Questions_and_answers_0003.pdf

PDF 125 KB Posted

Attached to
DEWA REPLACE HVAC SYSTEM PEIRCE HOUSE Federal contract opportunity
Solicitation number
140P4524R0009
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This document provides a set of Questions and Answers related to a federal contract opportunity for the DEWA REPLACE HVAC SYSTEM PEIRCE HOUSE project, solicitation number 140P4524R0009, issued by the Department of the Interior National Park Service Northeast Region.

The key details include:

  • Clarification on the maximum sizes of openings greater than 4" dia. referenced in the drawings, with most being less than 8"
  • Confirmation that all the 21 instances of patching holes from removed penetrations are similar to the examples shown
  • Confirmation that no hazardous materials have been found in the vermiculite insulation in Area 305
  • Clarification that the blower door and airflow test are for reference purposes only, with no required ACH value
  • No baseline blower door test has been performed
  • The contractor can propose a Samsung HVAC system if it meets the requirements as an "as equal product"
  • There are no phasing requirements, but the project will be shut down during winter months
  • The Superintendent, SSHO and QC Manager can be two separate individuals, but the QC/SSHO cannot be the Superintendent
  • No further site visits are planned
  • Period of performance may be extended after award if material/equipment lead times require it.

View the file

Other files for this federal contract opportunity

Other files attached to DEWA REPLACE HVAC SYSTEM PEIRCE HOUSE, newest first.
File Type Posted
Pre-Bid_MeetingParticipating_0003.pdf PDF
Sol_140P4524R0009_Amd_0003.pdf PDF
Sol_140P4524R0009_Amd_0002.pdf PDF
Sol_140P4524R0009_Amd_0001.pdf PDF
B08_Attachment_4_PPQ_Peirce_HVAC_DEWA.pdf PDF
B08_Attachment_3_WD_PA20240103_4-5-2024_Replace_HVAC_DEWA.pdf PDF
Sol_140P4524R0009.pdf PDF
B08_Attachment_1_SOW_Peirce_HVAC_DEWA.pdf PDF
B08_Attachment_5_Price_Schedule_Peirce_HVAC_DEWA.pdf PDF
B08_Attachment_2_Drawings_Peirce_HVAC_DEWA.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and answers

1. Drawing A1.1 – BASEMENT & FIRST FLOOR PLAN Keynote 4.1 says “Openings greater than 4” dia” – for pricing purposes please provide a maximum size for these openings, typical of 7 locations. No hole is greater than 18" and that one is shown as image #1. Most are less than 8".

2. Drawing A1.1 – BASEMENT & FIRST FLOOR PLAN Keynotes 4.1 & 4.2 - are all of these (21) instances similar to Images 1 & 2 on detail 1/A1.1, patching holes at removed penetrations? Yes.

3. Drawing 4/AD.1 – THIRD FLOOR PLAN – DEMOLITION – Keynote 7.1 – Area 305 appears to have vermiculite insulation. Has the insulation in area 305 been sampled and tested for hazardous materials? The Park has tested this building in the past and no asbestos or other hazardous materials have been found.

4. Drawing M0.1 MECHANICAL COVER SHEET – Blower Door and Airflow Test – Note C. says the blower door test shall occur following completion of construction. Is there an ACH value the contractor will be required to meet, or is blower door testing for reference purposes only?

Blower Door Test and Airflow Test is just for reference.

5. Has a baseline blower door test been performed? If so, please provide pre-construction test results. No blower door test has been performed.

6. In PROJECT SPECIFICATIONS Section 23 70 00 - 20, line 2.3S. states that the acceptable manufacturers are Governair, Greenheck, Semco, and Trane. Would you consider using a Samsung system for this project? They are widely used throughout the U.S. on similar projects.

Samsung system would be considered if the contractor can prove that that the Samsung system meets all of the requirements and is an "as equal product".

7. Are there any phasing requirements for this project? How many people will be in the building?

Are there any temporary heating/cooling requirements? There are no phasing requirements.

Employees will be teleworking during this time but will occasionally need to come into the building for files or equipment. Additionally, maintenance folks will be periodically conducting maintenance. The project will be shut down during the winter months and started back up in the spring. Shutdown, water, heating, and cooling will need to be coordinated between the gov selected contractor.

8. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals? It will need to be at least 2 separate people, the QC/SSHO cannot be the superintendent.

9. 3) Spec section 2.3S. (pg 23 70 00 - 20 ) states that the acceptable manufacturers are Governair, Greenheck, Semco, and Trane. Would you consider using a Samsung system for this project?

Samsung system would be considered if the contractor can prove that that the Samsung system meets all of the requirements and is an "as equal product".

10. Is the another opportunity for a site visit? No. Site visit has already occurred.

11. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project? Period of performance is set as specified, however, if there are conditions as described in the contract clauses that allow for contract extension, then extensions will be considered.

12. Please provide the site visit attendee sign in sheet.