Bid_Schedule_-_Replace_Boat_Ramp.xlsx
XLSX spreadsheet 31 KB Posted
- Attached to
- Replace Boat Ramp Federal contract opportunity
- Solicitation number
- 140P6423B0009
About this file
This document contains a federal contract opportunity to replace a boat ramp at Voyageurs National Park. The National Park Service Midwest Region is soliciting bids for a firm-fixed price construction contract between $250,000 to $500,000 to remove an existing concrete boat ramp, construct a new boat ramp area in a dry dock condition, and restore the site. Work is anticipated to begin in July/August 2023. The solicitation number is 140P6423B0009 and the NAICS code is 237990 with a $45 million size standard. This project is set aside 100% for total small businesses. Interested parties must register in the System for Award Management and complete online representations and certifications by the solicitation closing date. The point of contact is listed for any questions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6423B0009_Amd_0001.pdf | ||
| Questions_and_Answers_0001.pdf | ||
| Bid_Schedule_-_Replace_Boat_Ramp.pdf | ||
| Attachment_-_Drawings.pdf | ||
| Sol_140P6423B0009.pdf | ||
| Attachment_-_Submittal_List.xlsx | XLSX spreadsheet | |
| Attachment_-_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| Attachment_-_Notice_to_Contractors.pdf | ||
| Attachment_-_Construction_Contract_Admin.pdf | ||
| Wage_Determination_-_St_Louis_Co.pdf | ||
| Specifications_-_Replace_Boat_Ramp.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Voyageurs National Park | |
| U.S. Department of Interior | |
| National Park Service |
PROJECT: Replace Boat Ramp
BID SCHEDULE
Construction Items Unit Quantity Price/ Unit Subtotal
| Mobilization/Demobilization | ||||
| - Mob/Demob Costs | LS | 1 | $ - 0 | $ - 0 |
| Site Preparation, Cofferdam Installation and associated items | ||||
| - Materials | LS | 1 | $ - 0 | $ - 0 |
| - Labor | LS | 1 | $ - 0 | $ - 0 |
| Existing Ramp Removal and associated items | ||||
| - Materials | LS | 1 | $ - 0 | $ - 0 |
| - Labor | LS | 1 | $ - 0 | $ - 0 |
| Boat Ramp Construction and associated items | ||||
| - Materials | LS | 1 | $ - 0 | $ - 0 |
| - Labor | LS | 1 | $ - 0 | $ - 0 |
| Site Restoration, Cofferdam Removal and associated items | ||||
| - Materials | LS | 1 | $ - 0 | $ - 0 |
| - Labor | LS | 1 | $ - 0 | $ - 0 |
Subtotal $ - 0
| Overhead | % | $ - 0 |
| Profit | % | $ - 0 |
| Bonds | % | $ - 0 |
Grand Total $ - 0