city of park ridge BID PW-26-13 Library Masonry Project.pdf

PDF 830 KB Posted

Attached to
Exterior Concrete & Masonry Repairs at Park Ridge Public Library
Solicitation number
PW-26-13
Issued by
Cook County, Illinois

About this file

Summary

This is an Invitation for Bids issued by the City of Park Ridge, Illinois for exterior concrete and masonry repairs at the Park Ridge Public Library located at 20 South Prospect Avenue. The scope of work includes demolition and replacement of deteriorated concrete sidewalk sections, demolition and reconstruction of portions of the existing concrete retaining wall, masonry tuckpointing of deteriorated mortar joints, removal and replacement of damaged or cracked brick masonry units, concrete stair repairs with reinforcing dowels and new concrete material, repair and replacement of limestone capstones at terrace and front entry walls, removal, repair, repainting and reinstallation of handrail posts with new grout beds and sealant, repair of wall caps, masonry joints, sealants, and miscellaneous concrete and masonry deficiencies, and protection and restoration of adjacent improvements. The project completion deadline is November 23, 2026, with any punch list work to be completed within 30 days thereafter. The bid solicitation (PW-26-13) was issued August 6, 2026, with questions due by August 11, 2026 at 2:00 p.m., final Q&A addendum published August 13, 2026 at 2:00 p.m., bid responses due August 20, 2026 at 10:00 a.m., and anticipated contract award in September 2026. Bidders are required to examine contract documents and visit the site prior to submission. The contract term is one year following City Council approval and execution by the City Manager.

Bidders must submit all-inclusive pricing with no additional charges during the contract term. The contractor shall be responsible for all labor, materials, equipment, tools, storage, delivery, disposal, permits, traffic and pedestrian control, and incidentals necessary to complete the work. Contractors must maintain performance and payment bonds in the full contract amount per the Illinois Public Construction Bond Act and provide certificates of insurance evidencing workers' compensation, commercial general liability ($2,000,000 general aggregate, $1,000,000 each occurrence), commercial automobile liability ($1,000,000 combined single limit), and umbrella liability ($2,000,000 minimum per occurrence) coverage, with the City named as additional insured. Construction hours are restricted to 7:00 a.m. to 7:00 p.m. Monday through Friday only. Liquidated damages of $200 per calendar day apply for failure to complete by the required date. The Illinois Prevailing Wage Act applies to this public works project, requiring contractors and all subcontractors to pay prevailing wage rates established by the Illinois Department of Labor. Contractors must comply with all applicable federal, state, and local laws including equal employment opportunity requirements, sexual harassment policies, drug-free workplace provisions, and anti-collusion certifications.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF PARK RIDGE

505 Butler Place Park Ridge, IL 60068 Tel: 847-318-5200 www.parkridge.us

INVITATION FOR BIDS

EXTERIOR CONCRETE & MASONRY REPAIRS

PW-26-13

NOTICE TO BIDDERS

The City of Park Ridge is accepting bids from qualified contractors to provide exterior concrete and masonry repairs at the Park Ridge Public Library, located at 20 S. Prospect Avenue in Park Ridge, Illinois.

Bid documents can be obtained from on the City’s website (www.parkridge.us/purchasing) and Euna OpenBids (www.demandstar.com). All responses must be received via OpenBids or in-person at Park Ridge City Hall, Finance Department, 505 Butler Place, Park Ridge, IL prior to the Due Date and Time set forth below. Responses transmitted by fax or email will not be accepted. Responses received in person must be in a sealed envelope marked and clearly labeled: Company Name and Address, Solicitation Number, and Project Title.

Infrequent or first-time users of electronic bidding are encouraged to upload their responses at least 24 hours prior to bid opening. The City is not responsible for submittal errors or incomplete bid submissions. For technical issues or concerns, bidders may contact OpenBids support directly at hello@eunasolutions.com.

VIRTUAL BID OPENING

Click here to join the Virtual Bid Opening (via Microsoft Teams) from your computer or mobile device. Bids will be opened and read publicly at City Hall on the due date and time set forth below.

Any communication regarding this invitation between the date of issue and date of award is to be in writing and directed to procurement@parkridge.us. Answers to questions submitted in writing may be distributed as an addendum. If a plan holder chooses not to submit a proposal, please fill out the enclosed NO BID form and return it to the email above.

ACTION DATE TIME

Invitation for Bids Issued August 6, 2026 -

Questions Due August 11, 2026 2:00 P.M.

Final Q&A Addendum Published August 13, 2026 2:00 P.M.

Bid Responses Due Date August 20, 2026 10:00 A.M.

Anticipated Contract Award September 2026

GENERAL CONDITIONS AND INSTRUCTIONS

1. GENERAL

Throughout this document, “City of Park Ridge,” “City,” and “Owner” shall be synonymous and mean the City of Park Ridge. The words “bid,” “proposal,” “bidder,” “proposer,” “vendor,” “firm,” “contractor,” and “supplier” may be used in the alternative in these General Conditions and Instructions as intended and described by the Scope of Work. The phrases “request for proposal,” “invitation for bids,” “request for quotes,” “request,” “invitation,” and “solicitation” may also be used in the alternative.

2. EXAMINATION OF CONTRACT DOCUMENTS AND WORK SITE BY BIDDER

The Bidder shall, before submitting its Bid, carefully examine the plans, specifications, contract documents, Bid, and bond and insurance requirements and visit the site to verify conditions under which work will be performed.

Each Bidder is responsible for reading the bid documents and familiarizing itself with all requirements. Failure of a Bidder to do so shall not relieve the Bidder of any obligation with respect to said bid. If the Bidder’s bid is accepted, it shall be responsible for, and the City will make no allowance for any errors in their Bid resulting from its failure or neglect to comply with these instructions.

3. QUALIFICATIONS OF BIDDER

The City may take any action deemed necessary to investigate the qualifications of each Bidder. The City reserves the right to qualify or disqualify Bidders as a result of lack of similar project experience and/or any other information obtained from the project reference form, references listed thereon, or publicly available information. Bidders must also demonstrate that they have sufficient resources (i.e. capital, laborers, sub-contractors, etc.) to accomplish all tasks required within the schedule for the contract. In the event there are additional eligibility requirements described in the Special Conditions or Specifications, such requirements shall be supplemental to and not in limitation of this provision.

4. PREPARATION OF BID

The Bidder shall prepare their Bid on the attached Bid Form or alternatively include all required information in the Bidder’s proposal package if a Bid Form is not included. Unless otherwise stated, all blank spaces on the Bid page(s), applicable to the subject specification, must be correctly filled in. Either a unit price or a lump sum price, as the case may be, must be stated for each item, either typed in or written in ink, in figures, and, if required, in words. In the event of an error on the Bid page in which there is a conflict between the unit price and the extended price or the total bid price, the City may exercise its reasonable discretion to ascertain the actual price of the bid.

If the Bidder is a corporation, the President and Secretary shall execute the Bid, and the Corporate Seal shall be affixed. In the event that the Bid is executed by an officer other than the President, sufficient evidence of such signatory’s authority shall be submitted. If the Bidder is a partnership, majority owning partners or general partners shall execute the Bid, unless one partner has been authorized to sign for the partnership, in which case sufficient evidence of such authority shall be submitted. If the Bidder is a limited liability company, the manager shall execute the Bid, unless another officer has been authorized to sign for the company, in which case sufficient evidence of such authority shall be submitted.

Each Bid must contain all required certifications and signatures. In addition, if any addenda are issued by the City, the Bidder shall be required to acknowledge receipt of the formal addendum on the Bid form or proposal, as applicable. Failure of a Bidder to acknowledge any of the addenda issued or submit essential required documents contained in the solicitation shall deem its bid non-responsive; provided, however, that the City in reliance upon its home rule powers, may choose to waive this requirement if the City determines from the context of the Bid that the Bidder has considered the terms and conditions of the addendum.

The Bid submitted must not contain erasures, interlineations, or other corrections unless each correction is suitably authenticated by affixing in the margin immediately opposite the correction the surname or surnames of the person or persons signing the bid.

Modifications of bids already submitted will be considered if received at the office designated in the Invitation to Bid by the time set for opening of bids. Unless called for, alternate bids will not be considered. No compensation will be allowed due to any difficulties which the Bidder could have discovered or reasonably known prior to bidding.

5. SUBMISSION OF BID

All prospective Bidders shall submit their Bid in the manner specified in the Notice to Bidders by the specified due date and time of the bid. Bids received beyond the date and hour set for the bid opening will not be considered.

Submission of a bid will be considered presumptive evidence that the Bidder has visited the sites and is conversant with local facilities and difficulties, the requirements of the documents and of pertinent State or Local Codes, the state of Labor and Material Markets, and has made due allowance in the bid for all contingencies. Include in bid all costs of labor, material, equipment, allowance, fees, permits, guarantees, applicable taxes, insurance and contingencies, with overhead and profit necessary to produce a complete project, or to complete those portions of the work covered by the Specifications on which the Bid is made including all trades, without further cost to the Owner. Unless otherwise described in the Special Conditions or Specifications, Bidders shall be responsible to obtain all permits and arrange for all inspections. No unsolicited supplemental information will be accepted and will be returned without being considered by the City.

6. WITHDRAWAL OF BID

A Bidder may withdraw their Bid at any time prior to the time specified in the notice as the closing time for receipt of bids. However, no Bidder shall withdraw, cancel or modify their Bid for a period of sixty (60) calendar days after the specified closing time for the receipt of bid. Where this contract is subject to approval by another agency, such as the Federal Government or the State of Illinois, then the Bidder shall not withdraw, cancel or modify their Bid for a period of ninety (90) calendar days after the specified closing time for the receipt of bids.

7. CONSIDERATION OF BIDS

No Bid will be accepted from or contract awarded to any person, firm or corporation that is in arrears or is in default to the City of Park Ridge upon any debt or contract, or that is a defaulter, as surety or otherwise, upon any obligation to the City, or had failed to perform faithfully any previous contract with the City. The Bidder, if requested, shall present within 48 hours evidence satisfactory to the City of performance ability and possession of necessary facilities, pecuniary resources and adequate insurance to comply with the terms of these specifications and contract documents.

Each Bidder shall submit where necessary, or when requested by the Procurement Officer, catalogs, descriptive literature or detailed drawings fully detailing features, designs, construction, appointments, finishes and the like not covered in the specifications, necessary to fully describe the material or work they propose to furnish.

The City of Park Ridge reserves the right to disregard any informality in the bids and bidding, to waive technicalities, or to reject any and all bids when, in the opinion of the City Council, the best interest of the City will be served by such action.

8. ACCEPTANCE OF BIDS

The City will accept one of the bids or reject all bids within sixty (60) calendar days, or within ninety (90) calendar days where approval by other agencies is required, from the date of opening of bids, unless the successful Bidder, upon request of the City, extends the time of acceptance to the City. The contract will be awarded based on the City’s independent assessment of the bid by reference to the evaluation criteria described in the bid solicitation. Where no evaluation criteria are specified, the contract will be awarded to the lowest responsible and responsive bidder whose bid is most favorable to the City’s interests. The City may rely on any information presented in the bid and any publicly available information to assess the qualifications, responsiveness and responsibility of a bid.

In addition to price, the City may consider: (1) compliance with bid and contract requirement including bonds and insurance; (2) ability, capacity, and skill to perform; (3) adequacy of facilities, equipment, materials, financial resources, organization, and staffing; (4) character, integrity, reputation, judgment, experience, and efficiency;

(5) quality of past performance; (6) compliance with past contracts and applicable laws; (7) ability to provide future maintenance and service; (8) conditions or exceptions placed on the bid.

9. INTERPRETATION OF CONTRACT DOCUMENTS

Any Bidder in doubt as to the true meaning of any part of the specifications and contract documents may submit to the Procurement Officer a written request for an interpretation thereof by the deadline described in the Notice to Bidders. No oral comments will be made to any Bidder as to the meaning of the General or Special Conditions or any other contract documents and any inadvertently made are hereby disclaimed and void. The person submitting the request shall be responsible for its prompt delivery. Questions received after the deadline described in the Notice to Bidders cannot be considered. Such interpretation will be made only in the form of a written addendum duly issued by Procurement Officer. A copy of such addendum will be posted on the City’s website and DemandStar. Failure on the part of the prospective Bidder to receive a written interpretation prior to the time of the opening of bids will not be grounds for withdrawal of their Bid. The Bidder shall acknowledge receipt of each addendum issued.

Addenda may modify or interpret the Bidding Documents and will become part of the Contract Documents when the Contract is executed. Subsequent addenda shall govern over prior addenda only to the extent specified.

Any references in these specifications to manufacturer's name, trade name, or catalog number (unless otherwise specified) is intended to be descriptive but not restrictive and only to indicate articles or materials that will be satisfactory. Bids on other makes and catalogs will be considered, provided each Bidder clearly states on the face of their Bid exactly what is proposed to be furnished. Unless so stated in the Bid, it shall be understood that the Bidder intends to furnish the item specified and does not propose to furnish an "equal".

The City hereby reserves the right to approve as an equal, or to reject as not being an equal, any article the Bidder proposes to furnish which contains minor or major variations from specification requirements.

10. CHANGES:

Illinois law (720 ILCS 5/33E-9) requires that aggregate changes in excess of $25,000 or aggregate extensions greater than one hundred eighty (180) days must comply with the Criminal Code. Likewise, Illinois law (50 ILCS 525/5) expresses for a change order that authorizes or necessitates any increase in the contract price that is 50% or more of the original contract price or that authorizes or necessitates any increase in the price of a subcontract under the contract that is 50% or more of the original subcontract price, then the portion of the contract that is covered by the change order must be resubmitted for bidding in the same manner for which the original contract was bid. Upon approval, the Procurement Officer shall issue to the successful contractor a written change order to the original contract; such change orders shall be binding upon both parties thereto and shall in no way invalidate or make void the terms of the original contract not modified by such change.

11. FAIR EMPLOYMENT

Bidder’s signature on the Bid Form will be construed as acceptance of and willingness to comply with all provisions of the acts of the General Assembly of the State of Illinois relating to wages of laborers and discrimination and intimidation of employees. Provisions of said acts are herein incorporated by reference and become a part of this Bid and Specifications

12. DRUG FREE WORKPLACE ACT

At the time of contract, the Contractor will make certification required in the Contract and will comply with all provisions of the Drug Free Workplace Act that are applicable to the Company. False certification or violation of the requirements of the Drug Free Workplace Act may result in sanctions including but not limited to suspension of the Contract with the City, termination of the Contract and debarment of contracting with the City for at least one (1) year but not more than five (5) years.

13. HAZARD COMMUNICATION

All on-site contractors shall be informed of chemical hazards to which their employees could possibly be exposed while working for the City. Upon request, this information is made available to the contractors and their subcontractors by the prime contractor. It is the contractors and subcontractor’s responsibility to train their own employees on Hazardous Communications and the handling of hazardous materials. It is the responsibility of the contractor to inform the City of any hazardous substances brought and stored on City property. The contractor must also provide a Safety Data sheet for such chemicals.

14. WARRANTY/GUARANTEE

The Bidder warrants to the City that the labor shall be first class and conform to the requirements of the Specifications and shall be performed by persons qualified in their respective trades. Materials furnished under the Contract will be of good quality and new unless otherwise required or permitted under the Specifications, and that materials will be free from defects not inherent in the quality required or permitted. Work and materials not conforming to the Specifications, including substitutions not properly approved and authorized, may be considered defective and will be rejected by the City. This warranty excludes remedy for damage or defect caused by abuse, modifications not executed by the Bidder, improper or insufficient maintenance, improper operation, or normal wear and tear and normal usage. Unless otherwise described in the specifications, materials provided under this agreement will be guaranteed for a period of one year, or the term of the manufacturer’s warranty, whichever is greater. Unless otherwise described in the specifications, labor provided under this agreement will be guaranteed for a period of one year.

15. NON-BARRED BIDDING

The Bidder must certify that it is not barred from bidding on this contract as a result of a conviction for the violation of state laws prohibiting bid-rigging or bid rotating by executing the included certification as required by 720 ILCS 5/33E-11.

16. ILLINOIS FREEDOM OF INFORMATION ACT (FOIA)

Contractor understands that amendments to the Illinois Freedom of Information Act (P.A. 96-0542), which took effect January 1, 2010, requires the Contractor to produce to the City any of its company records and documents which are in any way related to the performance of services under this agreement and not exempt from disclosure within five (5) business days of the City’s receipt of a request for said records. Accordingly, the Contractor. agrees to be bound by the provisions of the Illinois Freedom of Information Act (5 ILCS 140/1 et seq.), and agrees to deliver to the City all records in its possession relating to this agreement within three (3) business days of a request by the City for said records. Contractor agrees to reimburse the City any fees, fines, or costs incurred by or assessed against the City for its failure to deliver requested records in the possession of the Contractor, and which the Contractor failed to deliver to the City within three (3) business days of its receipt of a request from the City to do so. An e-mail request for records and documents sent during business hours will be considered received by the Contractor on the day sent. The Contractor shall not be entitled to receive any wages, fees, or costs of any kind from the City for the production of documents and records in response to a Freedom of Information Act request.

17. INSPECTION OF MATERIALS

The City shall have a right to inspect any materials or equipment to be used in carrying out this contract. The Contractor shall be responsible for the contracted quality and standards of all materials, equipment, components or completed work finished under this contract up to the time of final acceptance by the City.

Materials, equipment, components or completed work not complying therewith may be rejected by the City and shall be removed and replaced by the Contractor at no cost to the City.

18. INDEMNITY

To the fullest extent permitted by law, the Contractor shall waive any right of contribution against the City and shall indemnify and hold harmless the City and the Architect/Engineer and their officers, officials, employees, volunteers and agents from and against all claims, damages losses and expenses, including, but not limited to, legal fees (attorney’s and paralegal’s fees, expert fees and court costs), arising out of or resulting from the performance of the Contractor’s work provided that any such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or injury to or destruction of property, other than the work itself, including the loss of use resulting therefrom, or is attributable to misuse or improper use of patent, trademark or copyright protected material or otherwise protected intellectual property, to the extent it is caused by any wrongful or negligent act or omission of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable. Such obligation shall not be construed to negate, abridge or otherwise reduce any other right to indemnity that the Owner would otherwise have. The Contractor shall similarly, protect, indemnify and hold and save harmless, the Owner, its officers, officials, employee, volunteers and agents against and from any and all claims, costs, causes, actions and expenses, including, but not limited to, legal fees, incurred by reason of Contractor’s breach of any of its obligations under, or Contractor’s default of any provisions of the Contract. The indemnification obligations under this paragraph shall not be limited in any way by any limitation on the amount or type of damages, compensation, or benefits payable by or for the Contractor or any subcontractor under Workers’ Compensation or Disability Benefit Acts or Employee Benefit Act.

19. SUBLETTING OR ASSIGNMENT OF CONTRACT OR CONTRACT FUNDS

No contract shall be assigned or any part of the same subcontracted without the prior written consent of an authorized agent of the City; but in no case shall such consent relieve the Contractor from their obligation or change the terms of this contract. The Contractor shall not transfer or assign any contract funds or claims due or to become due without the prior written approval of an authorized agent of the City having first been obtained.

The unauthorized transfer or assignment of any contract funds in whole or in part, or any interest therein, which shall be due or to become due to the Contractor, shall cause the annulment of said transfer or assignment so far as the City is concerned.

20. CONFLICT OF INTEREST

The Bidder covenants that to the best of its knowledge no member of the governing body of the City, and no other officer, employee, or agent of the City who exercises any functions or responsibilities in connection with the solicitation or approval of this contract, shall have or does have any personal interest, direct or indirect, in this contract.

The Bidder covenants that it presently has no interest and shall not acquire any interest, direct or indirect, in the work to which this contract pertains which would conflict in any manner or degree with the performance of its services hereunder. The Bidder further covenants that in the performance of this contract, it shall not employ any officer, employee, or agent of the City who exercises any functions or responsibilities in connection with the solicitation or approval of this contract.

21. COMPLETION

Bidder shall complete the services within the timeline set forth in the Bid Documents. Failure of the Bidder to complete these services in accordance with the Specifications shall constitute a breach of the Contract.

22. TERMINATION, CANCELLATION AND DAMAGES

This contract may be terminated for convenience upon mutual agreement of both parties. The City may terminate based on the Contractor’s breach or default. Unless the breach or default creates an emergency situation, as determined in the City’s sole discretion, the Contractor shall be given notice and a five (5) day opportunity to correct before the termination becomes effective.

If the City terminates this Contract because of the Contractor’s breach or default, the City shall have the right to purchase items or services elsewhere and to charge the Contractor with any additional cost incurred, including but not limited to the cost to cover, incidental and consequential damages and the cost of re-bidding. The City may offset these additional costs against any sums otherwise due to the Contractor under this bid or any unrelated contract

Upon such termination, Contractor shall be entitled to payment only as follows: (1) the actual cost of the work completed in conformity with this Agreement; plus, (2) any additional costs actually incurred by Contractor as are permitted by the prime contract and approved by City. The Contractor shall not be entitled to any claim or claim of lien against City for any additional compensation or damages in the event of such termination and payment

If the City of Park Ridge fails to appropriate funds to enable continued payment of yearly or multi-year Contracts the City may cancel, without termination charges, provided Contractor received at least thirty (30) days prior written notice of termination.

23. TAX EXEMPTION

Federal Excise Tax does not apply to materials purchased by the City of Park Ridge by virtue of Exemption Certificate No. 36-600-6041. Illinois Retailers' Occupation Tax, Use Tax, and Municipal Retailers' Occupation Tax do not apply to materials or services purchased by the City of Park Ridge by virtue of Statute. Illinois Tax Exemption Identification No. E9998-1408-05. The prices quoted herein shall comply with all Federal Laws and Regulations.

24. PAYMENTS

Payment terms shall be in accordance with the provisions of the Local Government Prompt Payment Act, 50 ILCS 505/1 et seq., after receipt by the City of the Contractor’s invoice.

25. QUANTITIES

The quantities shown herein are estimated for canvassing purposes only, and as such may not represent the actual quantities required during the life of any contract made pursuant to these specifications. Nothing herein shall be construed as an obligation of the City to order or pay for any services other than the amount determined to meet the actual requirements of the City. The right to increase or decrease the quantities shown herein, at any time during the life of this contract, is reserved to the City. The City will only be obligated to pay for such quantities as may be ordered and accepted by the City from time to time.

26. PRICING

Pricing shall remain consistent with the original terms accepted by the City for the term of the contract.

27. TERM OF CONTRACT

The term of this Contract shall be one (1) year following approval by City Council and execution of the contract by the City Manager.

28. PUBLIC RELATIONS

The Contractor shall endeavor at all times to maintain good public relations and to present the City in a positive light. Any action by the Contractor which damages the City’s good will shall be considered a breach of this Agreement.

29. PAYMENT & PERFORMANCE BONDS

The Contractor, before commencing the Work, shall furnish Performance and Payment Bonds per the Illinois Public Construction Bond Act, 30 ILCS 550. Upon notice of acceptance of Bid, the successful Bidder shall, within ten (10) calendar days of said notice, furnish to the City faithful Performance and Payment Bonds in the full amount of the contract, conditioned upon the faithful performance of all covenants, conditions, and stipulations under the contract. The bond shall be secured by a surety company acceptable to the City, licensed to do business as a Surety in the State of Illinois. The terms and conditions described in the Public Construction Bond Act shall be incorporated into the Bonds presented by the successful Bidder as though fully recited therein. The failure of the successful Bidder to enter into an Agreement and supply the required Bond within ten (10) days after the Notice of Award or within such extended period as the Agency may grant if the forms do not meet its approval shall constitute a default, and the Agency may either award the Agreement to the next responsible, responsive Bidder or re-advertise for bids. A charge against the defaulting Bidder may be made for the difference between the amount of the bid and the amount for which a contract for the work is subsequently executed, irrespective of whether the amount thus due exceeds the amount of the bid guarantee.

INSURANCE REQUIREMENTS

Prior to commencing any work or furnishing materials, the successful bidder shall provide the City a certificate of insurance evidencing the required coverages and limits specified below. All insurance shall be issued by a responsible insurer acceptable to the City, licensed to do business in the State of Illinois and rated at least A:VII by A.M. Best. Each policy shall include an endorsement requiring at least thirty (30) days’ prior written notice to the City of Park Ridge of cancellation or reduction in coverage. All required insurance shall be maintained in full force and effect for the duration of the contract and until all work has been approved and accepted by the City.

1. Worker’s Compensation: Statutory coverage for all persons whom the contractor may employ directly or through subcontractors in carrying out the work under this contract. Such insurance shall hold the City free and harmless of all personal injuries of all persons whom the contractor may employ directly or through subcontractors.

Employer’s Liability: $1,000,000 minimum liability for each accident/injury and disease.

2. Commercial General Liability: including bodily injury and property damage. Coverage shall be provided in the following minimum amounts:

$2,000,000.00 General Aggregate $1,000,000.00 Each Occurrence Bodily Injury and Property Damage $1,000,000.00 Products-Completed Operations Aggregate $1,000,000.00 Personal and Advertising Injury

3. Commercial Automobile Liability, Owned, Non-owned and Hired: including bodily injury and property damage, which may arise from the use of motor vehicles engaged in various operations under this contract. Coverage shall be provided in the minimum amount of $1,000,000 each accident for Combined Single Limit.

4. Umbrella Liability: $2,000,000 minimum per occurrence. The scope of coverage provided by the

Umbrella or Excess policy shall follow form with the general liability policy.

The City of Park Ridge shall be named as an additional insured on all liability policies required herein. The Contractor is solely responsible for obtaining and maintaining the required insurance, and such responsibility shall not be waived by any act or omission of the City. The Contractor shall require all subcontractors to maintain the required insurance and, upon request, shall provide the City with certificates of insurance and applicable policy endorsements.

The surety companies, other signers of any required bonds, and the insurance companies shall familiarize themselves with all of the conditions and provisions of these specifications and contract documents, and hereby waive all rights of special notification of any change or modification of this contract in regard to the scope of the work, time of completion, cancellation or termination, or of any other act or acts by the City of Park Ridge or its authorized employees and agents under the terms of this contract. Failure to notify the previously mentioned surety or insurance companies of change or modification shall in no way relieve the surety or insurance companies of their obligations under this contract.

PREVAILING WAGE

☐ The Illinois Prevailing Wage Act does not apply to this contract.

☒ The Illinois Prevailing Wage Act applies to this contract. This contract calls for the construction of “public work,” within the meaning of the Illinois Prevailing Wage Act, 820 ILCS 130/.01 et seq. The Contractor shall comply therewith and pay, and require every Subcontractor to pay, the prevailing rates of wages as established by the Illinois Department of Labor for each craft or type of work needed to execute the contract in accordance with 820 ILCS 130/.01 et seq. Contractor shall prominently post the current schedule of prevailing wages at the Contract site and shall notify immediately in writing all of its Subcontractors, of all changes in the schedule of prevailing wages. Any increases in costs to Contractor due to changes in the prevailing rate of wage during the terms of any contract shall be at the expense of Contractor and not at the expense of the Owner. Change orders shall, however, be computed using the prevailing wage rates applicable at the time the change order work is scheduled to be performed. Contractor shall be solely responsible to maintain accurate records as required by the prevailing wage statute and to obtain and furnish all such records to Owner or Department of Labor as required by Statute including certified payroll or, in lieu thereof, a certified letter stating that the Contractor is exempt from the application of the Act. Contractor shall be solely liable for paying the difference between prevailing wages and any wages actually received by laborers, workmen and/or mechanics engaged in the Work and in every way defend and indemnify Owner against any claims arising under or related to the payment of wages in accordance with the Prevailing Wage Act. The Owner agrees to notify the Contractor or Subcontractor of the pendency of any such claim, demand, lien, or suit.

The Illinois Department of Labor publishes the prevailing wage rates on its website at:

https://labor.illinois.gov/laws-rules/conmed/current-prevailing-rates.html

The Contractor is advised that the Department revises the prevailing wage rates, and the Contractor/subcontractor has an obligation to check the Department’s web site for revisions to prevailing wage rates. For information regarding current prevailing wage rates, please refer to the Illinois Department of Labor’s website.

The Contractor shall also:

(1) Insert into each subcontract and the project specifications for each subcontract, a written stipulation that the subcontractor shall not pay less than the prevailing rate of wages to all laborers, workers, and mechanics performing work under the contract.

(2) Require each subcontractor to insert into each lower-tiered contract and the project specifications for each lower tiered subcontract, a stipulation that the subcontractor shall not pay less than the prevailing rate of wages to all laborers, workers, and mechanics performing work under the contract.

STATEMENT OF WORK

PARK RIDGE PUBLIC LIBRARY

PW-26-13

PROJECT DESCRPITON

The City of Park Ridge is seeking a qualified contractor to furnish all labor, materials, equipment, supervision, permits, traffic and pedestrian control, disposal, and incidentals necessary to complete exterior concrete and masonry repairs at the Park Ridge Public Library, located at 20 South Prospect Avenue, Park Ridge, Illinois, in accordance with the attached structural drawings and details prepared by J.V. Henik, Inc (Exhibit A).

SCOPE OF WORK

The work generally includes, but is not limited to:

• Demolition and replacement of deteriorated concrete sidewalk sections.

• Demolition and reconstruction of portions of the existing concrete retaining wall.

• Masonry tuckpointing of deteriorated mortar joints.

• Removal and replacement of damaged or cracked brick masonry units.

• Concrete stair repairs including removal of deteriorated concrete, installation of reinforcing dowels/pins, and placement of new concrete repair material.

• Repair, removal, resetting, and replacement of limestone capstones at the terrace and front entry walls.

• Removal, repair, repainting, and reinstallation of existing handrail posts, including installation of new grout beds and sealant as required.

• Repair of wall caps, masonry joints, sealants, and other miscellaneous concrete and masonry deficiencies identified in the contract drawings.

• Protection of adjacent improvements, restoration of disturbed areas, and final cleanup.

The contractor shall perform all work in accordance with the contract drawings, details, notes, repair schedules, and manufacturer recommendations.

COMPLETION DATE

The Contractor must complete the project by November 23, 2026.

The completion date pertains to the work items outlined in this contract. Any “Punch List” work that is required shall be completed within 30-days of the completion date of this project.

PROJECT REQUIREMENTS

• Verify all field dimensions and existing conditions prior to construction. Notify the City of any concealed or differing site conditions before proceeding with repairs.

• All mortar, brick, concrete, stone, and sealant colors/textures shall match existing adjacent materials to the satisfaction of the City.

• Coordinate work to maintain safe pedestrian access to the library whenever practical.

• Temporary closures of sidewalks or library entrances must be coordinated with the City and appropriate pedestrian access maintained.

• Dispose all demolished materials off-site in accordance with applicable regulations.

• Restore disturbed lawn and landscaped areas upon completion, if needed.

• Complete all work in accordance with applicable OSHA and local building requirements.

SPECIAL CONDITIONS

FAILURE TO COMPLETE WORK ON TIME

Time is of the essence in the performance of this contract. The Contractor shall achieve Final Completion of the Work on or before the completion date specified in the Contract Documents, or within any extension of time granted in writing by the City. Should the Contractor fail to complete the work within the required contract time, the Contractor shall be liable and shall pay to the City the sum of two-hundred dollars ($200.00) per calendar day, not as a penalty, but as liquidated damages, for each day that Final Completion is delayed beyond the required completion date. The liquidated damages for failure to complete the contract on time are approximate, due to the impracticality of calculating and proving actual delay costs. The liquidated damage amount establishes the cost of delay to account for administration, engineering, inspection, and supervision during periods of extended and delayed performance. The costs of delay represented by the liquidated damages are understood to be a fair and reasonable estimate of the costs that will be borne by the City during extended and delayed performance by the Contractor for the work, remaining incidental work, correction of work improperly completed, or repair of work damaged as a result of the Contractor. The City will deduct these liquidated damages from any monies due, or to become due, to the Contractor from the City.

SCHEDULE OF WORK

The Contractor shall submit a written sequence and timetable for completion of the work within 10 calendar days after award of contract and no later than at the time of the preconstruction meeting.

HOURS OF CONSTRUCTION

Construction operations, including the delivery of equipment, supplies, materials, and the turning on of any engine, are permitted between the hours of 7 A.M. and 7 P.M. Monday – Friday only. Work at any other time, including emergencies, is only permitted with written permission from the City and must be requested a minimum of 48 hours in advance. Violations of this code are subject to Police enforcement and possible fines.

DUST CONTROL

Contractor’s responsibility for dust control. When, in the opinion of the Superintendent, dust becomes a problem despite normal cleanup measures, the Contractor may be required to wash down the work site.

This item shall be incidental to the contract.

Dust shall be controlled by the uniform application of sprinkled water or vacuum system and shall be applied only when directed by the Superintendent, in a manner meeting their approval.

If, in the opinion of the Superintendent, the Contractor has not satisfactorily corrected the dust problem within 4 hours of written notice, the City will deduct the amount of two-hundred dollars ($200.00) from any final payment, for each time dust control measures are required and not utilized.

Dust control will not be paid for separately but will be considered included in the total contract cost.

SITE CONDITION AND CLEAN-UP

The Contractor shall store materials and equipment where directed by the Superintendent of designee and shall move same materials and equipment, if and when it becomes necessary, at it’s own expense.

The Contractor shall have control over their employees' parking of automobiles on the site and shall provide receptacles for depositing wastepaper and garbage. The Contractor shall keep the site neat and shall clean up any debris when directed to do so by the Superintendent. Upon completion of the improvement, the site shall be left in a condition acceptable to the Superintendent and the City. Failure to keep the site neat, or clean up debris when directed to do so, shall be just cause for withholding of payments due to the Contractor and final acceptance will not be made until the site is in a condition acceptable to the Superintendent and City. Any damage to sidewalks, curbs, and parkways due to the negligence of the Contractor shall be restored by the Contractor at their own expense. No additional compensation shall be allowed to the Contractor for compliance with this requirement.

The Contractor shall maintain, during the entire construction period, barricades and warning lights at all material storage areas and around parked construction equipment.

The Contractor shall maintain cordoned off areas where needed in work zones where pedestrian traffic needs to be kept away from crews and equipment. This may be accomplished with barricades, cones and caution tape.

PROTECTION OF EXISITING FACILITIES

Existing facilities, including grounds, structures, landscaping, and so forth shall be protected by the Contractor. Any damage to existing facilities shall be reported to the Superintendent and shall be repaired promptly by the Contractor when ordered to do so by the Superintendent. All repairs of damage to existing facilities shall be made to the satisfaction of the Superintendent. Failure to repair damage shall be just cause to withhold payment for work that becomes due.

The Contractor shall make his own investigation to determine the existence, nature, and location of all utility lines and appurtenances within the limits of the improvement.

The Contractor shall be held responsible for any damage to existing utility lines and appurtenances resulting from the operations of their equipment and/or crew. No extra compensation will be allowed to the Contractor for any expense incurred because of delays, inconvenience, or interruption to their work resulting from compliance with the above requirements.

USE OF FIRE HYDRANTS

If the Contractor desires to use water from fire hydrants, meters and keys shall be obtained from the Water and Sewer Department with a deposit. Upon return of the equipment, the Contractor shall be billed for the water usage at the current rate. This applies to all pay items which require using water, including but not limited to parkway restoration, watering plants, dust control, maintenance of roadways, trench jetting, asphalt cold milling operations, asphalt rolling operations, etc.

Fire hydrants shall be accessible at all times to the Fire Department. No materials or other obstructions shall be placed closer than 15 feet to a fire hydrant. Any arrangements of less than 15 feet must be approved by the Fire Department.

TRAFFIC CONTROL AND PROTECTION

Traffic control shall be in accordance with the applicable sections of the most recent editions of the “Standard Specifications,” the Supplemental Specifications, the Illinois Manual on Uniform Traffic Control Devices for Streets and Highways, any special details and highway standards contained in the plans, the Traffic Specifications, and the Special Provisions contained herein.

END OF SPECIAL CONDITIONS

BID FORM

PW-26-13

The bid price shall include, as applicable, all machinery, materials, equipment, tools, labor, storage, delivery, disposal, and incidentals required to complete the Scope of Work for the project. Proposals are all inclusive and there shall be no additional charges during the term of the Contract.

Vendor Name:___________________________________________ Total Bid Amount: __________________________________________________ (in words)

FORM A

CONTRACT EXECUTION

TO BE EXECUTED BY OWNER / SOLE PROPRIETOR

Signature of Proprietor: ____________________________________________________

Doing Business As: _______________________________________________________

Business Address: ________________________________________________________

TO BE EXECUTED BY A PARTNERSHIP/LIMITED LIABILITY COMPANY

Partnership Name: ________________________________________________________

Business Address: ________________________________________________________

Signatures and Addresses of All Members of the Partnership/Managers of the LLC:

1)______________________________________________________________________

2) ______________________________________________________________________

TO BE EXECUTED BY A CORPORATION

Corporate name: __________________________________________________________

Address: ________________________________________________________________

State of Incorporation: _____________________________________________________

Names of Officers of the Corporation:

President: Secretary:

Vice President: Treasurer:

The undersigned agrees to perform the Scope of Work according to the terms and conditions of the Contract Documents, including the Bid Proposal and pricing hereby submitted, and I understand that any conflict between the Contract Documents and the Proposal will be resolved in favor of the Contract Documents.

• The undersigned hereby acknowledges having received a full Bid Document including ADDENDA

NUMBERS________________________ (if applicable)

Signature Date

Print Name Title

FORM B

CONTRACTOR CERTIFICATIONS / AFFIDAVIT

Please certify the following by signing below:

A. CERTIFICATION TAX COMPLIANCE

Bidder is not delinquent in the payment of any tax administered by the Illinois Department of Revenue or the City of Park Ridge, or if it is:

(1) it is contesting its liability for the tax or the amount of tax in accordance with procedures established by the appropriate Revenue Act; or

(2) it has entered into an agreement with the Department of Revenue for payment of all taxes due and is currently in compliance with that agreement.

B. CERTIFICATION - SEXUAL HARASSMENT POLICY

The undersigned, on behalf of the entity making this Bid or bid, certified that a written sexual harassment policy is in place, pursuant to Public Act 87-1257, effective July 1, 1993, 775 ILCS 5/2- 105 A. This Act has been amended to provide that every party to a public contract must have a written sexual harassment policy that includes, at a minimum, the following information:

1. The illegality of sexual harassment;

2. The definition of sexual harassment, under State law;

3. A description of sexual harassment, utilizing examples;

4. The vendor’s internal complaint process including penalties;

5. The legal recourse, investigative and complaint process available through the Department of

Human Rights and the Human Rights Commission;

6. Directions on how to contact the Department and Commission;

7. Protection against retaliation as provided by 6-101 of the Act.

C. ILLINOIS DRUG FREE WORKPLACE STATEMENT

1. Notify employees that the unlawful manufacture, distribution, dispensation, possession, or use of a controlled substance is prohibited in the workplace.

2. Specifying the actions that will be taken against employees for violating this provision.

3. Notifying the employees that, as a condition of their employment to do work under the contract with the City, the employee will:

a. Abide by the terms of the statement.

b. Notify the undersigned of any criminal drug stature conviction for a violation occurring in the workplace not later than five (5) days after such a conviction.

4. Establishing a drug free awareness program to inform employees about:

a. The dangers of drug abuse in the workplace.

b. The policy of maintaining a drug-free workplace.

c. Any available drug counseling, rehabilitation, or employee assistance program.

d. The penalties that may be imposed upon an employee for drug violations.

5. The undersigned shall provide a copy of the required statement to each employee engaged in the performance of the contract with the City and shall post the statement in a prominent place in the workplace.

6. The undersigned will notify the City within ten (10) days of receiving notice of an employee’s conviction.

7. Make a good faith effort to maintain a drug free workplace through the implementation of these policies.

8. The undersigned further affirms that within thirty (30) days after receiving notice of a conviction of a violation of the criminal drug statue occurring in the workplace, he shall:

a. Take appropriate action against such employee up to and including termination; or

b. Require the employee to satisfactorily participate in a drug abuse assistance or rehabilitation program approved for such purposed by a federal, state, or local health, law enforcement, or other appropriate agency.

D. BID RIGGING / ANTI-COLLUSION AFFIDAVIT

The undersigned does hereby certify to the City, its Council Members, officers and employees that neither I nor employees of the company are barred from bidding on the contract for which this bid is submitted, as a result of violation of either Section 33E-3 ("Bid-rigging") or Section 33E-4 ("Bid-rotating") of Article 33E of the Criminal Code of 1961 of the State of Illinois approved July 28, 1961, as amended.

E. CERTIFICATION - EQUAL EMPLOYMENT OPPORTUNITY

The Contractor and all subcontractors shall not discriminate against any employee or applicant for employment because of race, religion, color, sex, or national origin. The Contractor also agrees that all of the Contractors employees are authorized to work in the United States. Contractor shall comply with all terms of the Equal Employment Opportunity Clause of the Illinois Fair Employment Practices Commission.

The Contractor shall take affirmative action to ensure that all applicants are employed, and that employees are equally treated during employment, without regard to their race, religion, color, sex, or national origin. Such action shall include, but not to be limited to the following:

1. Employment, upgrading, demotion and transfer.

2. Recruitment or recruitment advertising.

3. Layoff or termination.

4. Rates of pay or other forms of compensation.

5. Selection for training including apprenticeship.

The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .