This project work statement outlines requirements for an electrical renovation project at the DC Booth Historic National Fish Hatchery and Archives Four-Stall Garage. The contractor shall install a new electrical supply and 400 amp panel to connect the garage to an existing transformer via underground conduit. Additional requirements include installing 12 circuits and conduit, wire, and outlets in the building. The project location is the DC Booth Historic National Fish Hatchery in Spearfish, Lawrence County, South Dakota. The contractor must coordinate work with hatchery staff and comply with all applicable safety and environmental regulations.

View the file

Other files

File Type Posted
B08_-_Pre-Solicitation_Synopsis_1.pdf PDF
B08_-_Submittals_1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT WORK STATEMENT

24-005 - DC Booth Historic National Fish Hatchery and Archives

Four-Stall Garage – Electrical Renovation

I. PROJECT SCOPE

A. General

The contractor shall install a new electrical supply, a new panel, and new circuits to the Four-Stall Garage building at the DC Booth Fish Hatchery. The contractor shall provide all material and trenching/boring equipment to connect from existing transformer to the garage.

The Four-Stall Garage built in the 1960s will be converted for Aquaculture use. The electrical renovation will allow hatchery personnel to install new water processing equipment for intensive fish culture. The current electric supply to the building is outdated and insufficient (Re: Attachment A for Site Location Map & Attachment C for Site Photos).

Project Objectives:

• Connect to garage to transformer via underground conduit.

• Install a new 400 amp, 42 pole outdoor rated panel

• Install (12 Circuits (Re: Attachment B)

• Install conduit wire and outlets in the North Bay and the North side of Middle Bay in the building (Re: Drawings).

• Install conduit wire and terminal connection for well variable frequency drive in Middle Bay (Re: Drawings).

II. SPECIFIC REQUIREMENTS

1. Contractor will coordinate with Black Hills Energy to connect to the nearest transformer.

a. Transformer is 134 feet from the four-stall garage (Re: Drawings).

b. Underground conduit will cross existing utilities (Gas, Electric).

i. Contractor shall be responsible to marking all existing utility locations prior to construction.

1. Electrical – Black Hills Power

2. Water – City of Spearfish

3. Natural Gas – Black Hills Power

2. All work shall comply with the 2021 IBC and the 2023 NEC.

3. Circuit layout (See Attachment B).

4. Contractor will replace any asphalt or concrete removed or damaged for underground conduit.

5. Contractor will coordinate work time and dates with site staff to accommodate visitor traffic.

III. PROJECT INFORMATION

1. Project Location: D. C. Booth Historic National Fish Hatchery, Spearfish, Lawrence County, South Dakota (See Attachment A).

2. Station Contact Information: Mike Adams (Facilities Operations Specialist), Phone: (605)641-1985, Email:

Mitchel_Adams@fws.gov and Carlos Martinez (Supervisory Fishery Biologist), Phone: (605) 642-7730 x223, Email: Carlos_Martinez@fws.gov mailto:Mitchel_Adams@fws.gov mailto:Carlos_Martinez@fws.gov

IV. WORK UNDER SEPARATE CONTRACTS

1. In the event there is work being performed under a separate contract the Contractor shall cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts. Coordinate the Work of this Contract with work performed under separate contracts.

V. ACCESS TO SITE

1. All operations of the Contractor (including storage of materials) upon Government premises shall be confined to areas authorized or approved by the Contracting Officer.

2. Limit use of Project site areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

a. Limits: Confine construction operations to the immediate area around the picnic structure.

b. Driveways, Walkways and Entrances: Keep driveways and loading areas, and entrances serving premises clear and available to Government, Government Representatives, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

3. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weather tight condition throughout construction period. Repair damage caused by construction operations.

VI. COORDINATION WITH OCCUPANTS

1. Partial Government Occupancy: Government will occupy the other premises during entire construction period, with the exception of areas under construction. Cooperate with Station Manager during construction operations to minimize conflicts and facilitate usage. Perform the Work so as not to interfere with Government operations.

Maintain existing exits unless otherwise indicated.

a. Provide not less than 48 hours' notice to Government of activities that will affect Government's operations.

VII. WORK RESTRICTIONS

1. Work Restrictions, General: Comply with restrictions on construction operations. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

2. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 4:00 p.m., Monday through Friday, unless otherwise indicated.

a. Work on weekends will be restricted to Contracting Officers approval and at the Station Managers discretion.

b. No work will take place over observed Federal holidays.

3. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

a. Notify Station Manager not less than 48 hours in advance of proposed utility interruptions.

4. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruptions to the Government.

a. Notify Station Manager not less than 48 hours in advance of proposed disruptive operations.

5. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet (8 m) of entrances, operable windows, or outdoor-air intakes.

VIII. PERMITS AND FEES

1. The Contractor shall be responsible for obtaining all necessary local, State, and Federal permits and licenses, and payment of related fees, per the Contract Clauses.

IV. MEANS AND METHOD

1. Means and methods of construction shall be such as the Contractor or subcontractors may choose; subject, however, to the Contracting Officer's right to reject means and methods proposed which:

a. Constitute a hazard to the work, persons, or property.

b. Will not produce finished work in accordance with terms of the contract.

c. Are contrary to specified means or methods included in the contract.

2. The right to reject means and methods of the Contractor or subcontractor shall not be construed or interpreted as acceptance of control of means and methods by the Contracting Officer.

3. The Contracting Officer's approval of means and methods or failure to exercise right to reject means and methods shall not relieve the Contractor of the obligation to complete the work required by the contract.

4. Total responsibility for control of all means and methods lies with the Contractor for all work.

V. SAFETY

1. The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient flasher lights, flagmen, danger signals and signs, and shall take all necessary precautions for the protection of the work and the safety of the public. All ponds and water control structures shall remain accessible by vehicle. Roads closed to traffic shall be protected by effective barricades and shall be placed with acceptable warning signs. All barricades and obstructions shall be illuminated at night and all lights shall be kept burning from sunset until sunrise. Install appropriate traffic signs at crossroads and approaches to site as needed to direct affected public traffic. Specific signs and barricade requirements are detailed in the U.S. Department of Transportation, "Manual on Uniform Traffic Control Devices".

2. The Contractor shall assume full responsibility and liability for compliance with all applicable Federal, State, and local regulations pertaining to the protection of workers, visitors to the site, and persons occupying areas adjacent to the site, including the provisions of 29CFR1910 and 29CFR1926 of the Code of Federal Regulations.

The Contractor shall hold harmless the Government for failure to comply with any applicable safety or health regulation on the part of himself, his employees, or his subcontractors.

3. Provide personal safety equipment and training commensurate with the hazards which may exist at the work site. The personal safety equipment and training shall be determined by a thorough hazard analysis of all work site areas. The safety program available at all work sites shall include a minimum of:

a. One nonfreezing-type fire extinguisher in each workshop and shed used for storage of materials at the work site. Place in location readily accessible to construction personnel.

b. A first aid kit for use of construction personnel commensurate with size of project with items necessary for first aid treatment of all injuries.

c. The Contractor shall conduct regular onsite safety inspections and all construction personnel shall receive a safety orientation.

d. Post telephone numbers of nearest hospital, ambulance service or flight for life, and fire station in conspicuous location. Advise all workers of location of telephone numbers.

VI. ENVIRONMENTAL PROTECTION

1. The Contractor shall abate and control all environmental pollution arising from construction activities by complying with all applicable Federal, State, and local laws and regulations concerning environmental pollution control and abatement, as well as the specified requirements in this contract. Compliance with this requirement by subcontractors will be the responsibility of the Contractor.

2. Fossils and Artifacts

a. Should the Contractor discover any fossils or artifacts during construction operations, such objects shall become the property of the Government. The Contractor shall cease construction operations in the area of the "find," and immediately notify the station manager of such discovery. Construction operations may proceed in other areas not affected by this clause. Care shall be exercised by the Contractor not to damage fossils or artifacts uncovered during excavation operations.

b. Failure to comply with this requirement may be considered a violation of the Archeological Resources Protection Act of 1979 as amended. Destruction of historic and prehistoric sites and/or unauthorized collection of cultural materials can result in criminal and/or civil penalties. Penalties can include fines, prison sentences, and/or confiscation of equipment.

c. If the Contractor uses fill from a nongovernmental source to perform work that is required under this project, and a new borrow site is opened or an existing borrow area is expanded in order to obtain such materials, the Contractor shall assure that any new borrow area disturbance meet the requirements of Section 106 of the National Historic Preservation Act.

3. Abatement of Air Pollution

a. The Contractor shall comply with applicable Federal, State, and local laws and regulations concerning the prevention and control of air pollution.

b. Construction activities shall be performed in such a manner that air pollution will be held to a minimum.

c. Burning of materials, trees and brush, combustible construction materials, and rubbish will not be permitted. Construction debris shall be disposed of at a location designated by the Contracting Officer or hauled off the Station to an approved disposal site.

4. Prevention of Water Pollution

a. The Contractor is responsible for implementing the terms and requirements of the State of South

Dakota storm water discharge permit, as issued to the State under the National Pollution Discharge Elimination System (NPDES) by the Environmental Protection Agency (EPA). The Contractor shall apply for and execute all permits as required by the State of South Dakota regarding storm water discharge from the construction site. The Contractor shall submit to the Contracting Officer a copy of all permit applications and a copy of all approvals from the State. Allow the Government 10 days for review of the application package prior to submission.

b. During construction, the Contractor shall comply with all applicable Federal, State, and local laws and regulations concerning the control and abatement of water pollution.

c. The Contractor's construction activities shall be performed by methods that will prevent entrance or accidental spillage of solid matter, contaminants, debris, and other objectionable pollutants and wastes into streams, flowing or dry water-courses, lakes, ponds, and underground water sources. The Contractor shall dispose of all pollutants such as petroleum products, rubbish, cement, concrete, etc., and objectionable material at a jurisdictionally accepted waste management facility.

d. Sanitary facilities, such as chemical toilets shall be located far enough from wells, live streams, or ponds to prevent pollution of the water.

e. Dewatering work for structure foundations or earthwork operations adjacent to or encroaching on streams or watercourses shall be conducted in a manner that prevents muddy water and eroded materials from entering streams or watercourses. This shall be accomplished by construction of intercepting ditches, bypass channels, barriers, settling ponds, or other approved means. Excavated material shall not be placed in or adjacent to watercourses where it can be washed away by high water or storm runoff.

5. Prevention of site contamination

a. The purpose of this section is to prevent invasive species from being introduced to the project work sites. This includes both plant and animal species. Invasive species can have long last detrimental effects at project sites at US Fish and Wildlife Service lands.

b. Prior to entrance to the work site, all equipment brought on site will be thoroughly washed to remove dirt, seeds, and plant parts. Any equipment that has been any body of water within the past 30 days will be thoroughly cleaned with hot water greater than 140 degree F (typically the temperature found at commercial truck washes) and dried for a minimum of five days before being used at this project site. In addition, before transporting equipment from the project site all visible mud, plants and fish/animals will be removed, all water will be eliminated, and the equipment will be thoroughly cleaned. Anything that came in contact with water will be cleaned and dried following the above procedure.

c. Environmental Litigation: Time lost due to work stoppage because of failure of the Contractor to comply with these requirements may not be the subject of a claim for extension of time, for additional costs, or damages.

VII. GENERAL COORDINATION PROCEDURES

1. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

a. Provide a construction schedule noting demolition activities, construction activities, deliveries, payments, etc., as needed to convey coordination information to the Contacting Officer, Contacting Officer’s Representative (COR), Government Inspector as well as local staff.

b. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

c. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

d. Make adequate provisions to accommodate items scheduled for later installation.

2. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

a. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

3. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities as well as any activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

a. Preparation of Contractor's construction schedule.

b. Preparation of the Schedule Of Values.

c. Installation and removal of temporary facilities and controls.

d. Delivery and processing of submittals.

e. Progress meetings.

f. Pre-installation conferences.

g. Project closeout activities.

h. Startup and adjustment of systems.

VIII. PROJECT MEETINGS

1. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.

a. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify the Facility Director, the Contracting officer and the COR of scheduled meeting dates and times.

b. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

c. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including the Contracting Officer and the COR, Construction Manager, and Architect, within three days of the meeting.

2. Preconstruction Conference: The Contracting Officer will schedule a preconstruction conference before starting construction, at a time convenient to the Contracting Officer, COR, Facility Director, On-Site Government Inspector and Contractor.

a. Attendees: Authorized representatives of the Contracting Officer, Government Project Manager, Owner's Commissioning Authority, Construction Manager, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

b. Agenda: Discuss items of significance that could affect progress, including the following:

i. Tentative construction schedule.

ii. Phasing.

iii. Critical work sequencing and long-lead items.

iv. Designation of key personnel and their duties.

v. Procedures for processing field decisions and Change Orders

vi. Procedures for RFIs.

vii. Procedures for testing and inspecting.

viii. Procedures for processing Applications for Payment.

ix. Distribution of the Contract Documents.

x. Submittal procedures.

xi. Preparation of record documents.

xii. Use of the premises and existing building.

xiii. Work restrictions.

xiv. Working hours.

xv. Owner's occupancy requirements.

xvi. Responsibility for temporary facilities and controls.

xvii. Procedures for moisture and mold control.

xviii. Procedures for disruptions and shutdowns.

xix. Construction waste management and recycling.

xx. Parking availability.

xxi. Office, work, and storage areas.

xxii. Equipment deliveries and priorities.

xxiii. First aid.

xxiv. Security.

xxv. Progress cleaning.

c. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.

3. Progress Meetings: Conduct progress meetings at regular intervals as directed by the Contracting officer and/or the COR.

a. Attendees: In addition to representatives of the Government, Construction Manager, and Architect (as applicable), each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

b. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

i. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

c. Review present and future needs of each entity present, including the following:

i. Interface requirements.

ii. Sequence of operations.

iii. Status of submittals.

iv. Deliveries.

v. Off-site fabrication.

vi. Access.

vii. Site utilization.

viii. Temporary facilities and controls.

ix. Progress cleaning.

x. Quality and work standards.

xi. Status of correction of deficient items.

xii. Field observations.

xiii. Status of RFIs.

xiv. Status of proposal requests.

xv. Pending changes.

xvi. Status of Change Orders.

xvii. Pending claims and disputes.

xviii. Documentation of information for payment requests.

4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

IV. USE CHARGES

1. General: Installation and removal of and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated. Allow other entities to use temporary services and facilities without cost, including, but not limited to testing agencies, and authorities having jurisdiction.

2. Water and Sewer Service from Existing System:

a. Potable and Non-potable water from Governments existing water system is available for use without metering and without payment for uses directly related to the project. Provide connections and extensions of services as required for construction operations. This water source is not at the work site, but available nearby.

b. Sanitary Facilities: Use of Government existing toilet facilities will NOT be permitted. Contractor shall comply with the requirements within this section for temporary sanitary facilities.

3. Electric Power Service from Existing System:

a. Electric power from Stations existing system is available for use without metering and without payment for use directly related to the project. Provide connections and extensions of services as required for construction operations. However, this power source is not at the work site, but available nearby roughly 100 yards away. Contractor will be responsible for provide their own power source at the work site as needed. The power source shall not create undue or excessive noise. Coordinate this issue with the local staff.

X. INFORMATION SUBMITTALS

1. Erosion- and Sedimentation-Control Plan: Show compliance with requirements of EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent.

XI. QUALITY ASSURANCE

1. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.

2. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service.

Install service to comply with NFPA 70.

XII. INSTALLATION

1. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

a. Locate facilities to limit site disturbance.

2. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

XIII. TEMPORARY UTILITY INSTALLATION

1. General: Install temporary service or connect to existing service.

a. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

2. Sanitary Facilities:

a. Toilets: Use of Owner's existing toilet facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use.

3. Electric Power Service:

a. Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations.

VX. SUPPORT FACILITIES INSTALLATION

1. Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved areas adequate for construction operations. Locate temporary roads and paved areas as coordinated with the local staff.

2. Traffic Controls: Comply with requirements of authorities having jurisdiction.

a. Protect existing site improvements to remain including curbs, pavement, and utilities.

b. Maintain access for fire-fighting equipment and access to fire hydrants.

3. Parking: use areas designated by Contracting Officer or Station Manager as parking areas for construction personnel.

4. Project Signs: Provide Project signs as indicated. Unauthorized signs are not permitted.

a. Temporary Signs: Provide other signs as indicated and as required to inform public and individuals seeking entrance to Project.

i. Provide temporary, directional signs for construction personnel and visitors.

b. Maintain and touchup signs so they are legible at all times.

XV. SECURITY AND PROTECTION FACILITIES INSTALLATION

1. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered.

Repair damage to existing facilities.

2. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

3. Temporary Egress: Maintain temporary egress from existing occupied facilities as indicated and as required by authorities having jurisdiction.

4. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.

XVI. OPERATION, TERMINATION, AND REMOVAL

1. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

2. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

XVII. ATTACHMENTS

A. Location Map B. Circuit spreadsheet C. Drawings

XVIII. SECTION 260500 - COMMON WORK RESULTS FOR ELECTRICAL

PART 1 - GENERAL

1.2 SUMMARY

1. This Section includes the following:

a. Maintenance manuals.

b. Rough-ins.

c. Electrical installation.

d. Cutting and patching.

e. Building wire, connectors, and splices for branch circuits and feeders.

f. Supporting devices for electrical components.

g. Touchup painting.

1.3 ACTION SUBMITTALS

1. Maintenance Manuals: Prepare maintenance manuals in accordance with Division 1. In addition to the requirements specified in Division 1, include the following information for equipment items:

a. Description of function, normal operating characteristics and limitations, performance curves, engineering data and tests, and complete nomenclature and commercial numbers of replacement parts.

b. Manufacturer's printed operating procedures to include start-up, break-in, and routine and normal operating instructions; regulation, control, stopping, shutdown, and emergency instructions; and summer and winter operating instructions.

c. Maintenance procedures for routine preventative maintenance and troubleshooting; disassembly, repair, and reassembly; aligning and adjusting instructions.

d. Servicing instructions and lubrication charts and schedules.

1.4 QUALITY ASSURANCE

1. Comply with NFPA 70 for components and installation.

2. All electrical installations shall be performed or supervised by a licensed electrician.

1.5 DELIVERY, STORAGE, AND HANDLING

1. Deliver products to the project properly identified with names, model numbers, types, grades, compliance labels, and other information needed for identification.

PART 2 - PRODUCTS

2.1 BUILDING WIRE

1. Description: Single conductor, copper. Solid conductor for No. 10 AWG and smaller; stranded conductor for larger than No. 10 AWG.

2. Thermoplastic Insulated Wire: Conform to NEMA WC 5.

3. Connectors and Splices: Units of size, amperage rating, material, type, and class suitable for service indicated.

Select to comply with Project's installation requirements.

2.2 SUPPORTING DEVICES

1. Channel and angle support systems, hangers, anchors, sleeves, brackets, fabricated items, and fasteners are designed to provide secure support from the building structure for electrical components.

a. Material: Steel, except as otherwise indicated, protected from corrosion with zinc coating or with treatment of equivalent corrosion resistance using approved alternative finish or inherent material characteristics.

b. Metal Items for Use Outdoors or in Damp Locations: Hot-dip galvanized steel, except as otherwise indicated.

2. Steel channel supports have ½" diameter holes at a maximum of 8" o.c., in at least 1 surface.

a. Fittings and accessories mate and match with channels and are from the same manufacturer.

3. Raceway and Cable Supports: Manufactured clevis hangers, riser clamps, straps, threaded C-clamps with retainers, ceiling trapeze hangers, wall brackets, and spring steel clamps or "click"- type hangers.

4. Sheet-Metal Sleeves: 0.0276" or heavier galvanized sheet steel, round tube, closed with welded longitudinal joint.

5. Pipe Sleeves: ASTM A 53, Type E, Grade A, Schedule 40, galvanized steel, plain ends.

6. Expansion Anchors: Carbon-steel wedge or sleeve type.

7. Toggle Bolts: All-steel springhead type.

8. Powder-Driven Threaded Studs: Heat-treated steel.

2.3 TOUCHUP PAINT

1. For Equipment: Provided by equipment manufacturer and selected to match equipment finish.

2. For Non-equipment Surfaces: Matching type and color of undamaged, existing adjacent finish.

3. For Galvanized Surfaces: Zinc-rich paint recommended by item manufacturer.

PART 3 - EXECUTION

3.1 ROUGH-IN

1. Verify final locations for rough-ins with field measurements and with the requirements of the actual equipment to be connected.

3.2 ELECTRICAL INSTALLATIONS

1. General: Sequence, coordinate, and integrate the various elements of electrical systems, materials, and equipment. Comply with the following requirements:

a. Coordinate electrical systems, equipment, and materials installation with other building components.

b. Verify all dimensions by field measurements.

c. Arrange for chases, slots, and openings in other building components during progress of construction, to allow for electrical installations.

d. Coordinate the installation of required supporting devices and sleeves to be set in poured-in-place concrete and other structural components, as they are constructed.

e. Sequence, coordinate, and integrate installations of electrical materials and equipment for efficient flow of the Work.

f. Where mounting heights are not detailed or dimensioned, install systems, materials, and equipment to provide the maximum headroom possible.

g. Coordinate connection of electrical systems with exterior underground and overhead utilities and services. Comply with requirements of governing regulations, franchised service companies, and controlling agencies. Provide required connection for each service.

h. Install systems, materials, and equipment to conform with approved submittal data, including coordination drawings, to greatest extent possible. Conform to arrangements indicated by the Contract Documents, recognizing that portions of the Work are shown only in diagrammatic form. Where coordination requirements conflict with individual system requirements, refer conflict to the Contracting Officer.

i. Install systems, materials, and equipment level and plumb, parallel and perpendicular to other building systems and components, where installed exposed in finished spaces.

j. Install electrical equipment to facilitate servicing, maintenance, and repair or replacement of equipment components. As much as practicable, connect equipment for ease of disconnecting, with minimum of interference with other installations.

k. Install systems, materials, and equipment giving right-of-way priority to systems required to be installed at a specified slope.

l. Coordinate connecting electrical power connections to components, equipment and devices furnished under Division 23.

3.3 WIRING METHODS

1. Feeders: Type THHN/THWN, copper conductor, in raceway, except as otherwise indicated.

2. Branch Circuits: Type THHN/THWN, Romex.

3.4 ELECTRICAL SUPPORTING METHODS

1. Damp Locations and Outdoors: Hot-dip galvanized materials or nonmetallic, U-channel system components.

2. Dry Locations: Steel materials.

3. Support Clamps for PVC Raceways: Click-type clamp system.

4. Conform to manufacturer's recommendations for selecting supports.

5. Strength of Supports: Adequate to carry all present and future loads, times a safety factor of at least 4; 200 lb minimum design load.

3.5 INSTALLATION

1. Install wires in raceway according to manufacturer's written instructions and NECA's "Standard of Installation."

2. Conductor Splices: Keep to the minimum and comply with the following:

a. Install splices and taps that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors.

b. Use splice and tap connectors that are compatible with conductor material.

3. Wiring at Outlets: Install with at least 8" of slack conductor at each outlet.

4. Connect outlets and components to wiring systems and to ground as indicated and instructed by manufacturer.

Tighten connectors and terminals, including screws and bolts, according to equipment manufacturer's published torque-tightening values for equipment connectors. Where manufacturer's torquing requirements are not indicated, tighten connectors and terminals according to tightening requirements specified in UL 486A.

5. Install devices to securely and permanently fasten and support electrical components.

6. Fastening: Unless otherwise indicated, securely fasten electrical items and their supporting hardware to the building structure. Perform fastening according to the following:

a. Fasten by means of wood screws or screw-type nails on wood; concrete inserts or expansion bolts on concrete; and by machine screws, welded threaded studs, or spring-tension clamps on steel.

b. Threaded studs driven by a powder charge and provided with lock washers and nuts may be used instead of expansion bolts, machine screws, or wood screws.

c. Drill holes in concrete so holes more than 3/4" deep do not cut main reinforcing bars.

d. Fill and seal holes drilled in concrete and not used.

e. Select fasteners so the load applied to any fastener does not exceed 25 percent of the proof-test load.

7. Install utility-metering equipment according to utility company's written requirements. Provide grounding and empty conduits as required by company.

3.6 TOUCHUP PAINTING

1. Thoroughly clean damaged areas and provide primer, intermediate, and finish coats to suit the degree of damage at each location.

2. Follow paint manufacturer's written instructions for surface preparation and for timing and application of successive coats.

XIV. SECTION 262416 - PANELBOARDS

PART 1 GENERAL

1.01 DESCRIPTION OF WORK

A. Work included: Lighting and power panelboards rated 600 V or less, mounting devices and related items.

1.02 QUALITY ASSURANCE

A. Comply with NFPA 70 – National Electrical Code, for components and installation.

B. Provide products specified in this Section that are “Listed and Labeled”, as defined in the National Electrical Code, Article 100. The Listing and Labeling agency shall be a “Nationally Recognized Testing Laboratory” (NRTL), as defined in OSHA Regulation 1910.7.

C. Comply with NEMA Standard PB-1, “Panelboards”.

Comply with UL Standard UL 61, “Panelboards”.

1.03 SUBMITTALS

A. Submit in accordance with provisions of Section 013300.

1. Product data on panelboards.

2. Product data on overcurrent protective devices.

PART 2 PRODUCTS

2.01 PANELBOARDS

A. Furnish and install, where indicated, a dead front panelboard incorporating switching and protective devices of the number, rating and type noted herein or shown on the drawings. Panelboards shall have general purpose enclosures and shall be surface mounted, except where noted. All panelboards shall be rated for the intended voltage and shall be in accordance with Underwriters' Laboratories, Inc., "Standard for Panelboards" and "Standard for Cabinets and Boxes" and shall be so labeled where procedures exist. Where panelboards are to be used as service entrance equipment, they shall be so labeled. Panelboards shall also comply with NEMA Standard for Panelboards, National Electrical Code for Federal Specification 115a (Power Distribution Panels) where applicable.

B. All interiors shall be completely factory assembled with switching and protective devices and wire connectors. All wire connectors, except screw terminals, shall be anti-turn solderless type and suitable for copper wire of the size indicated.

C. Interiors shall be so designed that switching and protecting devices can be replaced without disturbing adjacent units and without removing the main bus connectors, and so designed that circuits may be changed without machining, drilling or tapping.

D. Branch circuits shall be arranged using double row construction. Branch circuits shall be numbered by the manufacturer.

E. A nameplate shall be provided listing panel type, number of protective and switching devices and ratings.

F. Bus bars for the mains shall be of copper, sized in accordance with Underwriters' Laboratories standards. Unless otherwise noted, full size neutral bars shall be included. Bus bar taps for panels with single pole branches shall be arranged for sequence phasing of the branch circuit devices. Busing shall be braced throughout to conform to industry standard practice governing short circuit stresses in panelboards. Bracing shall be equivalent to, or compatible with, the rated interrupting capacity of the smallest overcurrent device in that panelboard.

G. Phase busing shall be full height without reduction. Cross connectors shall be copper.

H. Neutral busing shall have a suitable lug for each outgoing feeder requiring a neutral connection.

I. Spaces for future switching and protective devices on lighting and appliance panelboards shall be bused for the maximum device that can be fitted into them.

J. Three-phase busing shall be such that any three adjacent single pole breakers are individually connected to each of the three different phases in such a manner that two or three pole breakers can be installed at any location.

K. Circuit breakers shall be quick-make, quick-break, thermal-magnetic, trip indicating type, with common trip on multi-pole breakers.

L. Connection of the breaker to the bus shall be plug-on or bolt-on.

M. Unless otherwise indicated, circuit breakers shall have a minimum interrupting rating of at least 10,000 amperes, symmetrical, for 120 volt and 240 volt breakers.

N. Boxes shall be made from unpainted, galvanized, code gauge steel having multiple knockouts, except where noted. Boxes shall be of sufficient size to provide a minimum gutter space of 4 inches on all sides.

O. Boxes shall be galvanized steel of a minimum 20 inches wide in accordance with NEMA Standards Publication No. PBI and UL Standard No. 67.

P. At least four interior mounting studs shall be provided.

Q. Identification numbers shall be on the box.

R. Hinged doors covering all switch device handles shall be included in all panel trims, except that panelboards having individual metal clad externally operable dead-front units may be supplied without such doors.

S. Doors in panelboard trims shall conform to the following:

1. In making switching device handles accessible, doors shall not uncover any live parts.

2. Doors shall have semi-flush type cylinder locks and catches, except that doors over 48 inches in height shall have a vault handle and 3-point catch, complete with a lock arranged to fasten the door at the top, bottom and center. Door locks shall be keyed alike. A directory frame and card having a transparent cover shall be furnished on each door.

T. The trims shall be fabricated from code gauge sheet steel.

U. All exterior and interior steel surfaces of the panelboard shall be properly cleaned and finished with gray ANSI-61 paint over a rust inhibiting phosphatized coating.

V. Trims for flush panels shall overlap the box by at least 3/4 of an inch all around. Surface trims shall have the same width and height as the box. Trims shall be mountable by a screwdriver without the need for special tools.

PART 3 EXECUTION

3.01 LOCATION

A. All items shall be installed in the locations specified on the drawings (Field Verify Locations with On-Site Staff).

3.02 DIRECTORIES

A. All branch circuit panelboards and other equipment having card slots shall have the cards accurately filled out with a typewriter to identify the circuit or function. Cards shall be placed in the card slots and protected with a clear, plastic, cover sheet. Cards shall present a neat and clean appearance.

Attachment A. Location Map

Attachment B. Circuit sheet

Circuit # Item volts amps phase hp kw

1 UV sterilizer waste 240 6 1 2 UV sterilizer sump 115/230 2 1 3 UV sterilizer sump 115/230 2 1 4 UV sterilizer sump 115/230 2 1

6" Well pump 200 3 5 3.7 5 Waste sump pump 120 10 1 6 Waste sump pump 120 10 1 7 Waste sump pump 120 10 1 8 Re-use sump pump 208 3.8 3 0.5 9 Re-use sump pump 208 3.8 3 0.5

10 Re-use sump pump 208 3.8 3 0.5 11 Biofilter air pump 115 5 1 11 Biofilter air pump 115 5 1 11 Biofilter air pump 115 5 1 12 lighting 120 10 1 13 room Unit Heater 115 5.6 1 13 room Unit Heater 115 5.6 1 13 room Unit Heater 115 5.6 1 14 dehumidifier 115 10 1 14 dehumidifier 115 10 1 14 dehumidifier 115 10 1 15 Trout re-use pump 120 15 1 16 Trout re-use pump 120 15 1 17 Outlet 120 20 1 17 Outlet 120 20 1 17 Outlet 120 20 1 18 Outlet 120 20 1 18 Outlet 120 20 1 18 Outlet 120 20 1 19 Outlet 120 20 1 19 Outlet 120 20 1 19 Outlet 120 20 1 20 Outlet 120 20 1 20 Outlet 120 20 1 20 Outlet 120 20 1 21 Outlet 120 20 1 21 Outlet 120 20 1 21 Outlet 120 20 1 22 Outlet 120 20 1 22 Outlet 120 20 1 22 Outlet 120 20 1

Circuits to be installed all others are breaker only

Attachment C: Photograph log

1. All operations of the Contractor (including storage of materials) upon Government premises shall be confined to areas authorized or approved by the Contracting Officer.
2. Limit use of Project site areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
a. Limits: Confine construction operations to the immediate area around the picnic structure.
b. Driveways, Walkways and Entrances: Keep driveways and loading areas, and entrances serving premises clear and available to Government, Government Representatives, and emergency vehicles at all times. Do not use these areas for parking or storage o...
3. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weather tight condition throughout construction period. Repair damage caused by construction operations.
VI. COORDINATION WITH OCCUPANTS
1. Partial Government Occupancy: Government will occupy the other premises during entire construction period, with the exception of areas under construction. Cooperate with Station Manager during construction operations to minimize conflicts and faci...
a. Provide not less than 48 hours' notice to Government of activities that will affect Government's operations.
VII. WORK RESTRICTIONS
1. Work Restrictions, General: Comply with restrictions on construction operations. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
2. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 4:00 p.m., Monday through Friday, unless otherwise indicated.
a. Work on weekends will be restricted to Contracting Officers approval and at the Station Managers discretion.
b. No work will take place over observed Federal holidays.
3. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
a. Notify Station Manager not less than 48 hours in advance of proposed utility interruptions.
4. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruptions to the Government.
a. Notify Station Manager not less than 48 hours in advance of proposed disruptive operations.
5. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet (8 m) of entrances, operable windows, or outdoor-air intakes.
VIII. PERMITS AND FEES
PART 1 - GENERAL
1.2 SUMMARY
1. This Section includes the following:
a. Maintenance manuals.
b. Rough-ins.
c. Electrical installation.
d. Cutting and patching.
e. Building wire, connectors, and splices for branch circuits and feeders.
f. Supporting devices for electrical components.
g. Touchup painting.
1.3 ACTION SUBMITTALS
1. Maintenance Manuals: Prepare maintenance manuals in accordance with Division 1. In addition to the requirements specified in Division 1, include the following information for equipment items:
a. Description of function, normal operating characteristics and limitations, performance curves, engineering data and tests, and complete nomenclature and commercial numbers of replacement parts.
b. Manufacturer's printed operating procedures to include start-up, break-in, and routine and normal operating instructions; regulation, control, stopping, shutdown, and emergency instructions; and summer and winter operating instructions.
c. Maintenance procedures for routine preventative maintenance and troubleshooting; disassembly, repair, and reassembly; aligning and adjusting instructions.
d. Servicing instructions and lubrication charts and schedules.
1.4 QUALITY ASSURANCE
1. Comply with NFPA 70 for components and installation.
2. All electrical installations shall be performed or supervised by a licensed electrician.
1.5 DELIVERY, STORAGE, AND HANDLING
1. Deliver products to the project properly identified with names, model numbers, types, grades, compliance labels, and other information needed for identification.
PART 2 - PRODUCTS
2.1 BUILDING WIRE
1. Description: Single conductor, copper. Solid conductor for No. 10 AWG and smaller; stranded conductor for larger than No. 10 AWG.
2. Thermoplastic Insulated Wire: Conform to NEMA WC 5.
3. Connectors and Splices: Units of size, amperage rating, material, type, and class suitable for service indicated. Select to comply with Project's installation requirements.
2.2 SUPPORTING DEVICES
1. Channel and angle support systems, hangers, anchors, sleeves, brackets, fabricated items, and fasteners are designed to provide secure support from the building structure for electrical components.
a. Material: Steel, except as otherwise indicated, protected from corrosion with zinc coating or with treatment of equivalent corrosion resistance using approved alternative finish or inherent material characteristics.
b. Metal Items for Use Outdoors or in Damp Locations: Hot-dip galvanized steel, except as otherwise indicated.
2. Steel channel supports have ½" diameter holes at a maximum of 8" o.c., in at least 1 surface.
a. Fittings and accessories mate and match with channels and are from the same manufacturer.
3. Raceway and Cable Supports: Manufactured clevis hangers, riser clamps, straps, threaded C-clamps with retainers, ceiling trapeze hangers, wall brackets, and spring steel clamps or "click"- type hangers.
4. Sheet-Metal Sleeves: 0.0276" or heavier galvanized sheet steel, round tube, closed with welded longitudinal joint.
5. Pipe Sleeves: ASTM A 53, Type E, Grade A, Schedule 40, galvanized steel, plain ends.
6. Expansion Anchors: Carbon-steel wedge or sleeve type.
7. Toggle Bolts: All-steel springhead type.
8. Powder-Driven Threaded Studs: Heat-treated steel.
2.3 TOUCHUP PAINT
1. For Equipment: Provided by equipment manufacturer and selected to match equipment finish.
2. For Non-equipment Surfaces: Matching type and color of undamaged, existing adjacent finish.
3. For Galvanized Surfaces: Zinc-rich paint recommended by item manufacturer.
PART 3 - EXECUTION
3.1 ROUGH-IN
1. Verify final locations for rough-ins with field measurements and with the requirements of the actual equipment to be connected.
3.2 ELECTRICAL INSTALLATIONS
1. General: Sequence, coordinate, and integrate the various elements of electrical systems, materials, and equipment. Comply with the following requirements:
a. Coordinate electrical systems, equipment, and materials installation with other building components.
b. Verify all dimensions by field measurements.
c. Arrange for chases, slots, and openings in other building components during progress of construction, to allow for electrical installations.
d. Coordinate the installation of required supporting devices and sleeves to be set in poured-in-place concrete and other structural components, as they are constructed.
e. Sequence, coordinate, and integrate installations of electrical materials and equipment for efficient flow of the Work.
f. Where mounting heights are not detailed or dimensioned, install systems, materials, and equipment to provide the maximum headroom possible.