This document is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) for a task assignment under Contract Number CN328. Coastal Systems International, Inc., a consulting firm headquartered in Coral Gables, Florida, has been assigned to provide analysis and engineering services for the Fort Zachary Taylor Historic State Park Beach Nourishment Project. The assignment was executed in June 2022, with FDEP's Bureau of Design and Construction serving as the contracting authority and Andrew Lippens as the Project Manager.
The task assignment comprises two subtasks valued at a combined total of $22,516.64. Subtask 1, Topography & Beach Profiles, is priced at $9,797.62 in fixed costs plus $1,805.00 in reimbursable expenses and involves surveying beach topography, collecting sand samples, and delivering digital survey files within 30 days of contract execution. Subtask 2, Coastal Modeling, is priced at $10,914.02 in fixed costs and requires coastal engineering analysis using MIKE modeling tools, with deliverables due within 30 days of Subtask 1 completion. The fixed price costs are based on labor rates ranging from $59.27 to $213.44 per hour across various position classifications, and reimbursable expenses include equipment rental, mileage, and field supplies. Payment is contingent upon FDEP approval of deliverables for each subtask, with a completion deadline of December 31, 2023. The work is funded through FDEP's FLAIR code 37536060000 under organizational code 423001.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CN-370000-CN328-CMC1.pdf | ||
| CN-370000-CN328-CMC2.pdf | ||
| CN-370000-CN328-CMC5.pdf | ||
| CN-370000-CN328-T1CO2.pdf | ||
| CN-370000-CN328-T2CO1.pdf | ||
| CN-370000-CN306-T9.pdf | ||
| CN-370000-CN306-T9CO1.pdf | ||
| CN-370000-CN328-CMC3.pdf | ||
| CN-370000-CN328-T1CO1.pdf | ||
| CN-370000-CN328-CMC4.pdf | ||
| CN-370000-CN328-T1.pdf | ||
| CN-370000-CN328-T2.pdf | ||
| CN-370000-CN328-A1.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN328 3 FDEP 61405
Fort Zachary Taylor Historic State Park Additional Sand Placement
Coastal Systems International, Inc.
R. Harvey Sasso, P.E. 305-661-3655 rhsasso@coastalsystemsdev.com
Jeffrey Whitfield 850-245-2630 jeffrey.whitfield@floridadep.gov
Task assignment to provide analysis of current conditions and erosion patterns of the beach at Fort Zachary Taylor Historic State Park as per attached proposal dated 3/11/22.
Andrew Lippens
Upon Execution $ 20,711.64 12/31/23 $ 1,805.00
$ 22,516.64
Dianne Langston Diane Langston Digitally signed by Diane Langston Date: 2022.04.28 07:45:07 -04'00'
Andrew Lippens Andrew Lippens Digitally signed by Andrew Lippens Date: 2022.05.03 15:07:25 -04'00'
Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2022.05.03 15:12:49 -04'00'
R. Harvey Sasso, P.E. Ronald H Sasso Digitally signed by Ronald H Sasso Date: 2022.06.07 13:42:36 -04'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.06.13 09:05:23 -04'00'
61405 37536060000 140126/22 423001 U3200 131545 QL $ 22,516.64
$ 22,516.64
190840.01-R2
March 11, 2022
Mr. Andrew Lippens
Project Manager
Bureau of Design and Construction
Florida Department of Environmental Protection
3800 Commonwealth Boulevard
Tallahassee, FL 32399
RE: Coastal Systems International, Inc. Contract Number CN328-TA#02
Existing Conditions and Historic Erosion Analysis
Ft. Zachary Taylor State Park (190840)
Dear Mr. Lippens, For your review and approval, Coastal Systems International, Inc. has provided a Task Assignment for the services related to the Ft. Zachary Taylor State Park Beach Nourishment Project (Project), revised as requested. The summary and man-hour documentation for subtasks related to analyzing existing and historic conditions for the beach nourishment project is enclosed. We look forward to providing continuing services under the contract mentioned above.
File, RHS, TS, JAO, AZ, Accounting, Contract Book
F:\Project\190840.01\Proposal\(22-03-11) LTR Task Assignment No 2-R2.docx
COASTAL SYSTEMS INTERNATIONAL, INC.
464 South Dixie Highway • Coral Gables, Florida 33146 Tel: 305-661-3655 • Fax: 305-661-1914 www.coastalsystemsint.com
Matson_D Cross-Out
Matson_D Text Box z
Project Description
Ft. Zachary Taylor State Park – Beach Nourishment
Contract Number CN328, Task Assignment Number 2
Subtask 1 – Topography & Beach Profiles
Description: Coastal Systems will mobilize a survey team to collect survey data within the beach area outlined on Figure 1 to document beach topography to the approximate Mean Low Water Line.
Horizontal positioning will be based on differential GPS with accuracies suitable for a study of this nature. The beach topography will be collected using RTK with profiles collected every 50 feet. Mean
High Water and Mean Low Water will be identified.
Field data will be reduced to the horizontal coordinate system acceptable to the Client and a vertical datum established for this project. Contours will reflect elevations at 1-foot intervals. The base map can be represented upon a geo-referenced and ortho-rectified color aerial image.
Coastal Systems will collect up to thirty (30) total sand samples from the beach, along each transect, to be analyzed under standard regulatory agency requirements. The samples will be visually compared with existing sand quality product data from the Ortona sand mine for the fill material to confirm conformance with environmental criteria for beach quality sand. Geotechnical testing for grain size and Munsell color is not included within these services.
Figure 1. Outline of area of focus for field studies.
Deliverable: A digital survey file will be emailed to the Bureau of Design and Construction (BDC).
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, and accurate.
Fixed Price Cost:
Subtask 1
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Coastal Systems Principal/Director $213.44 5 $1,067.20
Coastal Systems Senior Project Manager $167.19 10 $1,671.90
Coastal Systems Project Manager $100.56 12 $1,206.72
Coastal Systems Surveyor $110.28 35 $3,859.80
Coastal Systems GIS Technician $99.60 20 $1,992.00
Total for Subtask 1: $9,797.62
Reimbursable Cost
Reimbursable Item Unit Cost Quantity Cost
Printing $0.40 / Sheet 20 Sheets $8
Mileage $0.445 / Mile 320 Miles $142
Survey Equipment $300 / Day 1 Day $300
Handheld Radio $25 / Day 2 Gear Sets, 1 Day $50
Field Ruggedized Laptop $150 / Day 1 Day $150
Snorkel Gear $25 / Day 2 Gear Sets, 1 Day $50
RTK R10 GPS $975 / Day 1 Day $975
Handheld GPS $50 / Day 1 Day $50
Upland Camera $50 / Day 1 Day $50
Sand Collection Equipment $30 / Day 1 Day $30
Reimbursable Total Cost: $1,805
Project Schedule: Subtask 1 shall be completed within 30 days of the Contract execution date, assuming the FKNMS field work permit has been issued.
Activity Duration (Calendar Days)
Subtask 1 Within 30 days of the Contract execution date.
Subtask 2: Coastal Modeling
Description: Coastal Systems will review the available coastal report/studies and as well as historical data i.e. storm (that passed within the Project vicinity), wind and wave data. However, the incident unidirectional wind generated sea and swell waves play important role in morphological changes.
Therefore, the detailed analysis of long period (historical) wind and wave data will be critical in assessing the rate of erosion in the project vicinity.
In this study, a combination of MIKE by DHI’s tools, i.e. MIKE21-SW (Spectral Wave), MIKE-HD
(Hydrodynamic) and MIKE21-ST (Sand Transport), will be utilized in coupled mode to evaluate the existing condition. The data collected under Subtask 1 will be used to calibrate the models. One (1) teleconference call with the Client to review the findings of the Coastal Engineering Report is included.
Deliverable: A digital copy of the Coastal Engineering Report will be emailed to the BDC
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, and accurate.
Fixed Price Cost:
Subtask 2
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Coastal Systems Principal/Director $213.44 12 $2,561.28
Coastal Systems Senior Project Manager $167.19 6 $1,003.14
Coastal Systems Project Engineer $123.79 50 $6.189.50
Coastal Systems Project Manager $100.56 8 $804.48
Coastal Systems Administrative Assistant $59.27 6 $355.62
Total for Subtask 2: $10,914.02
Project Schedule: Subtask 2 shall be completed within 30 days of completion of Subtask 1.
Activity Duration (Calendar Days)
Subtask 2 Within 30 days of the completion of Subtask 1.
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1 $9,797.62 $1,805
Subtask 2 $10,914.02 n/a
Overall Total Cost: $22,516.64
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
| Blank TA Form.pdf |
| (22-03-11) LTR Task Assignment No 2-R2.pdf |