BID FORM - RATE SHEET_Rev2.xlsx

XLSX spreadsheet 42 KB Posted

Attached to
On-Call Construction
Solicitation number
UD-27-367
Issued by
Los Angeles County, California

About this file

Summary

This is a Bid Form Rate Sheet for the Long Beach Utilities Department related to an on-call gas construction and emergency services contract. The rate sheet establishes unit pricing for comprehensive pipeline work including steel main replacement, installation, and abandonment across varying project scopes (501 feet to 3,000 feet), pavement types (PCC and asphalt), and installation methods (open trench and horizontal directional drilling). The document provides detailed line items for pipe sizes ranging from 2 inches to 20 inches in diameter, with differentiated pricing based on project scale and specific site conditions. Additionally, the rate sheet covers polyethylene (PE) main replacement and installation work, service replacement and installation, service tie-overs, service abandonment, and miscellaneous items such as valve installations, fittings, mobilization and demobilization, potholing, paving, and emergency services. Each line item specifies required crew composition, equipment, and work inclusions to ensure standardized pricing and scope clarity.

The rate sheet requires bidders to electronically input unit prices in USD for each of the 398 line items across multiple work categories. Pricing must account for labor, materials, equipment, and ancillary work specified in each item's comments section. The contract structure accommodates projects with varying depths, pavement thicknesses, and pipe materials, with add-on charges for extra pavement thickness and excess service line footage calculated as unit price multiplied by relevant area or linear footage measures. Bidders must provide complete pricing for all applicable categories to be considered responsive, with the rates serving as the basis for task order authorization under the on-call contract framework.

View the file

Other files

File Type Posted
ITB UD-27-367.pdf PDF
Attachments.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

All Line Items

RATE SHEET
Line Item No.DescriptionUnitCommentsUnit Price (USD)
input electronicallySection
1A. STEEL MAIN REPLACEMENT (OPEN TRENCH) - Pavement Type: PCC - x ≤ 4" thick1A
Total Project Main Footage: 501' - 1000'1A
1Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles1A
2Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles1A
3Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles1A
4Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles1A
Total Project Main Footage: 1001' - 3,000'1A
5Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles1A
6Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), Side boom + Vehicles1A
7Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), Side boom + Vehicles1A
Add-On Charges1A
8Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement1A
9Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement1A
1B. STEEL MAIN REPLACEMENT (OPEN TRENCH) - Pavement Type: Asphalt - x ≤ 5" thick1B
Total Project Main Footage: 501' - 1000'1B
10Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles1B
11Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles1B
12Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles1B
13Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles1B
Total Project Main Footage: 1001' - 3,000'1B
14Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles1B
15Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), Side boom + Vehicles1B
16Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), Side boom + Vehicles1B
Add-On Charges1B
17Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement1B
18Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement1B
2A. STEEL MAIN REPLACEMENT - ARTERIAL STREET CROSSING (OPEN TRENCH) - Pavement type: PCC - x ≤ 4" thick2A
Total Project Main Footage: 1' - 120'2A
19Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles2A
20Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles2A
21Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles2A
22Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles2A
23Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement2A
2B. STEEL MAIN REPLACEMENT - ARTERIAL STREET CROSSING (OPEN TRENCH) - Pavement type: Asphalt - x ≤ 5"2B
Total Project Main Footage: 1' - 120'2B
24Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles2B
25Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles2B
26Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles2B
27Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles2B
28Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement2B
3A. STEEL MAIN REPLACEMENT (HDD) - Pavement Type: PCC - x ≤ 4" thick3A
Total Project Main Footage: 501' - 1000'3A
29Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles3A
30Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles3A
31Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles3A
32Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles3A
Total Project Main Footage: 1,001' - 3,000'3A
33Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles3A
34Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), Side boom + Vehicles3A
35Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), Side boom + Vehicles3A
Add-On Charges3A
36Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement3A
37Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement3A
3B. STEEL MAIN REPLACEMENT (HDD) - Pavement Type: Asphalt - x ≤ 5" thick3B
Total Project Main Footage: 501' - 1000'3B
38Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles3B
39Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles3B
40Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles3B
41Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles3B
Total Project Main Footage: 1001' - 3,000'3B
42Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles3B
43Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), Side boom + Vehicles3B
44Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), Side boom + Vehicles3B
Add-On Charges3B
45Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement3B
46Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement3B
4A. STEEL MAIN REPLACEMENT - ARTERIAL STREET CROSSING (HDD) - Pavement type: PCC - x ≤ 4" thick4A
Total Project Main Footage: 1' - 120'4A
47Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles4A
48Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles4A
49Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles4A
50Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles4A
51Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement4A
4B. STEEL MAIN REPLACEMENT - ARTERIAL STREET CROSSING (HDD) - Pavement type: Asphalt - x ≤ 5"4B
Total Project Main Footage: 1' - 120'4B
52Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles4B
53Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles4B
54Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles4B
55Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles4B
56Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement4B
5A. STEEL MAIN INSTALLATION (OPEN TRENCH) - Pavement Type: PCC - x ≤ 4" thick5A
Total Project Main Footage: 501' - 1000'5A
57Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles5A
58Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles5A
59Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles5A
60Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles5A
Total Project Main Footage: 1001' - 3,000'5A
61Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles5A
62Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), Side boom + Vehicles5A
63Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), Side boom + Vehicles5A
Add-On Charges5A
64Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement5A
65Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement5A
5B. STEEL MAIN INSTALLATION (OPEN TRENCH) - Pavement Type: Asphalt - x ≤ 5" thick5B
Total Project Main Footage: 501' - 1000'5B
66Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles5B
67Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles5B
68Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles5B
69Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles5B
Total Project Main Footage: 1001' - 3,000'5B
70Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles5B
71Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), Side boom + Vehicles5B
72Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), Side boom + Vehicles5B
Add-On Charges5B
73Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement5B
74Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement5B
6A. STEEL MAIN INSTALLATION - ARTERIAL STREET CROSSING (OPEN TRENCH) - Pavement type: PCC - x ≤ 4"6A
Total Project Main Footage: 1' - 120'6A
75Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles6A
76Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles6A
77Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles6A
78Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles6A
79Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement6A
6B. STEEL MAIN INSTALLATION - ARTERIAL STREET CROSSING (OPEN TRENCH) - Pavement type: Asphalt - x ≤ 5"6B
Total Project Main Footage: 1' - 120'6B
80Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles6B
81Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles6B
82Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles6B
83Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles6B
84Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement6B
7A. STEEL MAIN INSTALLATION (HDD) - Pavement Type: PCC - x ≤ 4" thick7A
Total Project Main Footage: 501' - 1000'7A
85Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles7A
86Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles7A
87Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles7A
88Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles7A
Total Project Main Footage: 1001' - 3,000'7A
89Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles7A
90Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), Side boom + Vehicles7A
91Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), Side boom + Vehicles7A
Add-On Charges7A
92Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement7A
93Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement7A
7B. STEEL MAIN INSTALLATION (HDD) - Pavement Type: Asphalt - x ≤ 5" thick7B
Total Project Main Footage: 501' - 1000'7B
94Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles7B
95Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles7B
96Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles7B
97Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles7B
Total Project Main Footage: 1001' - 3,000'7B
98Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles7B
99Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), Side boom + Vehicles7B
100Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), Side boom + Vehicles7B
Add-On Charges7B
101Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement7B
102Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement7B
8A. STEEL MAIN INSTALLATION - ARTERIAL STREET CROSSING (HDD) - Pavement type: PCC - x ≤ 4" thick8A
Total Project Main Footage: 1' - 120'8A
103Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles8A
104Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles8A
105Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles8A
106Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles8A
107Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement8A
8B. STEEL MAIN INSTALLATION - ARTERIAL STREET CROSSING (HDD) - Pavement type: Asphalt - x ≤ 58B
Total Project Main Footage: 1' - 120'8B
108Main Installation - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles8B
109Main Installation - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles8B
110Main Installation - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles8B
111Main Installation - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles8B
112Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement8B
9A. EXISTING STEEL MAIN ABANDONMENT - Pavement Type: PCC - x ≤ 4" thick9A
Total Project Main Footage: 501' - 1000'9A
113Main Abandonment - 2" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9A
114Main Abandonment - 3" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9A
115Main Abandonment - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9A
116Main Abandonment - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9A
117Main Abandonment - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
118Main Abandonment - 10" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
119Main Abandonment - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
120Main Abandonment - 14" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
121Main Abandonment - 16" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
122Main Abandonment - 18" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
123Main Abandonment - 20" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
Total Project Main Footage: 1001' - 3,000'9A
124Main Abandonment - 2" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9A
125Main Abandonment - 3" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9A
126Main Abandonment - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9A
127Main Abandonment - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9A
128Main Abandonment - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
129Main Abandonment - 10" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
130Main Abandonment - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
131Main Abandonment - 14" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
132Main Abandonment - 16" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
133Main Abandonment - 18" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
134Main Abandonment - 20" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9A
Add-On Charges9A
135Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement9A
136Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement9A
9B. EXISTING STEEL MAIN ABANDONMENT - Pavement Type: Asphalt - x ≤ 5" thick9B
Total Project Main Footage: 501' - 1000'9B
137Main Abandonment - 2" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9B
138Main Abandonment - 3" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9B
139Main Abandonment - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9B
140Main Abandonment - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9B
141Main Abandonment - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
142Main Abandonment - 10" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
143Main Abandonment - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
144Main Abandonment - 14" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
145Main Abandonment - 16" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
146Main Abandonment - 18" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
147Main Abandonment - 20" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
Total Project Main Footage: 1001' - 3,000'9B
148Main Abandonment - 2" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9B
149Main Abandonment - 3" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9B
150Main Abandonment - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9B
151Main Abandonment - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles9B
152Main Abandonment - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
153Main Abandonment - 10" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
154Main Abandonment - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
155Main Abandonment - 14" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
156Main Abandonment - 16" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
157Main Abandonment - 18" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
158Main Abandonment - 20" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles9B
Add-On Charges9B
159Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement9B
160Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement9B
10A. EXISTING STEEL MAIN REMOVAL - Pavement Type: PCC - x ≤ 4" thick10A
Total Project Main Footage: 501' - 1000'10A
161Main Removal - 2" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10A
162Main Removal - 3" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10A
163Main Removal - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10A
164Main Removal - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10A
165Main Removal - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
166Main Removal - 10" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
167Main Removal - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
168Main Removal - 14" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
169Main Removal - 16" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
170Main Removal - 18" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
171Main Removal - 20" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
Total Project Main Footage: 1001' - 3,000'10A
172Main Removal - 2" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10A
173Main Removal - 3" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10A
174Main Removal - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10A
175Main Removal - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10A
176Main Removal - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
177Main Removal - 10" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
178Main Removal - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
179Main Removal - 14" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
180Main Removal - 16" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
181Main Removal - 18" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
182Main Removal - 20" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10A
Add-On Charges10A
183Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement10A
184Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement10A
10B. EXISTING STEEL MAIN REMOVAL - Pavement Type: Asphalt - x ≤ 5" thick10B
Total Project Main Footage: 501' - 1000'10B
185Main Removal - 2" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10B
186Main Removal - 3" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10B
187Main Removal - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10B
188Main Removal - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10B
189Main Removal - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
190Main Removal - 10" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
191Main Removal - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
192Main Removal - 14" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
193Main Removal - 16" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
194Main Removal - 18" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
195Main Removal - 20" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
Total Project Main Footage: 1001' - 3,000'10B
196Main Removal - 2" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10B
197Main Removal - 3" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10B
198Main Removal - 4" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10B
199Main Removal - 6" Pipelinear foot (lf)1 Foreman, 1 Welder, 3 Laborers, 1 Backhoe (with operator), + Vehicles10B
200Main Removal - 8" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
201Main Removal - 10" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
202Main Removal - 12" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
203Main Removal - 14" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
204Main Removal - 16" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
205Main Removal - 18" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
206Main Removal - 20" Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles10B
Add-On Charges10B
207Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement10B
208Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement10B
11. STEEL MISCELLANEOUS ITEMS AND RATES11
2091" SAV - Install, Tap, Stop & Completeeach (ea)11
2102" SAV - Install, Tap, Stop & Completeeach (ea)11
2112" Half Encirclement Pressure Control Fitting - Install, Tap, Stop & Completeeach (ea)11
2123" Half Encirclement Pressure Control Fitting - Install, Tap, Stop & Completeeach (ea)11
2134" Half Encirclement Pressure Control Fitting - Install, Tap, Stop & Completeeach (ea)11
2142" Full Encirclement Pressure Control Fitting - Install onlyeach (ea)11
2153" Full Encirclement Pressure Control Fitting - Install onlyeach (ea)11
2164" Full Encirclement Pressure Control Fitting - Install onlyeach (ea)11
2176" Full Encirclement Pressure Control Fitting - Install onlyeach (ea)11
2188" Full Encirclement Pressure Control Fitting - Install onlyeach (ea)11
21910" Full Encirclement Pressure Control Fitting - Install onlyeach (ea)11
22012" Full Encirclement Pressure Control Fitting - Install onlyeach (ea)11
22114" Full Encirclement Pressure Control Fitting - Install onlyeach (ea)11
22216" Full Encirclement Pressure Control Fitting - Install onlyeach (ea)11
22312" Full Encirclement Pressure Control Fitting - Tap, Stop, & Completeeach (ea)11
2242" Tie-in Fitting(e.g. 45, 90 ell, reducer, TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2253" Tie-in Fitting(e.g. 45, 90 ell, reducer, TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2264" Tie-in Fitting(e.g. 45, 90 ell, reducer, TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2276" Tie-in Fitting(e.g. 45, 90 ell, reducer, TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2288" Tie-in Fitting(e.g. 45, 90 ell, reducer,TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
22910" Tie-in Fitting(e.g. 45, 90 ell, reducer,TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
23012" Tie-in Fitting(e.g. 45, 90 ell, reducer,TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
23114" Tie-in Fitting(e.g. 45, 90 ell, reducer,TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
23216" Tie-in Fitting(e.g. 45, 90 ell, reducer,TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
23318" Tie-in Fitting(e.g. 45, 90 ell, reducer,TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
23420" Tie-in Fitting(e.g. 45, 90 ell, reducer,TF, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2352" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2363" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2374" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2386" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2398" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
24010" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
24112" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
24214" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
24316" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
24418" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
24520" Tie-in Fitting(e.g. weld tee, pup, etc.) - includes 2 weldseach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2462" Steel Ball Valve Installationeach (ea)11
2473" Steel Ball Valve Installationeach (ea)11
2484" Steel Ball Valve Installationeach (ea)11
2496" Steel Ball Valve Installationeach (ea)11
2508" Steel Ball Valve Installationeach (ea)11
25110" Steel Ball Valve Installationeach (ea)11
25212" Steel Ball Valve Installationeach (ea)11
25314" Steel Ball Valve Installationeach (ea)11
25416" Steel Ball Valve Installationeach (ea)11
25518" Steel Ball Valve Installationeach (ea)11
25620" Steel Ball Valve Installationeach (ea)11
2574" Mueller Flanged Tee (FT) Installationeach (ea)11
2586" Mueller Flanged Tee (FT) Installationeach (ea)11
2598" Mueller Flanged Tee (FT) Installationeach (ea)11
2602" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2613" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2624" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2636" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
2648" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
26510" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
26612" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
26714" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
26816" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
26918" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
27020" Non-Controllable Fitting installation (e.g. 45, 90 ell, reducer, TF, Insulation, Tee, End Cap, pup, etc.) - includes 1 weldeach (ea)If applicable, nominal diameter corresponds to larger side of fitting11
271Installation of 2” STL pipe ≤ 29'Per lf11
272Installation of 3” STL pipe ≤ 29'Per lf11
273Installation of 4” STL pipe ≤ 29'Per lf11
274Installation of 6” STL pipe ≤ 29'Per lf11
275Installation of 8” STL pipe ≤ 29'Per lf11
276Installation of 10” STL pipe ≤ 29'Per lf11
277Installation of 12” STL pipe ≤ 29'Per lf11
278Installation of 14” STL pipe ≤ 29'Per lf11
279Installation of 16” STL pipe ≤ 29'Per lf11
280Installation of 18” STL pipe ≤ 29'Per lf11
281Installation of 20” STL pipe ≤ 29'Per lf11
282STEEL Additional Mobilizationeach (ea)11
283STEEL Additional Demobilizationeach (ea)11
12A. PE MAIN REPLACEMENT (HDD) - Pavement Type: PCC - x ≤ 4" thick12A
Total Project Main Footage: 501' - 1,000'12A
284Main Replacement - 2" PE Coil Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of pipe size 3" or less12A
285Main Replacement - 4" PE Stick Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of like size or less12A
286Main Replacement - 6" PE Stick Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of like size or less12A
287Main Replacement - 8" PE Stick Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of like size or less12A
Total Project Main Footage: 1,001' - 3,000'12A
288Main Replacement - 2" PE Coil Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of pipe size 3" or less12A
289Main Replacement - 4" PE Stick Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of like size or less12A
290Main Replacement - 6" PE Stick Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of like size or less12A
Add-On Charges12A
291Extra PCC Pavement thickness (per 1" increment) for x > 4"
(501' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement12A
292Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement12A
12B. PE MAIN REPLACEMENT (HDD) - Pavement Type: Asphalt - x ≤ 5" thick12B
Total Project Main Footage: 501' - 1,000'12B
293Main Replacement - 2" PE Coil Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of pipe size 3" or less12B
294Main Replacement - 4" PE Stick Pipe (40' Sticks)linear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of like size or less12B
295Main Replacement - 6" PE Stick Pipe (40' Sticks)linear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of like size or less12B
296Main Replacement - 8" PE Stick Pipe (40' Sticks)linear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of like size or less12B
Total Project Main Footage: 1,001' - 3,000'12B
297Main Replacement - 2" PE Coil Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of pipe size 3" or less12B
298Main Replacement - 4" PE Stick Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of like size or less12B
299Main Replacement - 6" PE Stick Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles
Includes abandonment of like size or less12B
Add-On Charges12B
300Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(501' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement12B
301Extra Asphalt Pavement thickness (per 1" increment) for x > 5"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 5" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement12B
13A. PE MAIN INSTALLATION (HDD) - Pavement Type: PCC - x ≤ 4" thick13A
Total Project Main Footage: 501' - 1,000'13A
302Main Installation - 2" PE Coil Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles13A
303Main Installation - 4" PE Stick Pipe (40' Sticks)linear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles13A
304Main Installation - 6" PE Stick Pipe (40' Sticks)linear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles13A
305Main Installation - 8" PE Stick Pipe (40' Sticks)linear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles13A
Total Project Main Footage: 1,001' - 3,000'13A
478Main Installation - 2" PE Coil Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles13A
307Main Installation - 4" PE Stick Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles13A
308Main Installation - 6" PE Stick Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles13A
Add-On Charges13A
309Extra PCC Pavement thickness (per 1" increment) for x > 4"
(501' - 1,000')square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement13A
310Extra PCC Pavement thickness (per 1" increment) for x > 4"
(1,000' +)square foot (sf)Total add-on cost = unit price * excavated area * # of additional 1" increments above 4" thick
Unit Price includes: sawcut, excavate, additional materials & time, haul off, replacement13A
13B. PE MAIN INSTALLATION (HDD) - Pavement Type: Asphalt - x ≤ 5" thick13B
Total Project Main Footage: 501' - 1,000'13B
311Main Installation - 2" PE Coil Pipelinear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles13B
312Main Installation - 4" PE Stick Pipe (40' Sticks)linear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles13B
313Main Installation - 6" PE Stick Pipe (40' Sticks)linear foot (lf)1 Foreman, 1 Welder, 4 Laborers, 1 Backhoe (with operator), + Vehicles13B

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .