This document is a Project Specification for the replacement of the heating, ventilation, and air conditioning (HVAC) system at the Charles Peirce House in the Delaware Water Gap National Recreational Area. The work includes the complete replacement of the existing HVAC system.
The project will be constructed under a single prime contract. The contractor will have limited use of the site and must comply with various environmental and noise requirements, including recycling and waste management. The work must be coordinated with the ongoing operations and access requirements of the government. The contractor is required to provide a construction schedule, quality control plan, and other administrative submittals. Permits required for the work must be obtained and coordinated by the contractor. The project involves a 100% construction document submission, and the government will have the right to partially occupy the completed areas.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Pre-Bid_MeetingParticipating_0003.pdf | ||
| Questions_and_answers_0003.pdf | ||
| Sol_140P4524R0009_Amd_0003.pdf | ||
| Sol_140P4524R0009_Amd_0002.pdf | ||
| Sol_140P4524R0009_Amd_0001.pdf | ||
| B08_Attachment_3_WD_PA20240103_4-5-2024_Replace_HVAC_DEWA.pdf | ||
| Sol_140P4524R0009.pdf | ||
| B08_Attachment_5_Price_Schedule_Peirce_HVAC_DEWA.pdf | ||
| B08_Attachment_4_PPQ_Peirce_HVAC_DEWA.pdf | ||
| B08_Attachment_2_Drawings_Peirce_HVAC_DEWA.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Delaware Water Gap National Recreational Area
Charles Peirce House HVAC Design
DEWA PMIS No. 326047
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
Final 100% Construction Documents Submission
March 14, 2022
DEWA - 245920 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 26 01 CONTRACT MODIFICATION PROCEDURES
01 31 00 PROJECT MANAGEMENT AND COORDINATION
01 32 18 CONSTRUCTION SCHEDULE
01 32 33 PHOTOGRAPHIC DOCUMENTATION
01 33 23 SUBMITTAL PROCEDURES
01 35 13.22 ARCHEOLOGICAL PROTECTION
01 35 23 SAFETY REQUIREMENTS
01 35 91 HISTORIC PRESERVATION TREATMENT PROCEDURES
01 40 00 QUALITY REQUIREMENTS
01 42 00 REFERENCE STANDARDS
01 50 00 TEMPORARY SERVICES, FACILITIES AND CONTROLS
01 57 19.11 INDOOR AIR QUALITY MANAGEMENT
01 57 19.12 NOISE AND ACOUSTICS MANAGEMENT
01 57 23 UNDER AN ACRE POLLUTION PREVENTION
01 67 00 PRODUCT REQUIREMENTS
01 73 29 CUTTING AND PATCHING
01 73 40 EXECUTION
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 77 00 CLOSEOUT PROCEDURES
01 78 23 OPERATIONS AND MAINTENANCE DATA
01 79 00 DEMONSTRATION AND TRAINING
01 81 13 SUSTAINABLE DESIGN REQUIREMENTS
01 91 14 TOTAL BUILDING COMMISSIONING
DIVISION 02 – EXISTING CONDITIONS
02 41 00 SELECTIVE DEMOLITION
DIVISION 03 THRU 6 – NOT USED
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 21 26 BLOWN INSULATION
DIVISION 08 – OPENINGS
08 58 10 CUSTOM STORM WINDOWS
DIVISION 09 – FINISHES
09 91 13 EXTERIOR PAINTING
09 91 23 INTERIOR PAINTING
DIVISION 10 THRU 21- NOT USED
DIVISION 22 – PLUMBING
22 11 29 PLUMBING SYSTEM PUMPS
DIVISION 23 – HEATING, VENTILATION, AND AIR CONDITIONING
23 05 00 BASIC MECHANICAL MATERIALS AND METHODS
DEWA - 245920 TOC-2
23 05 48 MECHANICAL SOUND AND VIBRATION CONTROLS
23 05 93 TESTING ADJUSTING AND BALANCING
23 07 00 MECHANICAL INSULATION
23 09 23 HVAC INSTRUMENTATION AND CONTROLS
23 20 00 BUILDING SERVICES PIPING
23 31 13 DUCTS AND DUCT ACCESSORIES
23 34 16 FANS
23 37 13 AIR OUTLETS AND INLETS
23 70 00 HEATING, VENTILATING, AND AIR CONDITIONING
23 82 16 HEATING AIR COILS
DIVISION 25 – NOT USED
DIVISION 26 – ELECTRICAL
26 05 00 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19 ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
26 05 53 IDENTIFCATION FOR ELECTRICAL SYSTEMS
26 27 26 WIRING DEVICES
26 28 13 FUSES
26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
DIVISION 27 THRU 49 - NOT USED
END OF CONTENTS
DEWA - 245920 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Under Other Contracts
3. Contractor Use of Site
4. Public Use of Site
5. Occupancy Requirements for Buildings
6. Conduct of Operations
7. Work Restrictions
8. Special Construction Requirements
9. Soils Investigation Report
10. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Delaware Water Gap National Recreational Area, Charles Peirce House 294
Old Milford Road, Milford, PA 18337.
B. The Work consists of:
1. The Work includes complete replacement of the existing heating and cooling system.
C. Project will be constructed under a single prime contract.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Contractor shall note that work under this contract may run concurrent with other contracts at this site.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations during the construction period. Contractor's use of the site is limited by the Government's right to perform work or to retain other contractors on portions of Project.
1. Limits: Confine constructions operations to building areas requiring work, as indicated in the contract drawings.
2. Limit site disturbance, including earthwork and clearing of vegetation, to 4 feet beyond mechanical pad expansion.
DEWA - 245920 01 11 00 - 2
B. Protection of Public: Contractor shall at all times conduct project operations to ensure the least inconvenience to the NPS Employee and Visitor. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs in accordance with MUTCD-2009. Road closures will be permitted, when required, upon specific approval of Contracting Officer on a case by case basis with at least 48 hours advanced notice.
C. Storage of Materials: Confine storage of materials to locations coordinated with Park. Staging and parking for vehicles, equipment and materials shall be confined to hardscape areas and parking areas, and gravel areas with advanced park approval or directed otherwise by the
Contracting Officer. Long-term placement of equipment requires additional clearance. Storage of any materials or equipment on site shall be at the Contractor’s own risk.
D. Check the job site at the end of each day to remove trash, food, and food-related items remaining at the site and disposing of them in an appropriate receptacle.
E. Preservation of Natural Features and Environmental Requirements:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer Representative (COR) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
6. No operations should occur within drip area of any tree.
7. To reduce the potential for rutting, erosion and soil compaction, the use of heavy equipment will be used only when other options are exhausted.
8. Install erosion and sediment control measures at the work site in accordance with the contract specifications, drawings, and compliance requirements provided. If no drawing details are provided then E&S best practices prevail and a form documenting an “under
1 acre of disturbance plan” form must be provided to the government as part of Division
I submittals.
9. Use only certified weed-free straw or mulch to minimize the potential spread of exotic plants in disturbed areas.
10. Soil: Protect against erosion and topsoil depletion according to specifications, best practices or industry standard. Restore staging areas or any disturbed areas to their original condition. At the direction of the CO, restore/treat any turf or trees disturbed during construction according to specifications, best practices or industry standard.
11. Habitats: Protect natural habitats and ecological systems at Peirce House site (as identified in the Categorical Exclusion and delineated Construction Zone - Area of Potential
Affects).
12. Noise: Minimize noise generation during construction. Operate power equipment in accordance with local noise restrictions. See section 01 57 19.12 - Noise and Acoustics
Management.
13. Waste Management Goals: Employ processes that ensure the generation of as little waste as possible due to over-packaging, error, poor planning, breakage, mishandling, contamination, or other factors. Of the inevitable waste that is generated, as many of the
DEWA - 245920 01 11 00 - 3
waste materials as economically feasible shall be reused, salvaged, or recycled. Waste disposal in landfills shall be minimized.
14. Materials: Use resources efficiently. Use construction practices that achieve the most efficient use of resources and materials.
15. Recycling:
a. Recycling and recycling documentation of material and quantities is a requirement of this project. Provide NPS with a copy of the documentation. Materials to be recycled include but are not limited to the following:
1) Cardboard, paper, packaging
2) Clean dimensional wood, palette wood
3) Beverage containers
4) Land clearing debris
5) Concrete
6) Metals, wood trim, rebar, aluminum, copper, zinc, lead, brass, and bronze.
7) Paint
8) Rigid Foam
9) Plastics
b. All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park. Contractor shall be required to provide evidence of legal disposal of all construction materials.
16. The Contractor shall designate an on-site party (or parties) responsible for instructing workers and overseeing the Environmental requirements of this project and distribute copies of the Environmental requirements to the Job Site Foreman and each
Subcontractor.
F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
G. Construction Camp: Establishment of a camp within park will not be permitted.
H. Access Restrictions: Access to the project site must be from NPS drive from Route 209/Route 6, not Old Milford Rd. Old Milford Road is a residential low volume road and shall not be used for deliveries and/or site access. All deliveries and site access must be from Route 209/Route 6 onto
NPS Driveway.
I. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1. Ensure all vehicles and equipment entering the park are clean of soil, mud, vegetation, noxious weeds and exotic seeds and free from oil leaks. All vehicles are subject to inspection. Clean vehicles and equipment offsite and off NPS lands. Show attention to the under carriage and any surface where soil containing exotic seeds may exist like cracks, DEWA - 245920 01 11 00 - 4 crevices and tire treads. Wash all construction equipment with a high-pressure washing method to thoroughly remove all dirt, plant, and other foreign material prior to entering the Park. Use a minimum water pressure of 90 pounds per square inch for vehicle cleaning.
Equipment found operating on the project that has not been inspected, or has oil leaks will be shut down and subject to citation.
J. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA
241.
1. Responsible Person: A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.
2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of National Park Service.
3. Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in structures. Provide adequate ventilation during use of volatile or noxious substances, particularly during soldering or brazing work.
4. Spark Arresters: Equip all gasoline or diesel powered equipment used during periods of potential fire hazards or in potential forest and grass fire locations with spark arresters approved by the USDA Forest Service.
5. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.
6. Vehicles and Equipment: Provide one extinguisher on each vehicle or piece of equipment.
1.5 PUBLIC USE OF SITE
A. The building will be closed to the public during construction.
1.6 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings/New Building System
1. Partial Government Occupancy: Government will periodically occupy premises during entire construction period, with exception of areas under construction. Cooperate with
Government during construction operations to minimize conflicts and facilitate
Government usage. Perform Work so as not to interfere with Government’s operations.
Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from COR.
b. The Government will have continued access to the building for maintenance of the building, IT Computer servers and manual safe. The safe is located in the map room
- 208 and the computer server is located in the GIS Closet - 207.
c. Maintain continuity of power for IT system equipment including but not limited to servers, telecom/data and similar equipment. Provide temporary power for
DEWA - 245920 01 11 00 - 5
equipment to ensure continuous operation. Access to the server must be maintained throughout project duration.
d. Contractor to coordinate any interruptions to this access with the COR not less than five days in advance of a proposed interruption of access or services. IT personnel must coordinate with contractor prior to power disruption.
2. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.
a. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.
On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.
b. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.
1.7 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the COR. Submit requests 48 hours in advance of the work to the COR for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the COR.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise arranged with COR.
1. Weekend and Federal Holiday Hours: Saturday and Federal Holiday work will be permitted on a case by case basis. Notify COR of anticipated Saturday or Federal Holiday work a minimum of 48 hours in advance. Sunday work will not be permitted.
2. Hours for Utility Shutdowns: Will be coordinated with the COR and Park POC with a five work day advance notice.
B. Existing Utilities
1. Existing Utilities: Notify COR and utility companies of proposed locations and times for excavation.
DEWA - 245920 01 11 00 - 6
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving government facilities unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify COR not less than 10 business days in advance of proposed utility interruptions. IT personnel will need to be present, and date/time will need to e coordinated.
2. Do not proceed with utility interruptions without COR’s written permission.
3. Hours and length of Utility Shutdowns: Coordinate hours and duration of utility shutdowns with COR.
D. Temporary Utilities
1. Electric Power Service:
a. Install temporary service if needed. Arrange with utility company, for time when service can be interrupted, if necessary, to make connections for temporary services.
b. Provide connections and extensions of services as required for construction operations.
c. Electric Power/Service/Generator: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA
70.
d. Provide generator for temporary power to ensure continuous coverage and operation of computer Server.
2. Telephone Service: No telephone service is available on site for Contractor's use. Cell phone coverage is generally dependable, but spotty in certain areas.
3. Water: Neither potable water nor construction water is available from the park site.
Contractor will need to provide their own source of water from outside of the Park.
Existing sulfur water is from a bad well with little water pressure. Government is in process of trying to procure water authority connection.
E. Nonsmoking Building/Tobacco Use/Vaping: Smoking/Tobacco Use/Vaping is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes.
F. Prior to any cutting, patching or demolition work, all furniture, furnishings, equipment and electronics are to be sufficiently covered to avoid dust. Any electronic equipment that has a fan or generates heat must still be allowed adequate airflow so they will not be negatively impacted.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
DEWA - 245920 01 26 01 - 1
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
DEWA - 245920 01 26 01 - 2
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
DEWA - 245920 01 26 01 - 3
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
DEWA - 245920 01 26 01 - 4
3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
DEWA - 245920 01 26 01 - 5
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit………………X.XX%
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
DEWA - 245920 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
DEWA 245920 01 31 00 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. Project Meetings
7. Environmental Coordination
8. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction
B. Construction Permits – Contractor Provided
C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
DEWA 245920 01 31 00 - 2
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination
Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer
Representative (COR) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 millimeters) but no larger than 30 by
40 inches (750 by 1000 millimeters).
3. Number of Copies: Submit 2 opaque copies of each submittal. COR will return 1 copy.
DEWA 245920 01 31 00 - 3
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Section
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural, structural, mechanical, plumbing, fire-protection, fire-alarm, and electrical elements. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Plenum Space: Indicate sub-framing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.
3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.
6. Mechanical and Plumbing Work:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.
c. Fire-rated enclosures around ductwork.
7. Electrical Work:
a. Runs of vertical and horizontal conduit 1-1/4 inches (32 millimeters) in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
8. Fire-Protection System:
a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.
9. Review: COR will review coordination drawings to confirm Work is being coordinated;
details of coordination are Contractor's responsibility. If COR determines coordination drawings are not prepared in scope or detail, or are otherwise deficient, COR will inform
Contractor, who shall make changes and resubmit.
10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to:
DEWA 245920 01 31 00 - 4
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit coordination drawing files using Portable Document
Format (PDF) file format.
3. Contracting Officer will furnish Contractor one set of digital data files (AutoCad.dwg) of
Drawings for use in preparing coordination digital data files.
a. COR makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCad.dwg.
D. Division 1 documents: The following items shall be submitted a minimum of one week prior to
Preconstruction Conference. COR will notify Contractor of tentative date for Pre-Construction
Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
8. Waste Management Plan
9. Quality Control Plan
10. Under an Acre Pollution Prevention Plan (UPPP)
11. Indoor Air Quality (IAQ) Management Plan
12. Contractors Commissioning Plan
13. Historic Preservation Treatment Plan (HPTP)
14. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
E. Provide items listed to COR before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and COR will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of
Contract Documents, Contractor shall prepare and submit to the COR a completed RFI utilizing form found on NPS/DSC Website: www.nps.gov/dsc/workflows/index.html.
1. COR will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
DEWA 245920 01 31 00 - 5
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. COR’s Action: COR will review each RFI, determine action required, and respond. COR will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. COR’s action may include a request for additional information; time for response will date from time of receipt of additional information.
3. COR’s action on RFIs may result in need for a change to Contract Time or Contract Sum.
All contract changes will be processed following terms and conditions of contract.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, COR will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
DEWA 245920 01 31 00 - 6
7. Modifications
8. Payments to Contractor
9. Payroll reports
10. Contract time
11. Liquidated damages
12. Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
15. Correspondence procedures
16. Acceptance/rejection of work
17. Progress meetings
18. Submittal procedures
19. NPS Final Accessibility Inspection
20. Environmental requirements
21. Permit requirements
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials
25. Value engineering
26. Schedule of Values
B. Progress Meetings: COR will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the
Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and
DEWA 245920 01 31 00 - 7
installations that have preceded or will follow, shall attend meeting. Advise Contracting
Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Sustainable design requirements
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
m. Manufacturer's written instructions
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
q. Temporary facilities and controls
r. Space and access limitations
s. Regulations of agency(ies) with jurisdiction
t. Testing and inspecting requirements
u. Installation procedures
v. Coordination with other work
w. Required performance results
x. Protection of adjacent work
y. Protection of construction and personnel
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing
Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
DEWA 245920 01 31 00 - 8
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of Indoor Air Quality (IAQ) Management Plan.
d. Implementation of Under an Acre Pollution Prevention Plan (UPPP).
e. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
f. Training for Contractor personnel in accordance with position requirements.
g. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Indoor Air Quality (IAQ) Management
4. Noise and Acoustics Management
5. Temporary Storm Water Pollution Prevention Environmental Management
6. Construction Waste Management
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to building industry.
2. Overview of environmental issues related to Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Indoor Air Quality (IAQ) Management
c. Noise and Acoustics Management
d. Temporary Storm Water Pollution Prevention
4. Pollution Prevention (P2) practices: Submit evidence of familiarity with P2 practices.
5. Green Building Rating Programs: Submit evidence of familiarity with United States Green
Building Council-Leadership in Energy and Environmental Design (USGBC-LEED).
6. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of COR.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution
Prevention Plan.
1.8 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the
Government, be responsible for obtaining necessary licenses and permits, and for
DEWA 245920 01 31 00 - 9
complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the
Government. Contractor shall comply with appropriate Federal, State and local laws.
B. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
C. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with…