This is a Task Assignment Change Order Form (Change Order No. 03) issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN208. The consultant on the contract is Calvin Giordano & Associates, represented by James Messick, PE. The project is located at Fort Zachary Taylor and involves overflow parking improvements. The FDEP Contract Manager is Ralph Perkins, and the project manager is Theresa Carron. The change order was approved by FDEP's Budget Representative (Tamika Bass), Project Manager, Contract Manager, Contract Authority (Michael W. Foster Jr., PE), and signed by the consultant representative on February 15-17, 2023.

The change order is a time-only extension with no cost increase to allow completion of contracted tasks including bidding support and construction administration. The original task amount was $14,915.00 in reimbursement and $59,758.92 in fixed fees, totaling $74,673.92. This change order adds 122 days to the project schedule, extending the task end date from April 1, 2023 to July 30, 2023. The extension was requested due to project delays during the bid process and a delayed construction start date. The total task amount remains $67,503.92 with no net increase or decrease in this change order, as it is a no-cost time extension.

View the file

Other files

File Type Posted
CN-370000-GC911-T1.pdf PDF
CN-370000-GC911-T2.pdf PDF
CN-370000-GC911-T2CO1.pdf PDF
CN-370000-CN225-TA33.pdf PDF
CN-370000-GC911-A1.pdf PDF
CN-370000-GC911-T2CO2.pdf PDF
CN-370000-GC911-T2CO3.pdf PDF
CN-370000-GC911-T4.pdf PDF
CN-370000-GC911-T5.pdf PDF
CN-370000-GC911-T5CO1.pdf PDF
CN-370000-GC911-T6CO1.pdf PDF
CN-370000-GC911-T8.pdf PDF
CN-370000-GC911-T8CO1.pdf PDF
CN-370000-GC911-T1CO1.pdf PDF
CN-370000-GC911-T1CO2.pdf PDF
CN-370000-GC911-T2CO4.pdf PDF
CN-370000-GC911-T3CO2.pdf PDF
CN-370000-GC911-T7.pdf PDF
CN-370000-GC911-T3.pdf PDF
CN-370000-GC911-T3CO1.pdf PDF
CN-370000-GC911-T6.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN208 09 03 61311C

Fort Zachary Taylor Overflow Parking

Calvin Giordano & Associates

James Messick, PE 954-921-7781 Email:

essick cgasolutions.com

Ralph Perkins 850-245-2460 ralph.perkins@floridadep.gov

Time only addition to allow completion of contracted tasks (bidding support and construction administration) per the attached request dated 2/13/2023.

$ 14,915.00 $ 14,915.00 $ 7,745.00 $ 59,758.92 $ 67,503.92

$ 0.00 $ 0.00 $ 0.00 $ 7,745.00 $ 59,758.92 $ 67,503.92

10/09/2020

9/23/21

4/1/2023

7/30/2023

Tamika Bass

Theresa Carron T.Carron Digitally signed by T.Carron Date: 2023.02.13 10:18:55 -05'00'

Ralph Perkins

James Messick, PE

Michael W. Foster Jr., PE

$ 0.00

Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.02.15 10:29:36 -05'00'

James Messick Digitally signed by James Messick DN: CN=James Messick, dnQualifier=A01410D0000018337BC02C800065B3B, O=CALVIN GIORDANO AND ASSOCIATES INC, C=US

Date: 2023.02.15 14:34:32-05'00'

Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2023.02.17 10:58:46 -05'00'

Carron, Theresa

From: James Messick <JMessick@cgasolutions.com> Sent: Monday, February 13, 2023 9:54 AM To: Carron, Theresa; Williams, Brandon D Cc: Jenna Martinetti; Lissette Valdes; Post, James; Matson, David; Rowe, Richard J.

Subject: CN208 TA09 CO : Fort Zachary Taylor Overflow Parking (Time Extension)

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Theresa, Please accept this email as a formal request to modify Task Assignment No. TA09 CO2, �Fort Zachary Taylor Overflow Parking� project. Our request is to extend the complete date for subtask 9 �Shop Drawing, Construction Clarifications & Changes� to a new Completion date of 07/30/2023. This request is considered a �no-cost� time extension. This extension is due to project delay during the bid process and subsequently the start of construction date delayed.

Please let me know if you have any questions.

Thanks, Jimmy Messick, PE Senior Project Manager

Calvin, Giordano & Associates, Inc. - a SAFEbuilt Company 1800 Eller Drive | Suite 600 | Fort Lauderdale, FL 33316 Office: 954.921.7781 | Direct: 954.766.2789 | Fax: 954.921.8807

Fort Lauderdale | Miami-Dade | West Palm Beach | Clearwater/Tampa | Estero | Port St. Lucie

File details come from the government source that posted it. Updated .