This document is a Task Assignment Notification Form from the Florida Department of Environmental Protection (FDEP) for a contract with Mead & Hunt, Inc., involving the Florida Keys Overseas Heritage Trail (FKOHT) bridge project. The contract also involves multiple agencies and stakeholders including FDHR/SHPO, Florida Keys National Marine Sanctuary, US Army Corps of Engineers, US Coast Guard, Florida Department of Transportation (FDOT), and Terramar Environmental Services.

The contract, numbered CN684, is a fixed-price agreement totaling $324,938.00 for architectural and engineering services related to cantilever repair on 14 historic bridges. The project is divided into four primary tasks: preliminary engineering research and inventory, bridge assessment, cultural resources management, and environmental services. Key objectives include conducting visual assessments, drone inspections, environmental condition assessments, agency coordination, and developing technical memorandums to address historical preservation requirements. The project is scheduled to run from September 2023 to February 2024, with various tasks having specific durations and proposed date ranges. The work will focus on evaluating bridge conditions, developing permitting approaches, and preparing for potential future restoration and trail development.

View the file

Other files

File Type Posted
CN-370000-CN684.pdf PDF
CN-370000-BS136-T11CO2.pdf PDF
CN-370000-CN684-T1CO1.pdf PDF
CN-370000-GC824-A4.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN684 TA1 FDEP 61524C

Cantilever Repair- Multiple Bridges

Mead And Hunt

Michael Schwier (850) 391-5169 michael.schwier@meadhunt.com

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

The first phase includes an assessment of the 14 bridges including documentation of findings, coordination with stakeholders, development of engineering and permitting approach, and research into disposal options for the removed concrete and steel.. Phase 2 will consist of design. .See dated 8.11.23

Garland Sandel or successor

Upon Execution $ 299,449.00 1/25/26 $ 25,489.00

$ 324,938.00

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.09.14 16:20:51 -04'00'

Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.09.01 17:22:56 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.09.14 16:31:20 -04'00'

Michael Schwier Michael Schwier

2023.09.15 12:10:25-04'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2023.09.25 15:25:37 -04'00'

61524C 37505000263 080039/23 423001 U3200 131500 QK $ 324,938.00

$ 324,938.00

Florida Keys Overseas Heritage Trail

Architecture/Engineering Services for FKOHT – Can lever Repair Mul ple Bridges

Planning & Coordina on Phase

Contract: CN684, TA #1

August 11, 2023

Project Descrip on:

Florida Keys Overseas Heritage State Trail - Bridges Projects; Built in 1912, the Railroad was converted to the overseas Highway and was opened for vehicular traffic between 1938 and 1943. In the 1980's the historic bridges were decommissioned for vehicular use. By August of 2000 FKOHT were opened as a mulƟ-use bicycle and pedestrian resource that serves as a recreaƟonal and alternaƟve transportaƟon corridor for the Florida Keys. Paralleling U.S. Highway 1, a designated NaƟonal Scenic Highway and All-

American Road, this recreaƟonal pathway incorporates 23 of the historic Flagler Railroad bridges, offering a scenic venue for hiking, running, bicycling, skaƟng, sightseeing, fishing and paddling.

The scope of the project is to develop complete design and permiƫng required to remove canƟlevers and to add bicycle railing to mulƟple bridges that are part of the Florida Keys Overseas Heritage State trail and the remaining non-trail Flagler Bridges.

Currently seven of the 23 bridges have had overhangs previously removed. Seven Mile Bridge and Bahia

Honda Bridge are significant structures that will require significant funding to remove overhangs, restore and to open to trail usage. These two bridges and the seven bridges with overhangs previously removed will be considered as part of any programmaƟc discussion and agreement with the permit and commenƟng agencies. However, it is not anƟcipated that these nine bridges will be part of the engineering phase of this project.

The remaining 14 bridges are fully included in this project for removal of overhangs and permiƫng services:

Historic Bridges listed from South to North

Location Existing Bridge Width

Bridge Length (per Insp Rep)

Overhangs Accessible

3-Rockland Channel Bridge MM 09.8 25 1,230 Yes Open

4-Shark Channel Bridge MM 11 25 1,989 Yes Open

5-Saddlebunch #5 Bridge MM 12.5 25 800 Yes Open

6-Saddlebunch #4 Bridge MM 13.3 25 800 Yes Open

7-Saddlebunch #3 Bridge MM 14.2 25 658 Yes Open

8-Saddlebunch #2 Bridge MM 14.6 25 555 Yes Open

9-Lower Sugarloaf Bridge MM 15.5 25 1,210 Yes Open

13-Park Channel Bridge MM 18.9 25 779 Yes Open

14-Bow Channel Bridge MM 20.2 25 1,302 yes -maintain?

Open

16-Niles Channel Bridge MM 26 25 4,430 yes Collapsing

19-South Pine Channel Bridge MM 28.7 25 682 yes Open from both sides of break

23-Ohio Bahia Honda Bridge MM 38.5 25 1,006 yes Open

24-Ohio Missouri Bridge MM 39 25 2,400 yes -maintain?

Open

25-Missouri Little Duck Bridge MM 39.6 25 800 yes Open

This contract will proceed under several task assignments allowing the work to progress in a step wise approach. The first phase includes an assessment of the 14 bridges including documentaƟon of findings, coordinaƟon with stakeholders, development of engineering and permiƫng approach, and research into disposal opƟons for the removed concrete and steel.

Task 1: Preliminary Engineering Research and Inventory

Descrip on: To support FDEP and agency coordinaƟon in other tasks, Mead & Hunt will prepare an inventory of the bridges. FDEP has provided a number of documents including past inspecƟon reports, plans and reports that Mead & Hunt will review to beƩer understand the bridges. The inventory will idenƟfy bridge types and current railings, modificaƟons, general condiƟon, historical associaƟons and history, immediate safety issues, and potenƟal use as part of the trail system and preliminary assessment of items to consider as part of rehabilitaƟon.

Field review Ɵme required is included under Bridge Assessment task.

Deliverable: Electronic files (PFD files) summarizing understanding of documents provided by FDEP. This may include spreadsheets tabulaƟng aspects of each bridge or brief summaries of the documents and/or technical memos.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and Ɵmely.

Fixed Price:

Task 1 - Preliminary Engineering Research and Inventory

Firm Name Staff Classification Hourly Rate

Hours Total Fixed

Cost

Mead & Hunt, Inc. Senior Associate $279.00 18 $5,022.00

Engineer III $177.00 58 $10,266.00

Technician III $144.00 20 $2,880.00

Technician I $108.00 0 $0.00

Administrative Assistant $108.00 8 $864.00

Task Fixed Cost Total $19,032.00

Total Task 1 Cost: $19,032.00

Task 2: Bridge Assessment:

Descrip on: A visual assessment of the 14 bridges will be made by boat. Kayak or small motorboats will be uƟlized for visual assessment. Binoculars and cameras will be used to assess and document findings.

The inspectors will not be able to access all bridge components for a hands-on inspecƟon. No destrucƟve tesƟng will be performed. The purpose of the assessment is to be able to gain an overall understanding each bridge and to aid in the development of prioriƟzing future work on said bridges.

This task will also include research into disposal opƟons for the concrete and steel including use of borrow pits or other local reuse alternaƟves.

2A: Field inspecƟon of 14 bridges. InspecƟon will be performed by a team of two consisƟng of at least one Professional Engineer and/or CerƟfied Bridge Inspector.

2B: Field inspecƟon using drone to video capture the 14 bridges flying both sides of each bridge.

2C: Assessment Report consisƟng of descripƟon of each bridge, descripƟon of deficiencies, photographs, and sketches (as applicable). Bridge prioriƟzaƟon will be developed based on factors including but not limited to condiƟon, trail conƟnuity, public usage, and navigaƟon hazards.

Deliverable:

2A: PDF of field notes and photo record documenƟng general work performed.

2B: Drone video recordings with GPS posiƟoning.

2C: PDF of Assessment Report signed and sealed by Engineer of Record.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and Ɵmely.

Fixed Price:

Task 2A - Bridge Assessment; Field Inspection; Visual

Firm Name Staff Classification Hourly Rate

Hours Total Fixed

Cost

Mead & Hunt, Inc. Senior Associate $279.00 120 $33,480.00

Engineer III $177.00 128 $22,656.00

Technician III $144.00 128 $18,432.00

Technician I $108.00 20 $2,160.00

Administrative Assistant $108.00 25 $2,700.00

Task Fixed Cost Total $79,428.00

Task 2B - Bridge Assessment; Drone

Firm Name Staff Classification Hourly Rate

Hours Total Fixed

Cost

Mead & Hunt, Inc. Senior Associate $279.00 0 $0.00

Engineer III $177.00 0 $0.00

Technician III $144.00 0 $0.00

Technician I $108.00 64 $6,912.00

Administrative Assistant $108.00 5 $540.00

Task Fixed Cost Total $7,452.00

Task 2.C - Bridge Assessment; Report

Hourly Rate

Hours Total Fixed

Cost

Mead & Hunt, Inc. Senior Associate $279.00 16 $4,464.00

Engineer III $177.00 66 $11,682.00

Technician III $144.00 38 $5,472.00

Technician I $108.00 30 $3,240.00

Administrative Assistant $108.00 20 $2,160.00

Task Fixed Cost Total $27,018.00

Reimbursement Expense:

Task 2A - Bridge Assessment; Field Inspection; Visual

Expenses:

Unit Cost Units

No. of Units Total

Flights $375.00 each 3 $1,125.00

Truck Rental $414.00 /week 2 $828.00

Fuel $50.00 /week 2 $100.00

Kayak Rental (6 days x 3 boats) $25.00 /day /person 18 $450.00

Boat Rental $400.00 /day 2 $800.00

Lodging (14 days x 3 people) $225.00 /day /person 42 $9,450.00

Meals (14 days x 3 people) $69.00 /day /person 42 $2,898.00

Misc Equipment $200.00 each 1 $200.00

Total Expense Cost $15,851.00

Task 2B - Bridge Assessment; Drone

Expenses:

Unit Cost Units

No. of Units Total

Flights $375.00 each 0 $0.00

Vehicle Rental $414.00 /week 1 $414.00

Fuel $100.00 /week 1 $100.00

Lodging (6 days x 1 person) $225.00 /day /person 6 $1,350.00

Meals (6 days x 1 person) $69.00 /day /person 6 $414.00

Misc Equipment (batteries) $200.00 each 2 $400.00

Total Expense Cost $2,678.00

Total Task 2 Cost: $132,427.00

Task 3 - Cultural Resources

Task 3A: FDEP and Agency Coordina on

Descrip on: Mead & Hunt will coordinate with FDEP and federal and state agencies to discuss and confirm project approach for addressing the historic bridges under SecƟon 106 of the NaƟonal

Historic PreservaƟon Act (SecƟon 106) and Florida State Statutes Chapter 267- Historical Resources

(State Statute). The goal is to develop a regulatory process to consider the effects of the current and future projects on the historic bridges in a holisƟc manner through a ProgrammaƟc Agreement or alternaƟve agreement method that allow future projects to remain eligible for federal funding by saƟsfying SecƟon 106. It is expected that the agencies that need to be engaged and consulted in this task to understand roles to comply with SecƟon 106 and State Statute for the current project and potenƟal future projects include: FDHR/SHPO, FKNMS and NOAA, USACE, USCG and FDOT D6. Mead

& Hunt will engage with FDEP, FDHR/SHPO and FDOT D6 as the primary agencies to commence iniƟal coordinaƟon. As a NEPA assignment state, FDOT assumes federal responsibility for transportaƟon projects and therefore FDOT represents FHWA. AŌer iniƟal coordinaƟon with FDEP, FDHR/SHPO and

FDOT D6, Mead & Hunt will coordinate with addiƟonal state and federal agencies as idenƟfied.

Task 3A includes up to four virtual meeƟngs with for iniƟal coordinaƟon with FDEP and FDHR/SHPO to explore approaches to address project compliance with SecƟon 106 and State Statute. The results of coordinaƟon in this task will be informed by work in Task 3.C to develop a Cultural Resources

Technical Memo.

Deliverable:

Task 3A

Task 3A1: First two meeƟngs final meeƟng minutes summarizing results of iniƟal coordinaƟon with FDEP and FDHR/SHPO. (PDF file).

Task 3A2: Last two addiƟonal meeƟng final meeƟng minutes summarizing results of iniƟal coordinaƟon with FDEP and FDHR/SHPO. (PDF file).

Fixed Cost:

Task 3.A.1: Agency Coordination (Meetings 1 & 2 meetings)

Firm Name Staff Classification Hourly Rate

Hours Total Fixed

Cost

Mead & Hunt, Inc. Senior Associate $279.00 4 $1,116.00

Senior Project Scientist $249.00 18 $4,482.00

Senior Project Engineer $249.00 4.5 $1,120.50

Senior Scientist/Senior Historian $195.00 18 $3,510.00

Scientist II/Historian 2 $156.00 0 $0.00

Scientist 1/Historian 1 $138.00 0 $0.00

Senior Technician/Senior

GIS $171.00 0 $0.00

Technician II/GIS $123.00 0 $0.00

Tech Editor $120.00 0 $0.00

Admin $108.00 3 $324.00

Task Fixed Cost Total $10,552.50

Task 3.A.2: Agency Coordination (Up to 2 additional meetings)

Hourly Rate

Hours Total Fixed

Cost

Mead & Hunt, Inc. Senior Associate $279.00 4 $1,116.00

Senior Project Scientist $249.00 18 $4,482.00

Senior Project Engineer $249.00 4.5 $1,120.50

Historian $195.00 18 $3,510.00

Technician II/GIS $123.00 0 $0.00

Tech Editor $120.00 0 $0.00

Admin $108.00 3 $324.00

Task Fixed Cost Total $10,552.50

Task 3B: FDOT District 6 Coordina on

Descrip on: FDOT District 6 (D6) will be coordinated with as to understand potenƟal future funding and requirements. FDOT D6 has provided significant funding in the past through the Local Agency

Program (LAP). The D6 Environmental Management Office (EMO) has had substanƟal involvement in the past and will be able to provide background and understanding. Includes up to 2 extended virtual meeƟngs.

Deliverable:

PDF of notes and important facts from the FDOT District 6 coordinaƟon.

Technical Memo (PDF) outlining the environmental documentaƟons requirements (PD&E or

NEPA) for compliance with state and/or federal requirements depending on funding sources.

Fixed Cost:

Task 3.B - FDOT District 6 Coordination

Firm Name Staff Classification Hourly Rate

Hours Total Fixed

Cost

Mead & Hunt, Inc. Senior Associate $279.00 18 $5,022.00

Senior Project Scientist $249.00 20 $4,980.00

Technician III $144.00 52 $7,488.00

Technician I $108.00 0 $0.00

Administrative Assistant $108.00 8 $864.00

Task Fixed Cost Total $18,354.00

Task 3C: Preliminary Historical/Engineering Research and Inventory

Descrip on: To support agency coordinaƟon in the Cultural Resources task, Mead & Hunt will prepare an inventory of the current status of the bridges. The inventory will idenƟfy bridge types and current railings, modificaƟons, general condiƟon, historical associaƟons and history, immediate safety issues, potenƟal use as part of the trail system, and preliminary assessment of items to consider as part of rehabilitaƟon. This inventory will provide background informaƟon to assist with agency coordinaƟon on under SecƟon 106 and State Statute in the Cultural Resources Task.

A site visit will be conducted by two historians to assess the sites and exisƟng condiƟons.

PorƟons of this effort will be in conjuncƟon with Task 1.

Deliverable: Technical Memo outlining results of research and inventory

Fixed Cost:

Task 3.C: Preliminary research and inventory

Firm Name Staff Classification Hourly Rate

Hours Total Fixed

Cost

Mead & Hunt, Inc. Senior Associate $279.00 18 $5,022.00

Senior Project Scientist $249.00 82 $20,418.00

Senior Project Engineer $249.00 0 $0.00

Historian $195.00 98 $19,110.00

Scientist II/Historian 2 $156.00 32 $4,992.00

Technician II/GIS $123.00 16 $1,968.00

Tech Editor $120.00 8 $960.00

Admin $108.00 0 $0.00

Task Fixed Cost Total $52,470.00

Task 3.C: Preliminary research and inventory

Expenses: Unit Cost Units No. of Units Total

Flights $600.00 each 2 $1,200.00

Parking (airport) $15.00 /day 8 $120.00

Rental Car $40.00 /day 5 $200.00

Fuel $15.00 /day 5 $75.00

Meals (5 days x 2 people) $69.00 /day /person 10 $690.00

Lodging (5 days x 2 people) $225.00 /day /person 8 $1,800.00

Total Expense Cost $4,085.00

Task 3D: Cultural Resources Management Technical Memorandum

Descrip on: Based on agency coordinaƟon and background informaƟon developed in previous tasks, Mead & Hunt will prepare a technical memorandum that outlines recommended approaches to address compliance with SecƟon 106 and State Statute for the historic bridges for this project and similar future projects. The technical memorandum will present the results of agency coordinaƟon and development of an approach to consider the effects of current and future projects on the historic bridges holisƟcally through a ProgrammaƟc Agreement or alternaƟve agreement method that allows projects to remain eligible for federal funding and includes recommendaƟons for minimizaƟon and miƟgaƟon acƟviƟes to resolve adverse effects.

Deliverable: Digital Technical Memo outlining cultural resource management.

Fixed Cost:

Task 3.D: Cultural Resources Technical Memo

Firm Name Staff Classification Hourly Rate

Hours Total Fixed

Cost

Mead & Hunt, Inc. Senior Associate $279.00 4 $1,116.00

Senior Project Scientist $249.00 24 $5,976.00

Senior Project Engineer $249.00 2 $498.00

Historian $195.00 24 $4,680.00

Technician II/GIS $123.00 0 $0.00

Tech Editor $120.00 6 $720.00

Admin $108.00 0 $0.00

Task Fixed Cost Total $12,990.00

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and Ɵmely.

Total Task 3 Cost: $109,004.00

Task 4 – Environmental Services (Terramar)

Task 4A - Rapid Environmental Condi on Assessment

Descrip on: Conduct a rapid environmental assessment of current bridge condiƟons including benthic habitats present and coral resources aƩached to bridge pilings. This will be a rapid assessment to be used to present general current condiƟons to regulators during pre-applicaƟon meeƟngs. This will not be a full resource impact survey that would typically be required for permiƫng.

Work will be completed by a three-person field team of qualiƟed biologists.

Deliverable: Summary report of the bridges evaluated with descripƟons of habitats, coral resources and photos of typical environmental condiƟons organized by bridge locaƟon. This will serve as an agency briefing document for Task 4B meeƟngs.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and Ɵmely.

Fixed Cost:

Task 4A - Rapid Environmental Condition Assessment

Firm Name Staff Classification Hourly Rate

Hours Total Fixed

Cost

Terramar Env. Services Senior Environmental Scientist $168.00 136 $22,848.00

Environmental Scientist $140.00 136 $19,040.00

Task Fixed Cost Total $41,888.00

Task 4A - Rapid Environmental Condition Assessment

Expenses: Unit Cost Units No. of Units Total

21' Work Boat $575.00 /day 5 $2,875.00

Task 4B - Agency pre-applica on mee ngs

Descrip on: Conduct pre-applicaƟon scoping meeƟngs with the main regulatory agencies anƟcipated to require permits. This will include South Florida Water Management District, US Army

Corps of Engineers and Florida Keys NaƟonal Marine Sanctuary. This task may also involve discussions with the Florida Department of TransportaƟon (TBD). The goal of the pre-applicaƟon coordinaƟon will be to introduce the project to the regulatory agencies and gather informaƟon of permiƫng requirements, acceptable means and methods of construcƟon and other details of the permiƫng process.

Deliverable: Summary memorandum of the meeƟng notes with the various regulatory agencies, including South Florida Water Management District, US Army Corps of Engineers, and Florida Keys

NaƟonal Marine Sanctuary.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and Ɵmely.

Fixed Cost:

Task 4B - Agency pre-application meetings

Firm Name Staff Classification Hourly Rate

Hours Total Fixed

Cost

Terramar Env. Services Senior Environmental Scientist $168.00 64 $10,752.00

Environmental Scientist $140.00 64 $8,960.00

Task Fixed Cost Total $19,712.00

Total Task 4 Cost: $64,475.00

Summary of Fees:

Task Fixed Fee Limiting Amount

Task 1 - Preliminary Engineering Research and Inventory $19,032.00

Task 2A - Bridge Assessment; Field Inspection; Visual $79,428.00 $15,851.00

Task 2B - Bridge Assessment; Drone $7,452.00 $2,678.00

Task 2.C - Bridge Assessment; Report $27,018.00

Task 3.A.1: Agency Coordination (Meetings 1 & 2 meetings) $10,552.50

Task 3.A.2: Agency Coordination (Up to 2 additional meetings) $10,552.50

Task 3.B - FDOT District 6 Coordination $18,354.00 $4,085.00

Task 3.C: Preliminary research and inventory $52,470.00

Task 3.D: Cultural Resources Technical Memo $12,990.00

Task 4A - Rapid Environmental Condition Assessment $41,888.00 $2,875.00

Task 4B - Agency pre-application meetings $19,712.00

SubTotal $299,449.00 $25,489.00

Total $324,938.00

Schedule:

Task Estimated Duration

(Work Days) Proposed Dates

Executed Contract 0 9/15/2023

Task 1 - Preliminary Engineering Research and Inventory 38 09/19/23 to 11/09/23

Task 2A - Bridge Assessment; Field Inspection; Visual 35 10/27/23 to 12/14/23

Task 2B - Bridge Assessment; Drone 20 11/09/23 to 12/06/23

Task 2.C - Bridge Assessment; Report 25 12/22/23 to 01/25/23

Task 3.A.1: Agency Coordination (Meetings 1 & 2 meetings) 30 09/26/23 to 10/30/23

Task 3.A.2: Agency Coordination (Up to 2 additional meetings) 30 10/30/23 to 12/18/23

Task 3.B - FDOT District 6 Coordination 45 10/17/23 to 12/18/23

Task 3.C: Preliminary research and inventory 76 10/03/23 to 01/16/24

Task 3.D: Cultural Resources Technical Memo 49 12/20/23 to 02/26/24

Task 4A - Rapid Environmental Condition Assessment 55 09/26/23 to 01/25/24

Task 4B - Agency pre-application meetings 38 12/05/23 to 01/25/24

Blank TA Form v3.pdf
FKOHT scope of services R2.pdf

File details come from the government source that posted it. Updated .