The document is a Bid Schedule for the Westlands Park Water Feature Reconstruction project located in Colorado, detailing a comprehensive reconstruction of an existing water feature. The bid schedule encompasses 54 line items covering extensive work including mobilization, construction fencing, erosion control, demolition, concrete work, landscaping, plumbing, and mechanical systems. Key quantities include 1,184 square feet of colored concrete splash pad, 337 square feet of sandstone pavers, 13 seat boulders, 32 ornamental grasses, 650 linear feet of 4-inch supply piping, and various nozzle and valve assemblies. The project involves replacing pumps, installing new control panels, and renovating mechanical systems with an add alternate lump sum option for mechanical system renovations.
The bid schedule shows all line items currently priced at $0.00, indicating this is likely a preliminary document awaiting final pricing from contractors. The project appears to be a comprehensive water feature reconstruction that includes significant infrastructure upgrades involving concrete work, landscaping, hydraulic systems, and decorative elements. The scope suggests a complex municipal park improvement project with multiple technical components, requiring specialized construction and landscape expertise. While no specific budget is listed, the extensive line items suggest a substantial capital investment in park infrastructure and aesthetic improvements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Schedule Westlands Park Water Feature Reconstruction Bid Schedule June 24, 2025
| Item # | Item | Qty | Unit | Unit Price | Cost |
| 1 | Mobilization | 1 | LS | $0.00 | |
| 2 | Construction Fencing | 1 | LS | $0.00 | |
| 3 | Erosion Control | 1 | LS | $0.00 | |
| 4 | Construction Surveying | 1 | LS | $0.00 | |
| 5 | Demolition Items at Mechanical Room | 1 | LS | $0.00 | |
| 6 | Demolition Items at Plaza and in Park | 1 | LS | $0.00 | |
| 7 | Colored Concrete Splash Pad - Sandscape Finish, Thickened Section at Boulders | 1,184 | SF | $0.00 | |
| 8 | Wier Wall - With Formliner | 20 | LF | $0.00 | |
| 9 | Sandstone Pavers - Mortor Set Along Channel | 337 | SF | $0.00 | |
| 10 | Integral Colored Concrete Channel | 285 | SF | $0.00 | |
| 11 | Channel Waterproof Liner | 622 | SF | $0.00 | |
| 12 | Seat Boulders | 13 | EA | $0.00 | |
| 13 | Stepping Stone Boulders | 10 | EA | $0.00 | |
| 14 | Bubbler Boulders - Water Source For Channels | 3 | EA | $0.00 | |
| 15 | Reset Existing Boulders - Splash Pad | 7 | EA | $0.00 | |
| 16 | Reset Existing Boulders - Along Channel | 14 | EA | $0.00 | |
| 17 | Sandstone Stone Pavers - Sand Set | 70 | SF | $0.00 | |
| 18 | Ornametnal Trees | 1 | EA | $0.00 | |
| 19 | Ornamental Grasses | 32 | LS | $0.00 | |
| 20 | Perennials | 87 | LS | $0.00 | |
| 21 | Organic Mulch - Monkey Fur | 422 | SF | $0.00 | |
| 22 | Masonry Seat Wall - CIP Concrete with Stone Cap and Veneer Both Sides | 40 | LF | $0.00 | |
| 23 | Masonry Seat Wall - CIP Concrete with Stone Cap (North West of Splash Pad) | 40 | LF | $0.00 | |
| 24 | Concrete Steps (North West of Splash Pad) | 44 | SF | $0.00 | |
| 25 | Sanstone Pavers - Sand Set (North West of Splash Pad) | 120 | SF | $0.00 | |
| 26 | Poured in Place Safety Surface | 177 | SF | $0.00 | |
| 27 | New Control Panel | 1 | LS | $0.00 | |
| 28 | 4-Inch Supply Piping | 650 | LF | $0.00 | |
| 29 | 3-inch Supply Piping | 175 | LF | $0.00 | |
| 30 | 2-inch Supply Piping | 50 | LF | $0.00 | |
| 31 | Conduit | 200 | LF | $0.00 | |
| 32 | 2-inch Lateral Piping | 850 | LF | $0.00 | |
| 33 | 10-inch Return Piping | 250 | LF | $0.00 | |
| 34 | 4-inch Overflow Piping | 25 | LS | $0.00 | |
| 35 | 4-inch Drain Piping | 150 | LF | $0.00 | |
| 36 | 1-inch Piping for Quick Coupling Valve | 50 | LF | $0.00 | |
| 37 | Plaza Drain | 3 | EA | $0.00 | |
| 38 | Wet Well | 1 | EA | $0.00 | |
| 39 | Stone/Rock Outlet | 3 | EA | $0.00 | |
| 40 | Clean Out Assembly | 4 | EA | $0.00 | |
| 41 | Bubbler Nozzle | 6 | EA | $0.00 | |
| 42 | Spray Nozzle | 9 | EA | $0.00 | |
| 43 | Channel Outlet | 3 | EA | $0.00 | |
| 44 | 4-inch Gate Valve Assembly | 4 | EA | $0.00 | |
| 45 | 3-inch Gate Valve Assembly | 3 | EA | $0.00 | |
| 46 | 2-inch Gate Valve Assembly | 3 | EA | $0.00 | |
| 47 | Bollard Assembly | 2 | EA | $0.00 | |
| 48 | Solenoid Valve Manifold | 1 | LS | $0.00 | |
| 49 | Quick Coupling Valve Assembly | 1 | EA | $0.00 | |
| 50 | Move Existing BECSYS Controller | 1 | LS | $0.00 | |
| 51 | New 10 HP Pump | 1 | LS | $0.00 | |
| 52 | New 2 HP Pump | 2 | LS | $0.00 | |
| 53 | New 8-Inch Basket Strainer | 1 | LS | $0.00 | |
| 54 | Accu Tab Systems | 2 | EA | $0.00 | |
| Total Base Bid | $0.00 | ||||
| Add Alternate Lump Sum for Mechanical System Renovations Per Plan Sheet WF3.0 | $0.00 |