PIEDRAS WELL INVESTIGATION
Solicitation number
140L1224Q0017
Issued by

About this file

This document is a Performance Work Statement (PWS) for a federal contract opportunity related to investigating two existing groundwater wells at the Piedras Blancas Lighthouse property in California.

The key objectives are to determine the construction, water quality, and safe yield of the two wells to establish their viability as new water sources for the Piedras Blancas Lighthouse. The contractor will be required to video inspect the wells, conduct step-drawdown and constant-rate pump tests, and test the water quality. The contract has a period of performance of 6 months from the notice to proceed. The required tasks, deliverables, specifications, and government-furnished information are detailed in the PWS. The solicitation number is 140L1224Q0017, and the agency is the Department of the Interior Bureau of Land Management California Region.

View the file

Other files

File Type Posted
B03_Service_Contract_Act_WD_2015-5643.pdf PDF
B08_Attachment_2_Price_Schedule_03_15_24.xlsx XLSX spreadsheet
Sol_140L1224Q0017.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PWS Page 1

Performance Work Statement (PWS)

Piedras Blancas Lighthouse Well Investigation

Contents PWS 1.0 Background on the Government’s Requirement

PWS 2.0 General Scope of Work

PWS 3.0 Overall Objectives

PWS 4.0 Specific Tasks

General Specifications

Task 1: Camera each well

Task 2: Well Capacity Tests

Task 3: Test the water quality of each well

Task 4: Well Cap

PWS 6.0 Government-Furnished Property, Materials, Services

PWS 7.0 Security and Administrative Matters

PWS 8.0 Technical Exhibits and Definitions

Exhibit 1: Site Location Map and Limited Well Information

Exhibit 2: Bid Schedule

Exhibit 3: Submittal Register

PWS Page 2

PWS 1.0 Background on the Government’s Requirement

The objective of this work is to determine the well borehole construction, water quality, and safe yield of two existing ground water wells to establish their viability as potable water sources for the Piedras Blancas Lighthouse property.

This work ties into other future approved projects which have an overall goal to establish safe drinking water for both the BLM staff and volunteers at the Piedras Blancas Lighthouse field offices and residences. To accomplish this, the overall project is broken up into phases so that the BLM can change/adapt to the best course of action as new information is discovered. Exploring the viability of the two existing wells for providing drinking water at Piedras Blancas will allow the BLM to formulate the best source & water treatment system required to best utilize future project funds for the site.

PWS 2.0 General Scope of Work

Services of this contract include the Contractor accomplishing the following Tasks:

1. Camera each well to:

a. establish well construction,

b. verify well casing/screen condition,

c. provide subsequent maintenance recommendations, if any.

2. Test the water quality of water at each well:

a. Complete Title 22 primary & secondary suite testing and

b. Total Coliforms ((TC) Present/absent & E. coli)

3. Complete well capacity determination via:

a. a step drawdown pump test and

b. constant rate pump test.

See Exhibit 3 for a detailed submittal register of deliverables the Contractor shall provide.

Place of Performance:

The project site is located within San Luis Obispo County, California. The Piedras Blancas Lighthouse is located 15950 Cabrillo Hwy, San Simeon, CA 93452 which is approximately

6.5 miles north of San Simeon, California. See attached map in Exhibit 1.

• Piedras Blancas Lighthouse (35.666981°, -121.283105°) o Directions from San Simeon, continue on CA-Hwy 1 for 6.5 miles. Turn left onto Cabrillo Highway and continue straight to the site.

The exact locations of Well 1 and Well 2 will be provided upon award of the contract.

Period of Performance:

The period of performance shall be for 6 months from the Notice to Proceed.

PWS Page 3

PWS 3.0 Overall Objectives The objective of this work is to determine the construction, water quality, and establish the safe yield of two existing ground water wells to establish the wells’ viability as new water sources for the Piedras Blancas Lighthouse property.

PWS 4.0 Specific Tasks BLM was unable to locate the well logs and previous pump tests associated with the drilling of Well 1 and Well 2 at the Piedras Blancas Lighthouse. The only information that was found was two bid sheets (contained in Exhibit 5) that detail the borehole size and approximate depth. Historic staff knowledge implies the wells were drilled approximately in 2017 by the USGS.

General Specifications

The Contractor shall follow all industry standard protocols related to working with a drinking water well that include, but are not limited to the following:

1. Protection of groundwater quality

a. The Contractor shall:

i. take all necessary precautions to prevent contamination of the water in the well by preventing the introduction of any foreign substance, including contaminated water, gasoline, oil, and the like and

ii. conform to all laws applicable to the protection of water quality including California State Water Resources Control Board laws and regulations.

2. Production water

a. The Contractor is responsible for following Best Management Practices

(BMP’s) regarding water discharges during testing of the wells. It is the responsibility of the Contractor to use BMPs to limit pollutant discharge to de minimis quantities, thereby protecting waters of the State, in accordance California State Water Resources Control Board regulations.

b. Prior to the start of the work, the Contractor shall submit to the COR their plan to manage the water discharge during the testing of the wells.

i. Produced water may be contained in above-ground tanks and disposed of in a manner to prevent surface or subsurface contamination and to prevent degradation of natural or man-made water courses, impoundments, waterways, lakes, reservoirs, irrigation ditches, storm sewers, and dry stream beds.

c. Discharge of produced water will be allowed during development and testing provided there are no adverse impacts such as the following:

i. Water produced during development and testing shall be discharged into a holding tank or series of tanks or basins for settling.

ii. Discharge from the tanks or basins shall pass through straw bales and/or geofabric for erosion control and further filtration.

iii. The Contractor shall provide all of the tanks, hay bales, geofabric, riprap, flexible hose, PVC or other tubing, and other materials and

PWS Page 4 equipment to divert and dissipate the energy of and minimize erosion from the discharged water, filter and allow for settling of the solids in the discharged water.

d. Control of produced water shall conform with all applicable California State Water Resources Control Board regulations.

3. Final Cleanup

a. The Contractor shall thoroughly clean the site after completion of the test pumping operations. All debris and other materials used or generated during these operations shall be properly disposed of by the Contractor.

b. Following all operations, the Contractor shall promptly remove their equipment, temporary facilities, and materials, smooth the work site surface and leave the site in a condition acceptable to the Site Contact and COR. No reseeding is to be done during the final cleanup.

4. ANSI NSF 60 and 61

a. In accordance with California Safe Drinking Water laws, all interior surfaces that may contact well water must consist of products complying with ANSI/NSF Standard 61. This requirement applies to drop pipes, interior casing and slotted casing, well screens, coatings, adhesives, solders, fluxes, pumps, switches, electrical wire, sensors, and all other equipment or surfaces which may contact the drinking water.

b. All substances introduced into the well during testing and development shall be certified to comply with ANSI/NSF Standard 60 in accordance with California State Water Resources Control Board ANSI/NSF Standards 60 and 61 Certification. This requirement applies to drilling fluids (biocides, clay thinners, defoamers, foamers, loss circulation materials, lubricants, oxygen scavengers, viscosifiers, weighting agents) and regenerants. This requirement also applies to well grouting and sealing materials which may come in direct contact with the drinking water.

c. Contractor shall submit to the COR Safety Data Sheets (SDSs), formerly Material Safety Data Sheets (MSDSs) for all proposed chemicals (including lost circulation materials) to be added to the borehole for approval prior to their use.

Task 1: Camera each well The contractor shall video inspect Well 1 and Well 2 to document and establish:

a) well construction,

b) integrity of the well casings and screens

c) subsequent maintenance recommendations, if any.

The Contractor shall use a downhole video camera that shall record color video and show the depth of the camera at all times during logging. The video shall be of sufficient quality that is acceptable to the COR. The Contractor shall provide one copy of the completed video log to the COR on a DVD, USB flash drive, or electronically.

PWS Page 5

Task 2: Well Capacity Tests The contractor shall complete a step drawdown well test and constant rate pump test to be able to determine safe well yield and aquifer characteristics for use in pump rate optimization for Well 1 and Well 2.

1. General

a. During the step-rate and constant rate pumping periods, the Contractor shall have a person assigned full-time to keeping the rate constant during first 30 minutes of pumping, then at least every 30 minutes thereafter. The Contractor shall record the pumping rate at least every 30 minutes, even if the rate is constant; record fluctuations in pumping rate; record when adjustments are made to valves that control the pumping rate.

b. The Contractor shall be responsible for providing power for the test pump.

The Contractor shall provide a means for safe refueling during pumping operations to prevent even brief shutdowns. Power shutdowns before the end of the testing procedure will require the Contractor to allow the water level to recover to pre-pumping conditions and initiate the test again.

c. Contractor shall have at least one person at all times during the pumping test to operate the pump, power supply, monitor and control the pumping rate, and to make and record frequent water level and flow rate measurements.

d. The Contractor shall monitor and record specific conductance, temperature, turbidity and sand content during the step-rate and constant-rate pumping tests. Measurements shall be performed at about one-hour intervals while pumping.

e. After the well has been continuously pumped during the constant rate-pumping test, Contractor shall collect a water sample for submittal to an approved analytical laboratory within analytical hold-times (generally the same day as the sample is collected and several hours before the laboratory closes for the day).

f. After the constant rate test is completed, Contractor shall not disinfect the well or remove the pump for a minimum period of 24 hours while water level recovery measurements are being made.

g. The Contractor shall furnish and install all necessary equipment for development and testing, including the following:

i. Valve system to control flow.

ii. Smooth nosed sampling tap to collect water samples from discharge piping.

iii. Rossum sand tester.

iv. Totalizing meter with instantaneous flow rate indicator and/or an orifice weir for accurately measuring the discharge from the well.

v. 0.75-inch inside diameter tube (installed to within 10 feet of the pump) for measuring water levels during the pumping test.

vi. Pressure transducer (with a data logger) that is rated at a minimum of 220 psi and capable of measuring water levels from a depth of

PWS Page 6

500 feet. The pressure transducer shall be strapped to the entire length of the drop pipe or installed in a dedicated drop tube. The transducer shall be set to record water levels every minute during the step-rate and constant-rate pumping and recovery periods.

vii. Piping to discharge point and necessary materials to manage produced water in accordance with California State Water Resources Control Board

2. Step Rate Pumping Test

a. The Contractor shall conduct a step-test lasting up to 8 hours, which will consist of pumping the well at:

i. uniform increases in pumping rates over uniform time intervals with single drawdown measurements taken at the end of the intervals.

ii. be conducted to determine the maximum pumping rate for the desired intake setting.

iii. allow the well to recover overnight or until there are no changes in depth to water for at least six hours.

b. During the step-rate-test, the well shall be pumped at rates that range from about 1 to 15 gpm; each step shall be of a uniform duration ranging up to about 90 minutes each, and rates shall be held constant during each step.

c. The Contractor shall measure water levels (in feet to nearest tenth and from the same datum throughout aquifer testing):

i. The water level prior to starting the step-rate test;

ii. During the step-rate test, water level during each step at 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 15, 20, 25, 30, 35, 40, 45, 50, 55, and 60 minutes after start of each pumping step;

3. Constant Rate Pumping Test

a. During the constant-rate test, the pumping rate shall be held constant at a rate after completion of the step-rate test.

b. The Contractor shall measure water levels (in feet to nearest tenth and from the same datum throughout aquifer testing):

i. The water level prior to starting the constant-rate test;

ii. During the constant-rate test, the water level during pumping at 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 15, 20, 25, 30, 35, 40, 45, 50, 55, and 60 minutes after start of pumping, and every 30 minutes during the first 4 hours of pumping; and every hour for the next four hours, and every 4 hours thereafter until the water drawdown level is constant for at least four measurements

iii. Well data shall include the drawdown and pump discharge rate data versus the time

c. The Contractor shall also record the following information during the pumping tests:

i. The depth of the test pump intake;

ii. The time and date of starting and ending of pumping tests and recovery periods; and

iii. The actual pumping rate.

PWS Page 7

d. Do not over pump the well. Drawing the water level below the pump intake will cause a test failure, i.e. the pump starts to suck air. Stopping the test for any reason is a test failure. When failure occurs, restart the test at a reduced flow rate after recovery of the static water level. After completion of water level measurements for the three pumping rates, start the recovery test.

4. Recovery Test Procedure:

a. The Contractor shall measure water levels (in feet to nearest tenth and from the same datum throughout aquifer testing):

i. Water level during recovery at 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 15, 20, 25, 30, 35, 40, 45, 50, 55, and 60 minutes after ceasing to pump, and every 30 minutes thereafter. Continue recovery water level measurements for minimum of 12 hours following cessation of pumping, or until there are no changes in depth to water for at least six hours.

b. The Contractor shall not remove the pump until the recovery test is completed. Shutoff the pump and start the stopwatch at the same time. The Contractor shall measure recovery levels at reasonable the time increments until water level is within 95% of initial static water level. If water level measurements at the indicated times becomes difficult, record the actual times. Recording water levels every minute for the first 10 minutes is acceptable.

c. If problems occur during the pumping or recovery tests, contact the COR.

Name and phone number: Cheryl Parker (831) 277-6331.

Task 3: Test the water quality of each well The contractor shall test the water quality of Well 1 and Well 2 be completing the following tests as identified in item 8 above:

a) Complete Title 22 Primary and Secondary contaminates.

b) Complete a Total Coliforms (TC) Present/absent & E. coli).

All tests will be completed by a California Environmental Laboratory Accreditation Program (ELAP) accredited laboratory.

Task 4: Well Cap Upon completion of well construction and testing, the top of the Well1 and Well 2 well casings shall be equipped with a water-tight, tamper-resistant, locking steel casing cap.

The well caps shall have an access port to permit installation of a well sounder probe.

The access port shall be a minimum of 1-inch diameter and have a watertight plug. The temporary well cap will be removed and replaced for installation of the permanent pump at a later time under separate specifications.

PWS 5.0 Delivery / Performance Schedule

PWS Page 8

Standards

• Moving of Equipment and Supplies: The moving of equipment and supplies to the job site and between job sites shall be the responsibility of the Contractor.

• Replacement of Equipment: Contractor shall provide quality equipment capable of safely performing the work under the terms of the contract. If equipment is rejected because it does not meet minimum requirements, including but not limited to safety and operability, or if it becomes inoperative, the Contractor shall correct the deficiencies or furnish replacement equipment meeting contract requirements within 2 calendar days. All repairs are the total responsibility of the Contractor.

• Equipment Standards: Contractor shall make equipment available for inspection and approval before use. The Contractor must satisfy all applicable OSHA and DOT requirements or certifications for the operation of offered equipment. There will be no obligation to make payment for any equipment delivered that does not meet the Technical Specifications.

• Existing Facilities: All existing facilities such as piping, signs, cattle guards, drainage structures and road surfacing damaged by the Contractor's operations shall be replaced or repaired by the Contractor at no cost to the Government.

• Watershed Protection and Erosion Control: During all operations under this contract, the Contractor shall exercise reasonable measures to direct surface runoff water to stabilized waterways and to keep the drainage systems functioning effectively to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and equipment maintenance areas shall be stored and collected in a sanitary manner and disposed of in a State-approved sanitary landfill, per local, State, and Federal regulations.

Oil from crankcases or gear boxes, equipment waste or spilled or excess fuel shall be placed in containers and removed from the work site and disposed of as approved and required by local, State, and Federal regulations.

Contractor shall undertake every reasonable measure to minimize erosion and soil damage in connection with any operations under this contract.

Contractor shall immediately discontinue any operations under this contract that due to weather or soil moisture conditions, such operations will cause excessive damage to the soil as determined by the Contracting Officer.

Equipment shall not be fueled nor fluids changed within 100 feet of waters of the state. Any equipment operated adjacent to state waters shall be maintained in a good state of repair and have no damaged hoses, fittings, PWS Page 9 lines, tanks, etc. that may release pollutants into the water. Waste oil and fluids shall not be stored on site. If any such material is released into the waters, the responsible person must make an effort to contain the spill and notify the Contracting Officer within 24 hours. If unable to contain spill, immediately notify the Contracting Officer and call the National Response Center (NRC) at 1-800-424-8802.

• Emergency Spill Kit: Keep sufficient quantities of absorbent materials on the project site to absorb accidental fuel, hydraulic oil, or other petroleum produce spills. Use absorbent materials that are biodegradable, non-water absorbing and designed specifically for the types of spills associated with the Contractor’s operations.

Project site construction not completed during dry weather periods shall be winterized (along with Contractor’s approved onsite staging areas and storage sites) to minimize erosion and other damage to roadways, trails, watercourses, and sensitive habitat, as directed by the Contracting Officer.

• Disposal of Debris: The Contractor shall transport and dispose of all debris and excess material off-site at an approved facility, per local, State, and Federal regulations.

Any debris left onsite after the completion of the Contract shall become the property of the Contractor, and the Contractor shall be responsible for it.

Dispose of materials in a legal manner and payment of fees required is the Contractor's responsibility. Sale of material onsite is not allowed unless authorized in writing by the Contracting Officer. Burning of removed materials is not permitted on the work site.

• Project Boundary: Prior to implementation of Contract deliverables, a pre-work meeting will be held at the project sites with the Contractor, Contracting Officer Representative (COR), and/or Project Inspector (PI).

The intent is to ensure the Contractor understands where the project sites are located, project site specifics and specifications of the contract, and review the Contractor’s plan of operations. It is encouraged that all potential Contractors complete a thorough site visit before bidding on the contract.

• Access: Access to the project area is identified on the map. If roads or any type of access become subject to damage, because of adverse weather conditions or other natural causes, the Contracting Officer or COR will relay that information to the Contractor by phone, email, or in person and the contract could be delayed.

• Notification of Cessation or Restart of work: The Contractor shall notify the Contracting Officer prior to ceasing operations for three or more days, and before re-starting operations after a shutdown of three or more days.

PWS Page 10

This can be done by phone, E- mail, or in person.

• Protection of Cultural Resources: If objects of cultural value on the project area are discovered, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and notify the Authorized Office of the findings.

• Weed Prevention: To reduce the potential for introduction of noxious weeds to the contract area, the Contractor shall, prior to moving in motorized equipment to be used for mastication, clean all such equipment to remove all dirt, plant parts and materials that may carry noxious weed seeds. All equipment shall be inspected by the Contracting Officer prior to moving said equipment to the contract area.

• Fire Prevention: Contractor shall take necessary measures for prevention and suppression of fire on the contract area and other adjacent Government lands used or traversed by the Contractor in connection with operations as are required by applicable laws and regulations. Contractor shall comply with all applicable local, State, and Federal fire prevention regulations and standards. At all times during closed fire season, each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

• Fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with a 4 BC or higher rating

• Shovel, round point #0 lady or equal

• Axe, 2 pounds or over, 26-inch minimum length, or one pulaski

Delivery The Contractor shall complete all work within 180 calendar days after notice to proceed.

Final Inspection and Acceptance The Contracting Officer’s Representative or designated government representative will review all work. The Government’s final project inspections shall take place 1-3 business days following the Contractor’s written notification to the CO and COR of the completion of work. At the conclusion of the work, the Contracting Officer, or their representative, will inspect all sites for conformance with the specifications and requirements. Any deficiencies noted during the inspection will be corrected by the Contractor prior to release of final payment, at no additional cost to the Government. Prior to final payment the Contractor shall properly disposed of all waste materials including excess soil, completed site resurfacing and grooming of staging and storage areas, and submitted project photographs and project reports.

Work Schedule

PWS Page 11

The schedule shall be submitted at the pre-work conference. When requested by the CO or COR, submit an updated work schedule within 3 calendar days. As a minimum, the estimated start and completion dates shall be shown in the estimate.

PWS 6.0 Government-Furnished Property, Materials, Services

General:

The Contractor shall furnish all personnel, materials, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the work tasks defined in this Performance Work Statement, except for those items specified as government-furnished.

Applicable Publications (Current Editions):

• State and Local Codes. This project will not require local building permits, or approvals, for construction. However, State, and local building codes including the California Residential Code and Kern County Building Code shall be followed to the maximum extent practicable.

• Safety and Health. The Contractor must adhere to the applicable requirements in the Occupational Health and Safety Administration (OSHA) regulations for construction (29 CFR 1926) and general industry (29 CFR 1910). Additionally, the Contractor shall abide by applicable State and local safety/health/sanitation/construction codes and standards. In case of conflict, the more stringent shall apply.

• Code of Federal Regulations (CFR).

• American Society for Testing and Materials (ASTM).

• American Concrete Institute (ACI).

• American Institute of Steel Construction (AISC).

• 41 U.S.C. Ch. 83, Section 8303- Buy American Act.

• Administrative Rules of Montana, Title 36, Chapter 21. ASTM D5786, Standard Practice for (Field Procedure) for Constant Drawdown Tests in Flowing Wells for Determining Hydraulic Properties of Aquifer Systems.

• Dross, P. 2011. Technical Review Practical Guidelines for Test Pumping in Water Wells.

International Committee of the Red Cross (ICRC).

• Hantush, M. S., “Nonsteady Flow to Flowing Wells in Leaky Aquifer,” Journal of Geophysical Research, Vol 64, No. 8, 1959, pp. 1043-1052.

• http://nevada.usgs.gov/tech/excelforhydrology/Listing_and_Description.htm for Excel Workbooks used in analyzing time-drawdown data.

• Jacob, C. E., and Lohman, S. W., “Nonsteady Flow to a Well of Constant Drawdown in an Extensive Aquifer,”

• Lohman, S. W., “Ground-Water Hydraulics,” Professional Paper 708, U.S. Geological Survey, 1972.

PWS 7.0 Security and Administrative Matters

Security:

The Contractor shall be responsible for safeguarding all Government property provided for Contractor use or under their control, including securing all facilities the Contractor may access after normal business hours.

PWS Page 12

Contractor shall coordinate work schedule with Contracting Officers Representative to minimize public and employee ingress/egress to the building.

Safety:

The Contractor shall not require, or allow any employee, engaged in the performance of this Contract to work under conditions which are unsanitary, hazardous, or dangerous to his/her health or safety, as determined under safety and health standards promulgated by the Secretary of Labor under Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C. 327 et seq.) as amended and other Federal, State and applicable local government safety standards.

Department of Labor Code of Federal Regulations Title 29 and other Federal, State and local government safety standards will apply in its entirety to the Contractor.

Examples of applicable safety standards are OSHA 29 CFR 1910, OSHA 29 CFR 1926, California Title 19, "Public Safety", California Title 8, "General Industry Safety Orders", and 41 CFR, Subpart B, "Public Contracts, General Safety and Health Standards."

The contractor shall also use the “BLM SAFETY AND HEALTH STANDARDS” (The Yellow Book) for reference.

Should the contractor fail to comply with any of these standards and regulations, the contractor shall be found to have defaulted on the terms of the contract.

Contingency Plan:

Sudden or unusual events could result in a negative impact to the delivery / performance of these requirements.

As an aid to properly plan for such events, the Contractor shall prepare and submit for approval a Contingency Plan for each Place of Performance for these requirements.

The Contractor will outline in detail the method(s) that the Contractor shall use in meeting Contract requirements in the following circumstances:

• a natural disaster occurs which impacts upon the Contractor's ability to perform.

• a labor strike occurs which impacts upon the Contractor's ability to perform.

• a hazardous materials spill which impacts the Contractor’s ability to perform, or which may affect public safety.

• an incident which causes major damage which impacts the Contractor's ability to perform.

• other unforeseen circumstances.

In all cases, the Contractor will assume that government cannot provide supplemental forces and continues to need the same or additional performance under the Contract, which the Contractor must meet.

This Contingency Plan shall be submitted as a part of the Contractor proposal.

Emergency Response:

PWS Page 13

Response to emergency service calls outside of the normal business hours shall not exceed four (4) hours regardless of the time during the day or night, weekends or holidays.

Response to emergency service during normal business hours shall not exceed two (2) hours.

Response is defined as having all personnel and equipment required to correct an emergency at the site of the emergency or at a pre-approved staging area, ready, willing, and able to perform the emergency work. The Contractor will provide a draft emergency response plan prior to Contract start date.

Emergency Services:

On occasion, services may be required to support an activation or exercise of contingency plans outside the normal business hours described above. The Contractor's responsibilities for emergency support will be in accordance with the contingency plan.

Hazardous Materials and Hazardous Response:

The Contractor will conform to all Bureau, Federal, State, and local regulations in the use and disposal of hazardous materials and hazardous waste. The Contractor will provide the appropriate response to any emergency involving hazardous materials at any of the facilities covered by this Contract. The Contractor will provide proof/certification of its personnel qualified to work with hazardous materials and wastes to the Bureau. The Contractor will notify the Bureau immediately upon discovering a release of hazardous waste into the environment.

Public contact:

Contractor personnel may encounter adjacent landowners or members of the public during the performance of their work.

Contractor personnel will present a professional appearance and be able to provide appropriate identification, including display of proper identification by each employee.

All Contractor and subcontractor personnel shall comply with all Federal and State laws relative to citizenship.

Contractor personnel shall inform any trespassers along the right of way of hazards and, as necessary and appropriate, ask trespassers to leave fenced off or restricted areas.

If Contractor personnel may encounter emergency personnel, policemen, or firemen along the right of way, the Contractor personnel shall notify the On-Site Foreman If Contractor personnel encounter the news media, they should refer all questions to the On-Site Foreman, who shall keep the COR informed of all news media contacts.

Government Observations:

Government personnel other than COR may from time to time observe, photograph, or otherwise record Contract operations.

However, these personnel will not interfere with Contractor performance.

Regular Work Hours:

PWS Page 14

The performance period established for this contract is based upon all work being conducted during regular working hours between 7:00am and 4:00pm, Monday through Friday, excluding government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the Contracting Officer in sufficient time to allow satisfactory arrangements to be made for access to the work site.

Communications:

“Time” for communications received after 3:00pm, after 12:00 pm locally on Fridays, or after 12:00 pm locally prior to a holiday will not start until the next business day. All times are local Pacific Standard Time.

Federal Holidays:

The following Federal Legal Holidays are observed:

New Year’s Day Martin Luther King, Jr. Day President’s Day Memorial Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day

Fire Danger Season:

If the Contracting Officer Representative (COR) allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.

Preservation of Historical and Archeological Data:

The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.

If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.

Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.

The Contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives.

The Contractor shall immediately notify the Contracting Officer or his representative if

PWS Page 15 any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.

PWS 8.0 Technical Exhibits and Definitions

Standard Definitions:

Physical Condition The Physical appearance of Federal equipment or facilities that considers cracks, chips, dents, abrasions, rust, corrosion, general cleanliness, vibration, operating temperature, and discoloration and other items as identified by the COR. Physical condition may be determined by visual as well as diagnostic means.

Contracting Officer (CO) The Secretary of the Interior or designated authorized representative who is the only agent capable of signing a federal award or obligating funds.

Contracting Officer’s Representative (COR) The Contracting Officer’s designated representative as indicated in a delegation of authority letter.

Quality Assurance (QA) Surveillance of Contractor performance to determine performance requirements are met.

Performance Requirements Summary (PRS) (see Technical Exhibit below) The PRS identifies the key performance indicators of the Contract that will be evaluated by the Government to assure Contract performance standards are met by the Contractor.

Quality Control Those actions taken by the Contractor to control the production of goods or services so that they meet the requirements of the performance work statement.

Technical Exhibits:

Exhibit 1: Site Location Map Exhibit 2: Bid Schedule Exhibit 3: Submittal Register

PWS Page 16

Exhibit 1: Site Location Map and Limited Well Information

Site Location Map Legend

Piedras Blancas Lighthouse

1 mi

N ➤➤N Data CSUMB SFML, CA OPC

Data CSUMB SFML, CA OPC

Data CSUMB SFML, CA OPC

Data SIO, NOAA, U.S. Navy, NGA, GEBCO

Data SIO, NOAA, U.S. Navy, NGA, GEBCO

Data SIO, NOAA, U.S. Navy, NGA, GEBCO

Bid Sheet Bluff Bedrock Well

Piedras Blancas Light Station

Item Price Item {includes installation) Units QuantitY Unit Price

Lineal foot 310 Lo lEtooo 1 trifi Borehole: 1O-inch to 50', 8-inch 50-310'

Lump Sum 25oo 75oo 2 frnm Cahle tool to Air Rotarv (mobldemob)

Lineal foot .R I 2P,o 3 a,innh P\/c tr480 SDR 21. blank casinq

Lineal fool 65 ,0 Lso 4 D\/r' tr4Ro SnR rl screen. O-o4o-inch slots

Cubic yard 4.5 3oo { 350( ittar nack fA x 16 sand)

Lump Sum 1 Lump Sum I 5oo 6 annrrlar eaniterv seal {S0-feeu

Hour 2 ?oo 4oo 7 nqiler/Ai r-lift develoomenl

Lump Sum 1 Lump Sum 6oo 8 tnatall/remove test oumO

Hour 2 /oo 2oo o Pump develoPment

Hour 4 loo 4oo 10 Qt6n iact

Hour loo 4Da rlia-herfla faql

7b88o,'

TOTAL

Bid Sheet - Terrace Well

Piedras Blancas Light Station

Item Price Item {includes installation} Units Quantity Unit Price

Linealfoot 110 6o Laoo 1 DrillBorehole

Linealfoot 35 g 28o 2 innh P\,/c FaRn sDR 21. blank casino

Lineal foot 65 /o 65o 5 /f' trdnn snR ?'l screen. O.O4O-inch slots

Cubic Yard 2 3oo 6oo 4 ilter pack (8 x '16 sand)

LumP Sum 1 Lump Sum looo 5 ,tar <aniterv ceal {2o-feet)

Lump Sum 1 Lump Sum (e 6 tall/rcmnve test numD

Pumn develoDment Hour 2 /oo 2-oo 7 4ooHour 4 /CIoI \/orirhle rate dise}aroe test (o1trc

TOTAL

PWS Page 17

Exhibit 2: Bid Schedule

BID SCHEDULE

Piedras Blancas Wells Investigation

Base Bid

Piedras Blancas Well Investigation

QUANTITIES COST

# Units Unit of Measure Unit Total

ITEM DESCRIPTION

1 Mobilization/Demobilization 1 LS $ - $ - 2 Camera Well 1 & Well 2 1 LS $ - $ - 3 Pump Well 1 & Well 2 1 LS $ - $ - 4 Title 22 Primary and Secondary Well 1& Well 2 1 LS $ - $ - 5 Bacteria Test Well 1& Well 2 1 LS $ - $ -

Grand Total $ -

PWS Page 18

Exhibit 3: Submittal Register

Submittal Register Piedras Blancas Wells Investigation

Contractor Provided Submittals

Piedras Blancas Wells Investigation Dates

Received Approved Schedule Line Item

DESCRIPTION

2 Video and summary report of Well 1 Construction 3 Video and summary report of Well 2 Construction 4 Pump test results for Well 1 5 Pump test results for Well 2 6 Water contaminant results for Well 1 7 Water contaminant results for Well 2 8 Bacteria results for Well 1 9 Bacteria results for Well 2

PWS 1.0 Background on the Government’s Requirement
PWS 2.0 General Scope of Work
PWS 3.0 Overall Objectives
PWS 4.0 Specific Tasks
General Specifications
Task 1: Camera each well
Task 2: Well Capacity Tests
Task 3: Test the water quality of each well
Task 4: Well Cap
PWS 6.0 Government-Furnished Property, Materials, Services
PWS 7.0 Security and Administrative Matters
PWS 8.0 Technical Exhibits and Definitions
Exhibit 1: Site Location Map and Limited Well Information
Exhibit 2: Bid Schedule
Exhibit 3: Submittal Register