Questions_and_Answers_0001.pdf

PDF 57 KB Posted

Attached to
Replace Boat Ramp Federal contract opportunity
Solicitation number
140P6423B0009
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This document contains questions and answers regarding a solicitation to replace a boat ramp at Voyageurs National Park in Minnesota. The work includes removing the existing concrete boat ramp, constructing a new ramp area in a dry dock condition to allow for construction, and site restoration. The solicitation number is 140P6423B0009 and is valued between $250,000 and $500,000. It will be a firm-fixed price construction contract adhering to St. Louis County, MN wage rates. The NAICS code is 237990 for heavy construction with a size standard of $45 million. The project is set aside 100% for total small businesses. The deadline for questions was May 31, 2023 at 12PM ET and no extension was provided. No geotechnical investigations have been performed and material details of the existing ramp are unknown. Earthen fill will not be allowed for coffer dams due to sediment discharge restrictions. The awarded contractor may receive typical crib dock details from the park but plans for the existing dock are unavailable.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Boat Ramp, newest first.
File Type Posted
Sol_140P6423B0009_Amd_0001.pdf PDF
Bid_Schedule_-_Replace_Boat_Ramp.pdf PDF
Attachment_-_Drawings.pdf PDF
Sol_140P6423B0009.pdf PDF
Attachment_-_Submittal_List.xlsx XLSX spreadsheet
Attachment_-_Limitations_on_Subcontracting_Report.xlsx XLSX spreadsheet
Wage_Determination_-_St_Louis_Co.pdf PDF
Specifications_-_Replace_Boat_Ramp.pdf PDF
Bid_Schedule_-_Replace_Boat_Ramp.xlsx XLSX spreadsheet
Attachment_-_Notice_to_Contractors.pdf PDF
Attachment_-_Construction_Contract_Admin.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: 140P6423B0009

Amendment #: 0001

Replace Boat Ramp – VOYA

Questions and Answers listed below:

QUESTIONS:

Question # Question Answer/Response 1.

Due to the long holiday weekend, is it possible to have the questions due date extended to Friday June 2?

The deadline for Q&A will not be extended to Friday, June 2.

Deadline for Q&A will remain 31 May 2023 @ 12PM ET.

2.

Has there been any geotechnical performed for this project?

Geotechnical investigations have not been performed.

3.

Is the current rip rap material type known?

Current rip rap is not confirmed. If specification was followed when constructed in 1985, rip rap would be 6”-2’-0” size material (per sheet C00 in construction drawings) and comply with MN DOT Spec 3601.

4.

Can earthen fill be used as a coffer dam?

Earthen fill will not be allowed as coffer dam material. The project is subject to the MN DNR / USACE permitting with strict requirements for sediment and erosion projection. Reference sheet C01 in construction drawings, Cofferdam scope note 2 regarding approval of method as it relates to turbidity or sediment discharge into the lake. Placement of earthen fill would be defined as impactful sediment discharge into the lake.

5.

Are there any details on the existing crib dock if it will need to be removed/replaced?

The Park has typical crib dock details similar or adaptable to this crib dock which may be shared with the awarded Contractor; however, construction documents of this specific crib dock is not available.