans Description: 100% Civil Plans consisting of updates from the 60% design review comments. 100% Structural Plans for the construction of a new rock retaining wall to tie into the remaining existing rock retaining wall consisting of updates from the 60% design review comments. It also includes providing an Opinion of Probable Construction Cost.
Deliverable: Consultant will provide 24”x36” sheet size drawings and Opinion of Probable Construction Cost transmitted electronically in PDF format digitally signed and sealed to FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 6
Firm Name Position Classification Hourly Rate Hours Total Fixed
Price Cost GS Preble Structural Engineer $158.04 13 $2,054.52 Hydra Engineering & Construction, LLC Project Engineer $129.22 11 $1,421.42
Hydra Engineering & Construction, LLC Principal Engineer $227.41 3 $682.23
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Price Cost Total: $4,235.70
Total for Subtask 6: (Fixed Price Cost + Reimbursable) = $4,235.70
Subtask 7: Bidding Description: Respond to RFI’s and answer FDEP project manager’s questions regarding the bid.
Deliverable: Consultant will provide response letters, memorandums, and technical documents in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language).
Subtask 7
Rate Hours Total Fixed
Price Cost Hydra Engineering & Construction, LLC Principal Engineer $227.41 1 $227.41
Hydra Engineering & Construction, LLC Project Engineer $129.22 4 $516.88
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Price Cost Total $821.82
Total for Subtask 7: (Fixed Price Cost + Reimbursable) =$821.82
Subtask 8A: Pre-Construction Meeting Description: Upon request from BDC, a representative from Hydra and a representative from GS Preble will attend the pre-construction meeting on site and prepare minutes for the meeting.
Deliverable: Meeting minutes transmitted electronically in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 8A
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost GS Preble Structural Engineer $158.04 4.5 $711.18 Hydra Engineering & Construction, LLC Principal Engineer $227.41 1 $227.41
Hydra Engineering & Construction, LLC Project Engineer $129.22 5 $646.10
Hydra Engineering & Construction, LLC Office Administrator $77.53 0.5 $38.77
Fixed Price Cost Total $1,623.46
Total for Subtask 8A: (Fixed Price Cost + Reimbursable) =$1,623.46
Subtask 8B: Construction Administration Description: Construction administration includes answering Requests for Information, reviewing and approval shop drawings, submittals and project certification.
Deliverable: Responses to RFI’s, shop drawings, transmitted electronically in PDF format to project manager. RFI’s will be responded to within 7 working days and submittals will be responded to within 5 working days.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 8B
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost GS Preble Structural Engineer $158.04 3.5 $553.14 Hydra Engineering & Construction, LLC Principal Engineer $227.41 2 $454.82
Hydra Engineering & Construction, LLC Project Engineer $129.22 5 $646.10
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Price Cost Total $1,731.59
Total for Subtask 8B: (Fixed Price Cost + Reimbursable) =$1,731.59
Subtask 8C: Interim Site Visit #1 Description: A representative from Hydra and a representative from GS Preble will attend an interim site inspection to review the status of the project during construction.
Deliverable: Site visit notes transmitted electronically in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 8C
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost GS Preble Structural Engineer $158.04 4.5 $711.18 Hydra Engineering & Construction, LLC Principal Engineer $227.41 1 $227.41
LLC Project Engineer $129.22 5 $646.10
LLC Office Administrator $77.53 0.5 $38.77
Fixed Price Cost Total $1,623.46
Total for Subtask 8C: (Fixed Price Cost + Reimbursable) =$1,623.46
Subtask 8D: Substantial Completion Site Visit Description: A representative from Hydra and a representative from GS Preble will attend a site visit for substantial completion inspection.
Deliverable: Site visit notes transmitted electronically in PDF format to project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 8D
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost GS Preble Structural Engineer $158.04 4.5 $711.18 Hydra Engineering & Construction, LLC Principal Engineer $227.41 5 $1,137.05
Hydra Engineering & Construction, LLC Project Engineer $129.22 2 $258.44
Hydra Engineering & Construction, LLC Office Administrator $77.53 0.5 $38.77
Fixed Price Cost Total $2,145.44
Total for Subtask 8D: (Fixed Price Cost + Reimbursable) =$2,145.44
Subtask 9A: 1a-32 Permit Description: Prior to ground disturbing project activities, Chronicle Heritage will apply for a 1A-32 permit to conduct a CRAS on state lands. In accordance with 1A-32 permit requirements, Chronicle Heritage will also conduct background research to prepare a Research Design to be included with the permit application. This cost is based on the following assumptions: Acceptance of a Research Design by DHR and issuance of a 1A-32 permit and no pre-field kick off meetings, progress meetings, or work-in-progress update reporting is required. Such additional coordination can be provided on a time and materials basis through a separate cost proposal
Deliverable: Consultant will prepare permit application in PDF format to the FDEP project manager.
Fixed Price Cost:
Subtask 9A
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost Chronicle Heritage Principal $160.01 1.5 $240.02 Chronicle Heritage GIS Specialist $75.92 2 $151.84 Chronicle Heritage Associate Level $85.09 6 $510.54 Hydra Engineering & Construction, LLC Principal Engineer $227.41 1 $227.41
Hydra Engineering & Construction, LLC Project Engineer $129.22 2 $258.44
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Price Cost Total $1,465.78
Total for Subtask 9A: (Fixed Price Cost + Reimbursable) =$1,465.78
Subtask 9B: Cultural Resource Assessment Survey Description: Chronicle Heritage will prepare a Phase I CRAS to identify previously recorded and potentially unrecorded cultural resources within the APE. Chronicle Heritage anticipates the project area to have a high probability of containing cultural resources; therefore, fieldwork will entail subsurface testing excavated on a 25-m (82-foot) interval, with delineation shovel testing conducted within the APE limits at 12.5-m (41-foot) intervals.
Assumptions:
Excavation of up to 11 shovel test pits Delineation of site(s) will be limited to the APE.
Documentation of up to one archaeological site and one historic resource; no other cultural resources will be recorded.
Chronicle Heritage assumes no liability for delays, disruptions, or additional costs arising from adverse weather conditions that impact the scheduling, duration, or completion of fieldwork activities. In the event of weather-related delays, we will communicate promptly to reschedule and minimize any impact on project timelines to the best of our ability.
Deliverable: Consultant will provide completed shovel test forms in PDF format to the FDEP project manager.
Subtask 9B
Firm Name Position Classification Hourly Rate Hours
Total Fixed
Price Cost Chronicle Heritage Senior Level $103.14 13 $1,340.82 Chronicle Heritage Associate Level $85.09 10.5 $893.45 Hydra Engineering & Construction, LLC Principal Engineer $227.41 1 $227.41
Hydra Engineering & Construction, LLC Project Engineer $129.22 2 $258.44
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Price Cost Total $2,797.65
Total for Subtask 9B: (Fixed Price Cost + Reimbursable) =$2,797.65
Subtask 9C: Laboratory Analysis and Curation Description: If artifacts or cultural materials are recovered during the survey, they will be transported to Chronicle Heritage’s Tallahassee laboratory facilities for cleaning, stabilization, and analysis. Provisions of the 1A-32 permit for curation with the Florida Bureau of Archaeological Research (BAR) will be followed, including artifact cleaning, sorting, and conservation preparation, and complete artifact provenience data in Excel format.
Assumptions:
Artifact analysis table and curated artifacts for BAR.
Assumes laboratory analysis for up to 75 artifacts; should additional laboratory analysis be needed; this will be conducted as a separate fee and timeline with a revised delivery date for the report.
Deliverable: Consultant will provide Artifact analysis table, curated artifacts, and project documentation in PDF format to the FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 9C
Price Cost
Chronicle Heritage Senior Level $103.14 9.5 $979.83 Hydra Engineering & Construction, LLC Principal Engineer $227.41 1 $227.41
Hydra Engineering & Construction, LLC Project Engineer $129.22 2 $258.44
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Price Cost Total $1,543.21
Total for Subtask 9C: (Fixed Price Cost + Reimbursable) =$1,543.21
Subtask 9D: Cultural Resource Assessment Survey Report Description: A technical report of findings will be produced that details background research, methodology, testing results as well as recommendations regarding the treatment of the resource(s) including but not limited to preservation or avoidance, minimization or mitigation of potential impacts, or no action. This technical report will follow the requirements of Chapter 1A-46 of the Florida Administrative Code. Upon review by the client, any comments will be addressed pertaining to the report and ultimately submitted in a final report form to the DHR. Upon final approval and acceptance of the report, the documentary and cultural materials generated during this project will be transferred to the BAR as part of the terms of the 1A-32 permit.
Assumptions:
Assumes one round of client review for all deliverables.
Assumes laboratory analysis for up to 75 artifacts; should additional laboratory analysis be needed; this will be conducted as a separate fee and timeline with a revised delivery date for the report.
Deliverable: Consultant will provide Phase I CRAS Report in PDF format to the FDEP project manager.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)
Fixed Price Cost:
Subtask 9D
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Chronicle Heritage Senior Level $103.14 25 $2,578.50 Chronicle Heritage Principal $160.01 5 $800.05 Chronicle Heritage GIS Specialist $75.92 2 $151.84
Chronicle Heritage Administrative Assistant $71.44 3.5 $250.04 Hydra Engineering & Construction, LLC Principal Engineer $227.41 1 $227.41
Hydra Engineering & Construction, LLC Project Engineer $129.22 2 $258.44
Hydra Engineering & Construction, LLC Office Administrator $77.53 1 $77.53
Fixed Price Cost Total $4,343.81
Total for Subtask 9D: (Fixed Price Cost + Reimbursable) =$4,343.81
Project Schedule:
Activity Duration (Calendar Days) Dates Subtask 1: Scoping Site Visit 7
Subtask 2: Topographic Survey 60 Upon Receiving Authorization
Subtask 3: Geotechnical Investigation 60 Start after Completion of
Subtask 2
Subtask 4: 60% Plans 45 Start after Completion of Subtask 2 and Subtask 3
Subtask 5A: Wetland Delineation and Environmental Survey Report 30 Upon Receiving
Authorization Subtask 5B-5C: Environmental
Resource Exemption Application and No Permit Required Determination Request
65 Starts after Approval of Subtask 4
Subtask 6: 100% Plans 30 Starts after Completion of Subtask 5B-5C
Subtask 7: Bidding *Contingent on when department advertises the project for bidding
TBD
Subtask 8A-D: Construction Administration
*Contingent on when department advertises the project for bidding
TBD
Subtask 9A-8D: CRAS 45 Starts after Approval of Subtask 6
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1 Scoping Site Visit $2,145.44 $0.00 Subtask 2 Survey $6,864.28 $0.00 Subtask 3 Geotech $17,132.58 $0.00 Subtask 4 60% submittal $7,675.38 $0.00 Subtask 5A Wetland Delineation and Report $3,347.38 $0.00
Subtask 5B Preparation of Environmental Resource Exemption Application $2,114.23 $100.00
Subtask 5C Corps Exemption $1,823.23 $0.00 Subtask 6 100% plans $4,235.70 $0.00 Subtask 7 Bidding $821.82 $0.00 Subtask 8A Pre-Construction $1,623.46 $0.00 Subtask 8B Construction Administration $1,731.59 $0.00 Subtask 8C Progress Site Visit $1,623.46 $0.00 Subtask 8D Substantial Completion Site Visit $2,145.44 $0.00
Subtask 9A 1a-32 Permit $1,465.78 $0.00 Subtask 9B Phase I CRAS $2,797.65 $0.00 Subtask 9C Laboratory and Curation $1,543.21 $0.00 Subtask 9D CRAS Report $4,343.81 $0.00
Total Fixed Price Cost: $63,434.44 Total Reimbursable Cost: $100.00
Overall Total Cost: $63,534.44
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)