Bid Notice-Florence Lane Pump Station and Piping Upgrades.pdf

PDF 299 KB Posted

Attached to
Florence Lane Pump Station and Piping Upgrades
Solicitation number
C12831
Issued by
Washington County, Oregon

About this file

This is a bid notice issued by Tualatin Valley Water District in Oregon for the Florence Lane Pump Station and Piping Upgrades project (Project No. C12831). The project scope includes replacing three existing pumps and motors with new units, replacing approximately 34 feet of steel discharge piping with new steel piping and associated components, replacing an exhaust fan and louver, replacing tapping saddle assemblies for pressure transducers and water quality sensing lines, and excavating and installing a 24-inch valve into a 36-inch concrete cylinder water line. The District will supply pumps, motors, discharge piping, and various components; the contractor must purchase additional equipment as needed and coordinate with a system integrator for SCADA implementation, an electrician for wiring, and District staff for shutdowns and testing. Sealed bids must be submitted electronically through Bid Locker by 2:00 p.m. Pacific Daylight Time on August 12, 2026. A mandatory pre-bid conference is scheduled for Tuesday, July 28, 2026 at 2:00 p.m. at 6675 SW Florence Lane, Portland, Oregon 97223; bidders who do not attend will be deemed non-responsive. The District intends to issue a Notice to Proceed no later than August 31, 2026. Bids will be publicly opened and read aloud immediately after the closing time on a conference call, with interested parties able to request a Teams meeting invitation.

The Engineer's estimate for the project is $550,000 to $650,000. Bidders must submit a certified check or bid bond equal to five percent of the bid amount, with original copies of Bid Security required within five business days of the Bid Closing Time. First Tier Subcontractor Disclosure Forms must be submitted to Bid Locker within two hours of the Bid Closing Time as required by ORS 279C.370. Bidders must complete a Statement of Bidder's Qualifications and provide statements regarding resident bidder status and Oregon Construction Contractors Board registration. Contractor licensing for asbestos abatement is a requirement. All work must comply with prevailing wage provisions under ORS 279C.800 through 279C.870. The bid documents consist of three PDF files totaling approximately 70 megabytes and are available electronically through Bid Locker or in electronic or hard copy format from Plan Center Northwest. Bidders must register with Bid Locker and complete a Confidentiality Agreement; vendor profiles require manual approval and vendors should ensure approval at least three business days prior to bid submission.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florence Lane Pump Station & Piping Upgrades

Solicitation Type: ITB

Issued by: Tualatin Valley Water District [open agency website in new window ]

Publish Date: Jul 22, 2026 12:00AM

Bids Due Date: Aug 12, 2026 2:00PM (Pacific Daylight Time) add to calendar

Status: Open save to watchlist save to watchlist express interest express interest submit bid submit bid

Description Sealed bids for the construction of the Florence Lane Pump Station & Piping Upgrades, Project No.

C12831 (Project) for Tualatin Valley Water District (Owner) will be accepted electronically at https://bidlocker.us/details/6196_Florence_Lane_Pump_Station_Piping_Upgrades (Bid Locker), until 2:00 p.m. local time on August 12, 2026 (Bid Closing Time). Bidders must sign up with Bid Locker at https://bidlocker.us/a/tvwd/BidLocker before being allowed to submit a bid. There is no cost to register. Any bids received after the Bid Closing Time will not be considered.

The single point of contact for this bid is Janet Fleshman, Procurement Specialist, and can be reached at bidsandproposals@tvwd.org.

Registration with Bid Locker requires a correctly completed Confidentiality Agreement, which is available through the registration process. Following completion of the requested vendor information and upload of the Confidentiality Agreement, the vendor profile will be sent for manual approval.

Please allow one business day for the vendor profile to be approved. If it has not been approved within one business day, or if there are questions about this process, please contact bidsandproposals@tvwd.org. Bidders are advised to ensure that their Bid Locker vendor profile is active and approved a minimum of three business days prior to the Bid Closing Time to prevent any issues with submitting a bid on time.

secure bid submission https://bidlocker.us/a/tvwd https://www.tvwd.org/ https://www.tvwd.org/ https://bidlocker.us/Details/CloseDateInvite/6196 https://bidlocker.us/details/6196_Florence_Lane_Pump_Station_Piping_Upgrades https://bidlocker.us/a/tvwd/BidLocker mailto:bidsandproposals@tvwd.org mailto:bidsandproposals@tvwd.org https://bidlocker.us/Home/BidLockerUS https://bidlocker.us/Home/BidLockerUS https://bidlocker.us/Home/BidLockerUS https://bidlocker.us/Home/BidLockerUS

Bids received by the Bid Closing Time will be publicly opened and read aloud immediately thereafter on a conference call at 971.300.4841, phone conference ID 270 065 92#. Interested parties who wish to view the electronic bid opening shall request an electronic Teams meeting invitation by emailing bidsandproposals@tvwd.org by 4:00 p.m. on Tuesday, August 11, 2026. Requests received after this time are not guaranteed to receive the Teams invitation and may still call in at the number provided.

Bidders are required to submit a First Tier Subcontractor Disclosure Form (First Tiers), as described by ORS 279C.370. The First Tiers must be submitted to Bid Locker within two hours of the Bid Closing Time. The Owner must reject a bid if the Bidder fails to submit the First Tiers to Bid Locker within two hours of the Bid Closing Time. Original copies of the Bid Security must be submitted to Owner within five business days of the Bid Closing Time as prescribed in Section 00 21 13.

The Project consists of furnishing required labor, equipment, and materials for construction of the following:

1. Replacing three existing pumps and motors with three new pumps and motors, replacing approximately 34 feet of steel discharge piping with new steel piping, valves, check valves, dismantling joints, sensing equipment, air release valves, field welding, pressure testing, disinfection, startup and closeout.

2. Replacing existing exhaust fan with new exhaust fan and louver.

3. Replacing existing tapping saddle and assemblies for pressure transducers and water quality sensing lines.

4. The District will supply pumps, motors, discharge piping, and various components for construction.

Contractor to purchase additional equipment as needed. Coordination with system integrator for SCADA implementation, electrician for wiring, and District staff for shutdowns and system testing will be required.

5. Excavate and cut into a 36-inch concrete cylinder water line and install a 24-inch valve, with fittings, blow offs, an air release valve, thrust restraint, and trench repair as needed.

The Engineer’s estimate for this Project is $550,000-$650,000.

All work is to be completed according to the schedule provided in the Contract documents. District intends to issue Notice to Proceed date no later than August 31, 2026.

This document contains information related to public drinking water systems which is considered critical infrastructure information and is protected under Homeland Security Presidential Directive 7 and Oregon Revised Statutes 192.355. No portion of this document may be uploaded to an artificial intelligence (AI) engine or similar platform under any circumstances.

Bid Documents may be obtained electronically from Bid Locker or in in either electronic or hard copy format by contacting Plan Center Northwest, PO Box 2486, Clackamas, OR 97015, Phone:

503.650.0148, e-mail: megan@plancenternw.com, https://plancenternw.com/. If a potential Bidder obtains the Bid documents from Plan Center Northwest, the Bidder is still responsible for registering with Bid Locker to submit their bid.

Addenda will be published to Bid Locker. Bidders who download bid packages from Bid locker will automatically be notified via email when addenda are published. It is the responsibility of the Bidder to obtain all addenda. Bidders are responsible for the cost of obtaining and/or printing the Bid Documents. The Bidder, including subcontractors, will also be responsible for signing a confidentiality agreement prior to obtaining the documents. Return of the documents is not required, and the amount paid for the Bid Documents is nonrefundable.

mailto:bidsandproposals@tvwd.org mailto:megan@plancenternw.com https://plancenternw.com/

Bidders are required to attend the mandatory pre-bid conference for this Project on Tuesday, July 28, 2026 at 2:00 pm at 6675 SW Florence Ln, Portland, OR 97223. Bidders who do not attend the pre-bid conference will be deemed non-responsive.

Contractors must be qualified in accordance with the applicable parts of ORS 279 to enter into a contract with the Owner for public work in Oregon. Bidders are required to complete and submit Section 00 45 13, “Statement of Bidder’s Qualifications” with their bid. The Owner will investigate and determine if the qualifications of the apparent low Bidder meet the minimum requirements as part of its evaluation of the lowest responsive and responsible bid.

No bid will be received or considered by the Owner unless the Bid Form contains, or is accompanied by, a statement by the Bidder as a part of the bid that the provisions required by ORS 279C.800 through 279C.870 pertaining to prevailing wages are included in this Contract. Contractor licensing under ORS 468A.720 for asbestos abatement IS a requirement of this Project. Each bid must contain a statement as to whether the bidder is a resident bidder as defined in ORS 279A.120. Each bid must contain a statement as to whether the bidder is registered with the Oregon Construction Contractors Board in accordance with the provisions of ORS 279C.365.

Bids must be submitted on the prescribed forms and must be accompanied by a certified check or bid bond executed in favor of Tualatin Valley Water District in an amount equal to five percent of the amount bid as described in Paragraph 11.1 of Section 00 21 13 Instructions to Bidders. The successful Bidder will be required to furnish the necessary additional bond(s) for the faithful performance of the Contract as prescribed in the Contract Documents.

The Owner reserves the right to reject all bids not in compliance with all prescribed public contracting procedures and requirements, including bidder responsibility under ORS 279C.375(3)(b), and may reject for good cause all bids upon the Owner’s finding that it is in the Owner’s or the public’s best interest to do so. The Owner reserves the right to waive informalities and to award a Contract to the qualified lowest responsive and responsible Bidder.

Published July 22, 2026

Special Instructions Bidders are required to attend the mandatory pre-bid conference for this Project on Tuesday, July 28, 2026 at 2:00 pm at 6675 SW Florence Ln, Portland, OR 97223. Bidders who do not attend the pre-bid conference will be deemed non-responsive.

Line Items

This solicitation has the following line items for which you can submit a bid. Please review the bidding instructions in the bid documents for information on these line items:

Item No Item

Unit of Measure Quantity Cost Required?

Schedule A

1 Mobilization (Max 5% of Bid Total) LS 1.00

2 Health and Safety LS 1.00

3 Temporary Traffic Control LS 1.00

4 Erosion Control LS 1.00

5 Owner Contingency

($100,000.00) LS 1.00

6 Connection to Existing Water System LS 1.00

Schedule B – Pump Station Upgrades and Piping

7 Receipt, Storage, and Handling of Owner-Furnished Material LS 1.00

8 Demo Pumps and Motors LS 1.00

9 Demo HVAC Equipment and Hatch Covers LS 1.00

10 Pump and Motor Installation LS 1.00

11 Exhaust Fan and Hatch Cover Installation LS 1.00

12 Pump Station Steel Piping Header Installation LS 1.00

13 Suction Header Instrument Assemblies Installation LS 1.00

14 Asbestos Removal LS 1.00

15 Pipeline Cleaning, Testing, Disinfection LS 1.00

16 Commission and Startup LS 1.00

17 Miscellaneous Clean up and Surface Restoration LS 1.00

Schedule C – 24-Inch Valve Insertion

Unit of Measure Quantity Cost Required?

18 Potholing EA 13.00

19 Construction Survey LS 1.00

20 Removal of Existing Concrete Pressure Pipe LF 30.00

21 Over-Excavation and Backfill CY 20.00

22 Boulder Excavation, Haul, and Disposal CY 10.00

23 Rock Excavation, Haul, and Disposal CY 10.00

24 Sanitary Sewer Lateral Replacement EA 1.00

25 24-inch Butterfly Valve Installation EA 1.00

26 24-inch Ductile Iron Piping, Class 52 LF 8.00

27 24-Inch Small Ductile Iron Fitting EA 4.00

28 24-Inch Large Ductile Iron Fitting EA 2.00

29 36-Inch Small Ductile Iron Fitting EA 2.00

30 36-inch Steel Spool EA 2.00

31 36-inch Steel Butt Straps EA 2.00

32 Concrete Thrust Collar and Anchor Ring EA 2.00

33 Water Service Type K (All Sizes, Fittings) EA 1.00

34 Water Service Reconnection EA 1.00

35 Isolation Flange Kit, CP Test Station and CP Systems EA 2.00

36 2-inch Blow Off Assembly EA 1.00

Unit of Measure Quantity Cost Required?

37 4-Inch CARV and 4-inch Blow Off Assembly EA 1.00

38 Pipeline Cleaning, Testing, Disinfection LS 1.00

39 Cold Planing Pavement Removal, 2-inch Depth SY 211.00

40 Permanent Asphalt Concrete Trench Restoration TN 41.00

41 Miscellaneous Surface Restoration LS 1.00

Download Line Items as .CSV Download Line Items as .CSV

Line 1 may not exceed 5% of the total bid amount. Double-check math prior to submitting.

Attachments

This project has the following solicitation documents.

Bid Document File Size

Florence Lane PS & Piping Upgrades ITB v 1 of 3.pdf 8,786,343

Florence Lane PS & Piping Upgrades ITB v 2 of 3.pdf 17,116,624

Florence Lane PS & Piping Upgrades ITB v 3 of 3.pdf 43,832,576

You will need to:

Be logged into Bid Locker Be registered with Tualatin Valley Water District

Vendor Questions and Answers

Submitted Questions About This Bid

Tualatin Valley Water District has not yet posted any answers to submitted questions. When they do, their answers will appear here.

Download All Documents as a .ZIP File Download All Documents as a .ZIP File https://bidlocker.us/Details/LineItemsCsv/6196

For Questions or Additional Information, Contact:

All inquiries regarding this bid shall be sent to the single point of contact at bidsandproposals@tvwd.org.

Interested Parties and Planholders

Interested Parties

These are the vendors who have expressed interest in this solicitation:

Business When

DJC Oregon Project Center Jul 22, 2026

Plan Center Northwest Jul 22, 2026 (plan center)

Salem Contractors Exchange Jul 22, 2026 (other)

Seattle Daily Journal of Commerce Jul 22, 2026 (plan center)

Tri-City Construction Council Jul 22, 2026 (plan center)

Download Interested Parties as .CSVDownload Interested Parties as .CSV

Planholders

These are the vendors who have downloaded the solicitation documents:

Business When

Cascade Water Works LLC Jul 22, 2026

Moore Excavation Inc. Jul 22, 2026

Rangeline Tapping Services Jul 22, 2026

Rotschy, LLC. Jul 22, 2026 (prime)

Schneider Equipment, Inc. Jul 22, 2026

Shannon & Wilson Jul 22, 2026

The Saunders Company Jul 22, 2026

Download Planholders as .CSVDownload Planholders as .CSV https://bidlocker.us/Details/BiddersListCsv/6196 https://bidlocker.us/Details/PlanholdersListCsv/6196

Commodity Codes

913-60:

Commodity Codes (NIGP):

Construction, Water System, Plants, Main And Service Line

About Tualatin Valley Water District

Contracting with TVWD TVWD is a special district, established to provide drinking water, and is governed by an elected Board of Commissioners. Because some of the information in our solicitations is confidential and protected under US law, all vendors are required to complete a Confidentiality Agreement prior to their TVWD Bid Locker profile being approved. This approval is a manual process. Please allow one business day for approval and follow any emailed instructions received. TVWD is not responsible for vendors who cannot download and/or submit solicitation responses due to vendor profiles that are not approved.

Public agencies with questions about a solicitation should call 503.848.3055 or email bidsandproposals@tvwd.org for information. Vendors who reach out directly will be redirected to the instructions in the specific solicitation or other emailed instructions.

Share:

Questions? Feedback? Email us: help@bidlocker.us | Call us: 267-225-1407 Bid Locker is a secure online bid submission service, offered by Bid Locker LLC.

mailto:help@bidlocker.us

File details come from the government source that posted it. Updated .