_Bid_Form_Hangar_Development_ITB_47-2025_rev_06-17-2025.pdf
PDF 112 KB Posted
- Attached to
- Hangar Site Development State and local contract opportunity
- Solicitation number
- ITB-47-2025
- Issued by
- Rutherford County, Tennessee
About this file
This document is a Bid Form for the City of Murfreesboro's Hangar Site Development project (ITB-47-2025), detailing a comprehensive infrastructure and utility development contract. The bid covers 25 line items including site preparation, excavation, pipe installation, drainage systems, fencing, and landscaping, with specific quantities such as 1,743 linear feet of silt fence, 3,800 cubic yards of unclassified excavation, 13,900 cubic yards of borrow excavation, 1,740 linear feet of water pipe, and 290 linear feet of sanitary sewer pipe. The project includes storm drain infrastructure, utility demolition, hydro-seeding, sodding, and installation of storm drain inlets, manholes, and headwalls.
The bid form includes a 5% Owner's Contingency allowance, with unit prices to be determined in accordance with the General Conditions and final payment based on actual quantities. Bidders are advised that estimated quantities are not guaranteed and are solely for bid comparison purposes. The document specifies that any use of the Owner's Contingency must be approved in writing by the Owner's Representative prior to work being performed, and the successful bidder is not required to bond for the Owner's Contingency. The bid allows for detailed pricing of individual line items, enabling precise cost estimation for the complex infrastructure development project.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| CAD_file_Hangar_Development_MBT_Site_Grading.dwg | DWG drawing | |
| _BID_SPECS_Hangar_Development_ITB_47-2025_06-12-2025rev06-17-2025.pdf | ||
| _PLANS_Hangar_Development_ITB_47-2025.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
00 41 00 - 4 Bid Form
05/2025 37419-08
ARTICLE 5 – BASIS OF BID
5.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s):
BASE BID
Item No.
Spec. Item
Description
Estimated Qty.
Unit
Unit Price
Total Price
1 C-102-5.1 SILT FENCE (INSTALLATION & REMOVAL) 1,743 LF $ $
C-102-5.2 INLET PROTECTION (INSTALLATION &
REMOVAL)
EA
3 C-102-5.3 TEMPORARY SEDIMENT BASIN 1 LS $ $
C-102-5.4 CULVERT PROTECTION (INSTALLATION &
REMOVAL)
EA
5 C-105-6.1 MOBILIZATION 1 LS $ $
6 P-152-4.1 UNCLASSIFIED EXCAVATION 3,800 CY $ $
P-152-4.2 BORROW EXCAVATION (FROM OFF-SITE
MATERIAL)
13,900
CY
D-701-5.1 15” REINFORCED CONCRETE PIPE,
CLASS III
LF
D-701-5.2 30”x19” ELLIPTICAL REINFORCED
CONCRETE PIPE, CLASS III
D-701-5.3 38”x24” ELLIPTICAL REINFORCED
D-701-5.4 45”x29” ELLIPTICAL REINFORCED
D-701-5.5 53”x34” ELLIPTICAL REINFORCED
13 D-751-5.1 STORM DRAIN INLET 9 EA $ $
14 D-751-5.2 STORM MANHOLE 2 EA $ $
15 D-752-5.1 30”x19” HEADWALL 1 EA $ $
16 D-752-5.2 53”x34” HEADWALL 1 EA $ $
17 F-162-5.1 CHAIN-LINK FENCE 1,800 LF $ $
18 F-162-5.2 ACCESS GATE (16’ WIDE DOUBLE SWING) 2 EA $ $
19 T-901-5.1 HYDRO-SEEDING 10.38 AC $ $
20 T-904-5.1 SODDING 1,502 SY $ $
21 T-905-5.1 TOPSOIL (OBTAINED ON SITE) 5,500 CY $ $
00 41 00 - 5 Bid Form
05/2025 37419-08
Item No. Spec. Item Description Estimated
Qty. Unit Unit Price Total Price
22 02600 SANITARY MANHOLE 2 EA $ $
23 02713 WATER PIPE 1,740 LF $ $
24 02722 SANITARY SEWER PIPE (8”) 290 LF $ $
25 PLANS EXISTING UTILITIES DEMOLITION 1 LS $ $
TOTAL BASE BID
BASE BID ITEMS 1 THROUGH 25, INCLUSIVE, THE AMOUNT OF:
DOLLARS ($______________).
OWNER’S CONTINGENCY (5% OF BASE BID):
DOLLARS ($______________)
TOTAL BID AMOUNT (BASE BID PLUS OWNER’S CONTINGENCY):
TOTAL DOLLARS ($_______________)
Bidder acknowledges Unit Prices have been determined in accordance with Paragraph 11.03.C of the General Conditions.
Bidder acknowledges that estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities, determined as provided in the Contract Documents.
Owner’s Contingency Allowance: Contractor agrees that an Owner’s ontingency allowance, if any, is for the sole use of Owner to cover unanticipated costs. ANY use of the Owner’s Contingency must be approved in writing and signed by the Owner’s Representative prior to work being done.
File details come from the government source that posted it. Updated .