CHR Elevator Modernization_Technical Specification.pdf
PDF 933 KB Posted
- Attached to
- Chaleroi Elevator Modernization Federal contract opportunity
- Solicitation number
- W911WN23B8022
About this file
This document outlines a federal contract opportunity for elevator modernization work. The U.S. Army Corps of Engineers, Pittsburgh District, requires refurbishing an existing electrical geared traction elevator at the Monongahela River Charleroi Locks and Dam in Westmoreland County, Pennsylvania. The major work includes removing and replacing the elevator driving machine, controls, wiring, cables, fixtures, and governor assembly. Additional work involves installing a new HVAC split system, upgrading lighting and receptacles, and installing fire and smoke detectors. The small business set-aside has a size standard of $22 million. The Government anticipates the construction and service repair work will take less than 270 days at an estimated cost between $250,000 and $500,000. Interested contractors should be registered in the System for Award Management and Procurement Integrated Enterprise Environment Solicitation Module by mid-August when the solicitation is expected to post and award made.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Results List Bid Opening.pdf | ||
| DBA WD 06232023.gov.pdf | ||
| W911WN23B8022 Amendment 2.pdf | ||
| CHR Site Visit Sign in Sheet.pdf | ||
| W911WN23B8022 0001.pdf | ||
| W911WN23B8022 06212023.pdf | ||
| DBA WD 06152023.gov.pdf | ||
| CHR Reference Dwgs Photos.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W911WN23B8022
Elevator Modernization Monongahela River Basin Charleroi Locks and Dam
100% CERTIFIED FINAL (HTC)
Technical Specifications
June 2023
Elevator Modernization CHRELEVREHAB23
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 22 00.00 08 PRICE AND PAYMENT PROCEDURES
01 30 00.00 08 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 08 PROJECT SCHEDULE BAR CHART
01 33 00 SUBMITTAL PROCEDURES
01 35 00.00 08 SPECIAL PROCEDURES
01 35 26.00 08 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 08 QUALITY CONTROL
01 45 00.15 08 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19.00 08 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 02.00 08 CLOSEOUT SUBMITTALS (AS-BUILT DRAWINGS)
01 78 23 OPERATION AND MAINTENANCE MANUALS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
DI VI SI ON 14 - CONVEYI NG EQUI PMENT
14 21 13 ELECTRIC TRACTION FREIGHT ELEVATORS
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
100% CERTIFIED FINAL (HTC) - W911WN23B8022
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 08
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
1.2 SINGLE JOB PAYMENT ITEMS
1.2.1 Reimbursement For Actual Performance And Payment Bond Premiums
1.2.2 Rehabilitation of Elevator
1.2.2.1 Payment
1.2.2.2 Unit of Measure
1.2.2.3 Payment Item (s)
1.2.3 HVAC Unit
1.2.3.1 Payment
1.2.3.2 Unit of Measure
1.2.3.3 Payment Item (s)
1.2.4 Electrical Upgrade
1.2.4.1 Payment
1.2.4.2 Unit of Measure
1.2.4.3 Payment Item (s)
1.2.5 Replacement of Existing Elevator Car
1.2.5.1 Payment
1.2.5.2 Unit of Measure
1.2.5.3 Payment Item (s)
1.2.6 Replacement of Existing Crosshead
1.2.6.1 Payment
1.2.6.2 Unit of Measure
1.2.6.3 Payment Item (s)
1.2.7 Replacement of Existing Safety Plank
1.2.7.1 Payment
1.2.7.2 Unit of Measure
1.2.7.3 Payment Item (s)
1.2.8 Replacement of Existing Deflector Sheaves
1.2.8.1 Payment
1.2.8.2 Unit of Measure
1.2.8.3 Payment Item (s)
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 22 00.00 08 Page 1
SECTION 01 22 00.00 08
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for i nformation only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
1.2 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Reimbursement For Actual Performance And Payment Bond Premiums
Payment for reimbursement for actual performance and payment bond premiums will be made as specified in 00 73 00 SUPPLEMENTARY CONDITIONS, PARAGRAPH
00 73 00 - 02 PAYMENT FOR PERFORMANCE AND PAYMENT BONDS.
0001 REIMBURSEMENT FOR ACTUAL PERFORMANCE AND PAYMENT BOND PREMIUMS
1.2.2 Rehabilitation of Elevator
1.2.2.1 Payment
Payment will be made for costs associated with rehabilitation of elevator (see Section 14 21 13 for more details), heat/smoke detector upgrade, and inspection of existing car, crosshead, safety plank & deflector sheaves.
1.2.2.2 Unit of Measure
Unit of measure: Job.
1.2.2.3 Payment Item (s)
0002 REHABILITATION OF ELEVATOR
1.2.3 HVAC Unit
1.2.3.1 Payment
Payment will be made for costs associated with furnishing and installing
SECTION 01 22 00.00 08 Page 2 new HVAC unit.
1.2.3.2 Unit of Measure
Unit of measure: Job.
1.2.3.3 Payment Item (s)
0003 HVAC UNIT
1.2.4 Electrical Upgrade
1.2.4.1 Payment
Payment will be made for costs associated with all electrical work upgrade.
1.2.4.2 Unit of Measure
Unit of measure: Job.
1.2.4.3 Payment Item (s)
0004 ELECTRICAL UPGRADE
1.2.5 Replacement of Existing Elevator Car
1.2.5.1 Payment
Payment will be made for costs associated with 'in-kind' replacement of elevator car if not in satisfactory condition.
1.2.5.2 Unit of Measure
Unit of measure: Job.
1.2.5.3 Payment Item (s)
0005 REPLACEMENT OF EXISTING ELEVATOR CAR
1.2.6 Replacement of Existing Crosshead
1.2.6.1 Payment
Payment will be made for costs associated with 'in-kind' replacement of crosshead if not in satisfactory condition.
1.2.6.2 Unit of Measure
Unit of measure: Job.
1.2.6.3 Payment Item (s)
0006 REPLACEMENT OF EXISTING CROSSHEAD
1.2.7 Replacement of Existing Safety Plank
1.2.7.1 Payment
Payment will be made for costs associated with 'in-kind' replacement of
SECTION 01 22 00.00 08 Page 3 safety plank if not in satisfactory condition.
1.2.7.2 Unit of Measure
Unit of measure: Job.
1.2.7.3 Payment Item (s)
0007 REPLACEMENT OF EXISTING SAFETY PLANK
1.2.8 Replacement of Existing Deflector Sheaves
1.2.8.1 Payment
Payment will be made for costs associated with 'in-kind' replacement of deflector sheaves if not in satisfactory condition.
1.2.8.2 Unit of Measure
Unit of measure: Job.
1.2.8.3 Payment Item (s)
0008 REPLACEMENT OF EXISTING DEFLECTOR SHEAVES
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 22 00.00 08 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00.00 08
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 ACRONYMS
1.4 CONTRACT ADMINISTRATION
1.5 USACE ACQUISITION INSTRUCTIONS (UAI)
1.5.1 UAI 5122.1302-100 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY
CORPS OF ENGINEERS CONTRACTS
1.6 SUPERVISION
1.6.1 Minimum Communication Requirements
1.6.2 Superintendent Qualifications
1.6.2.1 Duties
1.6.3 Non-Compliance Actions
1.7 PRECONSTRUCTION CONFERENCE
1.8 PARTNERING
1.8.1 Informal Partnering
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 30 00.00 08 Page 1
SECTION 01 30 00.00 08
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 SUMMARY
This sections contains contract administrative requirements which are not covered in Section 00 70 00 CONDITIONS OF THE CONTRACT or Section 00 73 00
SUPPLEMENTARY CONDITIONS.
1.2 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.3 ACRONYMS
DFARS - Defense Federal Acquisition Regulations Supplement EP - Engineer Pamphlet FAR - Federal Acquisition Regulations SAT - Simplified Acquisition Threshold UAI - USACE Acquisition Instructions
1.4 CONTRACT ADMINISTRATION
An Administrative Contracting Officer or designated representative will be designated on this contract to act within the limits delegated by the Contracting Officer. The Administrative Contracting Officer or designated representative designation letter will clearly detail what the authorities of the Administrative Contracting Officer or designated representative.
1.5 USACE ACQUISITION INSTRUCTIONS (UAI)
1.5.1 UAI 5122.1302-100 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS
OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
U.S. Department of Labor Veterans’ Employment and Training Service (VETS): https://www.dol.gov/vets/
SECTION 01 30 00.00 08 Page 2
Federal Veteran Employment Information: https://www.fedshirevets.gov/
Veterans Opportunity to Work (VOW) Program:
https://www.benefits.va.gov/vow/
U.S. Army Warrior Transition Command Employment Index:
https://wct.army.mil/modules/employers/index.html
Hiring Our Heroes:
https://www.uschamberfoundation.org/hiring-our-heroes
1.6 SUPERVISION
1.6.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.6.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years of experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer or designated representative may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.6.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer or designated representative for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer or designated representative may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
SECTION 01 30 00.00 08 Page 3
1.7 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer or designated representative to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, clear expectations of the "Interim DD Form 1354" Submittal, and the processes for joint risk management between the Contractor and Government. Major subcontractors who will engage in the work must also attend.
1.8 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that includes joint risk management, is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer or designated representative will provide Information on the Informal Partnering Process and a list of key and optional personnel who should attend the Informal Partnering meeting.
1.8.1 Informal Partnering
The Contracting Officer or designated representative will organize the Informal Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.
The Initial Informal Partnering session should be a part of the Pre-Construction Meeting. Informal Partnering sessions will be held at a location agreed to by the Contracting Officer or designated representative and the Contractor (typically a conference room provided by the Resident Engineer office or the Contractor). The Initial Informal Partnering Session may be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer or designated representative. The Partners will determine the frequency of the follow-on sessions, at no more than three to six month intervals.
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
NOT USED
-- End of Section --
SECTION 01 30 00.00 08 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 01.00 08
PROJECT SCHEDULE BAR CHART
PART 1 GENERAL
1.1 SUBMITTALS
1.2 PROJECT SCHEDULER QUALIFICATIONS
PART 2 EXECUTION
2.1 GENERAL REQUIREMENTS
2.2 PROGRESS SCHEDULE - BAR CHART
2.3 REQUESTS FOR TIME EXTENSIONS
2.3.1 Justification of Delay
2.3.2 Time Extension
2.3.3 Impact to Early Completion Schedule
2.4 FAILURE TO ACHIEVE PROGRESS
2.4.1 Artificially Improving Progress
2.4.2 Failure to Perform
2.4.3 Recovery Schedule
-- End of Section Table of Contents --
SECTION 01 32 01.00 08 Page 1
SECTION 01 32 01.00 08
PROJECT SCHEDULE BAR CHART
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Progress Schedule - Bar Chart; G, RO
1.2 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports.
PART 2 EXECUTION
2.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor.
Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. A bar chart shall be prepared in accordance with paragraph PROGRESS SCHEDULE
- BAR CHART.
2.2 PROGRESS SCHEDULE - BAR CHART
The progress chart to be prepared by the Contractor pursuant to Section 00
70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-15 SCHEDULES FOR CONSTRUCTION
CONTRACTS shall consist of a bar chart as described herein. In preparing this schedule, the scheduling of construction is the responsibility of the Contractor and contractor management personnel shall actively participate in its development. The chart may be prepared in a format proposed by the Contractor and approved by the Contracting Officer or designed representative. Each activity shall include the applicable Price Schedule item number and show the estimated cost and show activity duration.
Larger activities shall be broken down into smaller activities with clearly defined limits (i.e. Excavation between STA xx and STA yy). In general, the estimated cost of any individual activity should not exceed $50,000. The selection and number of activities shall be subject to the Contracting Officer or designated representative approval. The chart shall
SECTION 01 32 01.00 08 Page 2 be updated monthly to show actual progress and percentage of work completed for each activity. The Contractor shall submit, as part of his monthly request for payment, updated copies of his progress schedule identifying the work completed during the reporting period. If the Government issues changes to the existing work or adds additional work items to the contract, the Contractor shall revise his progress schedule accordingly. All costs associated with revising the schedule shall be included as part of the modification of the contract. If the Contractor's progress falls behind his planned work effort, a revised schedule shall be furnished to show how the Contractor proposes to complete the remaining work within the contract time. If the Contractor fails to submit updates as required, the Contracting Officer may withhold approval of partial payment estimates, until such submittals are made.
2.3 REQUESTS FOR TIME EXTENSIONS
Provide a justification of delay to the Contracting Officer or designated representative in accordance with the contract provisions and clauses for approval within 10 calendar days of a delay occurring. Also prepare a time impact analysis for each Government request for proposal (RFP) to justify time extensions.
2.3.1 Justification of Delay
Provide a description of the event(s) that caused the delay and/or impact to the work. As part of the description, identify all schedule activities impacted. Show that the event that caused the delay/impact was the responsibility of the Government. Provide a time impact analysis that demonstrates the effects of the delay or impact on the project completion date or interim completion date(s). Evaluate multiple impacts chronologically; each with its own justification of delay. With multiple impacts consider any concurrency of delay. A time extension becomes part of the project schedule and all future schedule updates upon approval by the Contracting Officer or designated representative.
2.3.2 Time Extension
The Contracting Officer or designated representative must approve the Justification of Delay including the time impact analysis before a time extension will be granted. No time extension will be granted unless the delay consumes all available Project Float and extends the projected finish date ("End Project" milestone) beyond the Contract Completion Date.
The time extension will be in calendar days.
Actual delays that are found to be caused by the Contractor's own actions, which result in a calculated schedule delay will not be a cause for an extension to the performance period, completion date, or any interim milestone date.
2.3.3 Impact to Early Completion Schedule
No extended overhead will be paid for delay prior to the original Contract Completion Date for an Early Completion IPS unless the Contractor actually performed work in accordance with that Early Completion Schedule. The Contractor must show that an early completion was achievable had it not been for the impact.
SECTION 01 32 01.00 08 Page 3
2.4 FAILURE TO ACHIEVE PROGRESS
Should the progress fall behind the approved project schedule for reasons other than those that are excusable within the terms of the contract, the Contracting Officer or designated representative may require provision of a written recovery plan for approval. The plan must detail how progress will be made-up to include which activities will be accelerated by adding additional crews, longer work hours, extra work days, etc.
2.4.1 Artificially Improving Progress
Artificially improving progress is prohibited. Indicate assumptions made and the basis for any duration and calendar changes used in the creation of the recovery plan. Any additional resources, manpower, or daily and weekly work hour changes proposed in the recovery plan must be evident at the work site and documented in the daily report along with the Schedule Narrative Report.
2.4.2 Failure to Perform
Failure to perform work and maintain progress in accordance with the supplemental recovery plan may result in an interim and final unsatisfactory performance rating and may result in corrective action directed by the Contracting Officer or designated representative pursuant to Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS, FAR 52.249-10 DEFAULT (Fixed-Price Construction), and other contract provisions.
2.4.3 Recovery Schedule
Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS.
-- End of Section --
SECTION 01 32 01.00 08 Page 4
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
1.1.2 Project Type
1.1.3 Submission of Submittals
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
1.4.2 For Information Only
1.5 PREPARATION
1.5.1 Transmittal Form
1.5.2 Identifying Submittals
1.5.3 Submittal Format
1.5.3.1 Format of SD-01 Preconstruction Submittals
1.5.3.2 Format for SD-02 Shop Drawings
1.5.3.2.1 Drawing Identification
1.5.3.3 Format of SD-03 Product Data
1.5.3.3.1 Product Information
1.5.3.3.2 Standards
1.5.3.3.3 Data Submission
1.5.3.4 Format of SD-05 Design Data
1.5.3.5 Format of SD-06 Test Reports
1.5.3.6 Format of SD-07 Certificates
1.5.3.7 Format of SD-08 Manufacturer's Instructions
1.5.3.7.1 Standards
1.5.3.8 Format of SD-09 Manufacturer's Field Reports
1.5.3.9 Format of SD-10 Operation and Maintenance Data (O&M)
1.5.3.10 Format of SD-11 Closeout Submittals
1.5.4 Source Drawings for Shop Drawings
1.5.4.1 Source Drawings
1.5.4.2 Terms and Conditions
1.5.5 Electronic File Format
1.6 QUANTITY OF SUBMITTALS
1.7 INFORMATION ONLY SUBMITTALS
1.8 PROJECT SUBMITTAL REGISTER
1.8.1 Submittal Management
1.8.2 Preconstruction Use of Submittal Register
1.8.3 Contractor Use of Submittal Register
1.8.4 Approving Authority Use of Submittal Register
1.8.5 Action Codes
1.8.5.1 Contractor Action Codes
SECTION 01 33 00 Page 1
1.8.6 Delivery of Copies
1.9 VARIATIONS
1.9.1 Considering Variations
1.9.2 Proposing Variations
1.9.3 Warranting that Variations are Compatible
1.9.4 Review Schedule Extension
1.10 SCHEDULING
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED SUBMITTALS
1.13 APPROVED SUBMITTALS
1.14 APPROVED SAMPLES
1.15 WITHHOLDING OF PAYMENT
1.16 STAMPS
PART 2 PRODUCTS
PART 3 EXECUTION
ATTACHMENTS:
attached to these specifications
-- End of Section Table of Contents --
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
The Contracting Officer or designated representative may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2 Project Type
The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, Manufacturer's, or Fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves;
test reports; test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required submittals.
1.1.3 Submission of Submittals
Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby.
All submittals shall be in English.
Section 00 70 00 CONDITIONS OF THE CONTRACT , FAR 52.236-5, MATERIAL AND WORKMANSHIP, paragraph (b) and FAR 52.236-21 Alternate I, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, paragraphs (d), (e), and (f) apply to all submittals.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
SD-01 Preconstruction Submittals
Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.
Preconstruction Submittals include schedules and a tabular list of
SECTION 01 33 00 Page 3 locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of Insurance
Surety Bonds
List of Proposed Subcontractors
List of Proposed Products
Baseline Network Analysis Schedule (NAS) or Construction Progress Schedule
Submittal Register
Schedule Of Prices Or Earned Value Report
Accident Prevention Plan
Work Plan
Quality Control (QC) Plan
Environmental Protection Plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
Design submittals, design substantiation submittals and extensions of design submittals.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a
SECTION 01 33 00 Page 4 material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Testing must have been within three years of date of contract award for the project.
Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports
Daily logs and checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits
Text of posted operating instructions
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and As-Built drawings. Also, SECTION 01 33 00 Page 5 submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve the submittal.
1.2.3 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G, RO
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.
Within the terms of Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-21 Alternate I, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."
1.4.2 For Information Only
Submittals not requiring Government approval will be for information only. Within the terms of Section 00 70 00 CONDITIONS OF THE CONTRACT, FAR 52.236-21 Alternate I, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."
1.5 PREPARATION
1.5.1 Transmittal Form
Use the ENG Form 4025 transmittal form for submitting both Government-approved and information-only submittals. Submit in accordance with the instructions on the reverse side of the form. These forms are included in the RMS CM software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
SECTION 01 33 00 Page 6
1.5.2 Identifying Submittals
The Contractor's Quality Control Manager must prepare, review and stamp submittals, including those provided by a subcontractor, before submittal to the Government.
Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title and location
b. Construction contract number
c. Dates of the drawings and revisions
d. Name, address, and telephone number of Subcontractor, supplier, manufacturer, and any other Subcontractor associated with the submittal.
e. Section number of the specification by which submittal is required
f. Submittal description (SD) number of each component of submittal
g. For a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission
h. Product identification and location in project.
1.5.3 Submittal Format
1.5.3.1 Format of SD-01 Preconstruction Submittals
When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.3.2 Format for SD-02 Shop Drawings
Unless otherwise specified, shop drawings shall be full size ANSI D (22 inches by 34 inches). Prepare drawings to accurate size, with scale indicated, unless another form is required. Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.
a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.
b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.
Shop drawings shall be submitted electronically through directly through
SECTION 01 33 00 Page 7 the Resident Management System (RMS) in accordance with paragraph Electronic File Format. Reproduced contract drawings submitted as shop drawings will not be accepted. All electronic shop drawings submitted, regardless of size, shall have a clear space 3 inches by 4 inches in size, in the lower right hand corner just above the title block in which the Government may indicate the action taken. This clear space shall be located in the same exact location on all of the shop drawings within a given Portable Document Format (PDF) file to facilitate electronic stamping. All shop drawings within the same PDF file shall be of the same page size.
1.5.3.2.1 Drawing Identification
Include on each drawing the drawing title, number, date, and revision numbers and dates.
Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.
1.5.3.3 Format of SD-03 Product Data
Present product data submittals for each section as a complete, bound volume . Include a table of contents, listing the page and catalog item numbers for product data.
Indicate, by prominent notation, each product that is being submitted;
indicate the specification section number and paragraph number to which it pertains.
1.5.3.3.1 Product Information
Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.
Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.
1.5.3.3.2 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer or designated representative. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
SECTION 01 33 00 Page 8
1.5.3.3.3 Data Submission
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of the construction effort.
Submit the manufacturer's instructions before installation.
1.5.3.4 Format of SD-05 Design Data
Provide design data and certificates on 8 1/2 by 11 inch paper. Provide a bound volume for submittals containing numerous pages.
1.5.3.5 Format of SD-06 Test Reports
Provide reports on 8 1/2 by 11 inch paper in a complete bound volume.
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
1.5.3.6 Format of SD-07 Certificates
Provide design data and certificates on 8 1/2 by 11 inch paper. Provide a bound volume for submittals containing numerous pages.
1.5.3.7 Format of SD-08 Manufacturer's Instructions
Present manufacturer's instructions submittals for each section as a complete, bound volume . Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry, and technical-society publication references. If supplemental information is needed to clarify the manufacturer's data, submit it as specified for SD-07 Certificates.
Submit the manufacturer's instructions before installation.
1.5.3.7.1 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer or designated representative. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.3.8 Format of SD-09 Manufacturer's Field Reports
Provide reports on 8 1/2 by 11 inch paper in a complete bound volume.
By prominent notation, indicate each report in the submittal. Indicate the
SECTION 01 33 00 Page 9 specification number and paragraph number to which each report pertains.
1.5.3.9 Format of SD-10 Operation and Maintenance Data (O&M)
Comply with the requirements specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA for O&M Data format.
1.5.3.10 Format of SD-11 Closeout Submittals
When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.4 Source Drawings for Shop Drawings
1.5.4.1 Source Drawings
The entire set of source drawing files (DWG) will not be provided to the Contractor. Request the specific Drawing Number for the preparation of shop drawings. Only those drawings requested to prepare shop drawings will be provided. These drawings are provided only after award.
1.5.4.2 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim, and waives to the fullest extent permitted by law any claim or cause of action of any nature against the Government, its agents, or its subconsultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities, or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic source drawing files are not construction documents.
Differences may exist between the source drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic source drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. The Contractor is responsible for determining if any conflict exists. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished source drawing files, the signed and sealed construction documents govern. Use of these source drawing files does not relieve the Contractor of the duty to fully comply with the contract documents, including and without limitation the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction data related to this contract, remove all previous indication of ownership (seals, logos, signatures, initials and dates).
SECTION 01 33 00 Page 10
1.5.5 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. All electronic submittals shall be submitted directly through the Resident Management System (RMS) in accordance with Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM). Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, and coordinate the file naming convention with the Contracting Officer or designated representative. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer or designated representative. Generate PDF files directly from original electronic documents, and include bookmarks, so that the text included in the PDF file is searchable and can be copied. Scanned documents shall be limited to when documents cannot be generated directly from a native software or program and shall be limited to signed letters, certificates of compliance and material certificates. If documents are scanned, optical character recognition (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file so that the text included in the PDF file is searchable and can be copied. When required, the electronic file must include a valid electronic signature or a scan of a signature.
Electronic shop drawings shall be submitted in large size format (ANSI D) and have the reserved clear space as described in paragraph FORMAT FOR SD-02 SHOP DRAWINGS. Scanned shop drawing submitted as electronic files shall be rejected. The text size, arrow heads and drafting leaders shall be of sufficient size to be legible on the electronic shop drawings using industry CADD drafting standards. For example the industry minimally acceptable standard text size on large size format drawings is 1/8-inch text height. All text and graphics on the shop drawings shall be in black with gray pattern shading only.
Testing reports and demonstration reports shall be submitted in electronic format in black and white or in full color as appropriate to present the information in a clear and concise manner.
It is acceptable to scan signed letters and place the scanned document at the front of the submittal with the remaining portion of the report text, graphs and pictures generated directly from the original native program.
1.6 QUANTITY OF SUBMITTALS
All electronic submittals shall be submitted directly through the Resident Management System (RMS) in accordance with Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM). At the direction by the Contracting Officer or designated representative, provide hard copies of submittals as specified in this or other specification sections. Up to five additional hard copies of any submittal may be requested from the Contractor at the discretion of the Contracting Officer or designated representative, at no additional cost to the Government.
In addition, after all shop drawings are approved the Contractor shall submit one approved full size hard copy set of shop drawings to the Contracting Officer or designated representative.
All hardcopy submittals shall be submitted to:
SECTION 01 33 00 Page 11
Resident Engineer Lower Mon Resident Office 1811 Schoonmaker Road Monessen, PA 15062
1.7 INFORMATION ONLY SUBMITTALS
Submittals without a "G" designation must be certified by the QC manager and submitted to the Contracting Officer or designated representative for information-only. Approval is not required on information only submittals. The Contracting Officer or designated representative will mark "receipt acknowledged" on submittals for information and will return only the transmittal cover sheet to the Contractor. Normally, submittals for information only will not be returned. However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract.
This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer or designated representative from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.8 PROJECT SUBMITTAL REGISTER
A sample Project Submittal Register showing items of equipment and materials for when submittals are required by the specifications is attached to these specifications.
1.8.1 Submittal Management
Prepare and maintain a submittal register, as the work progresses. Do not change data that is output in columns (c), (d), (e), and (f) as delivered by Government; retain data that is output in columns (a), (g), (h), and
(i) as approved. As an attachment, provide a submittal register showing items of equipment and materials for which submittals are required by the specifications. This list may not be all-inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM). The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD Number and type, e.g., SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in each specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting the project requirements.
SECTION 01 33 00 Page 12
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.
1.8.2 Preconstruction Use of Submittal Register
Submit the submittal register. Include the QC plan and the project schedule. Verify that all submittals required for the project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for the approving authority to receive submittals.
Column (h) Contractor Approval Date: Date that Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.8.3 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in the program used by the Contractor with each submittal throughout the contract.
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) Date submittal transmitted.
Column (q) Date approval was received.
1.8.4 Approving Authority Use of Submittal Register
Update the following fields:
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (l) Date submittal was received.
Column (m) through (p) Dates of review actions.
Column (q) Date of return to Contractor.
SECTION 01 33 00 Page 13
1.8.5 Action Codes
1.8.5.1 Contractor Action Codes
DESIGN BID BUILD SUBMITTALS
Submittal Classifications shown in UFGS Sections
Submittal Classification
Corresponding SpecsIntact
Submittal Register Code which is populated in the SI Submittal Register.
Software Limitations:
(The software shows one character delineation in the SpecsIntact Submittal Register)
RMS – The following Submittal
Classifications are populated in RMS when the SpecsIntact
Submittal Data File is…
This is the start of the file's text. The full file is on GovTribe.