This document is a Change Order for a Construction Services Contract (CN 193) issued by the Department of Environmental Protection, involving The Watatauga Company/Jason Snodgrass as the contractor for work at Okeehobee Battlefield State Park. The contract change order is dated March 10, 2015, and involves multiple signatories including Bryan Bradner, Katie Parrish, Patrick Vicknair, and Jason Snodgrass.

The change order authorizes modifications to the original contract, including changes in restroom door hardware, restroom concrete foundation, driveway culverts, septic system, and subsurface soil conditions, with supporting documentation. The original contract sum was $159,025.00, and this change order adds $21,607.50, bringing the new contract sum to $181,532.50. The project timeline was adjusted, with the original substantial completion date of February 19, 2015, modified to a new substantial completion date of March 24, 2015, and a final completion date of April 23, 2015. The change represents an increase in the contract value and extends the project timeline to accommodate the specified modifications.

View the file

Other files

File Type Posted
CN-370000-CN193-CO2.pdf PDF
CN-370000-CN193.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .