Bid_Schedule_-_Replace_Boat_Ramp.xlsx

XLSX spreadsheet 31 KB Posted

Attached to
Replace Boat Ramp Federal contract opportunity
Solicitation number
140P6423B0009
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This document contains a federal contract opportunity to replace a boat ramp at Voyageurs National Park. The National Park Service Midwest Region is soliciting bids for a firm-fixed price construction contract between $250,000 to $500,000 to remove an existing concrete boat ramp, construct a new boat ramp area in a dry dock condition, and restore the site. Work is anticipated to begin in July/August 2023. The solicitation number is 140P6423B0009 and the NAICS code is 237990 with a $45 million size standard. This project is set aside 100% for total small businesses. Interested parties must register in the System for Award Management and complete online representations and certifications by the solicitation closing date. The point of contact is listed for any questions.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Boat Ramp, newest first.
File Type Posted
Sol_140P6423B0009_Amd_0001.pdf PDF
Questions_and_Answers_0001.pdf PDF
Bid_Schedule_-_Replace_Boat_Ramp.pdf PDF
Attachment_-_Drawings.pdf PDF
Sol_140P6423B0009.pdf PDF
Attachment_-_Submittal_List.xlsx XLSX spreadsheet
Attachment_-_Limitations_on_Subcontracting_Report.xlsx XLSX spreadsheet
Attachment_-_Notice_to_Contractors.pdf PDF
Attachment_-_Construction_Contract_Admin.pdf PDF
Wage_Determination_-_St_Louis_Co.pdf PDF
Specifications_-_Replace_Boat_Ramp.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Voyageurs National Park
U.S. Department of Interior
National Park Service

PROJECT: Replace Boat Ramp

BID SCHEDULE

Construction Items Unit Quantity Price/ Unit Subtotal

Mobilization/Demobilization
- Mob/Demob CostsLS1$ - 0$ - 0
Site Preparation, Cofferdam Installation and associated items
- MaterialsLS1$ - 0$ - 0
- LaborLS1$ - 0$ - 0
Existing Ramp Removal and associated items
- MaterialsLS1$ - 0$ - 0
- LaborLS1$ - 0$ - 0
Boat Ramp Construction and associated items
- MaterialsLS1$ - 0$ - 0
- LaborLS1$ - 0$ - 0
Site Restoration, Cofferdam Removal and associated items
- MaterialsLS1$ - 0$ - 0
- LaborLS1$ - 0$ - 0

Subtotal $ - 0

Overhead%$ - 0
Profit%$ - 0
Bonds%$ - 0

Grand Total $ - 0

Printed: &D &T &Z&F image1.png