This document is a Statement of Work (SOW) for the Prosper Ridge Road Culvert Replacement Project, a federal contract opportunity solicited by the Department of the Interior Bureau of Land Management California Region.
The SOW requires the contractor to remove and replace deteriorated culverts along approximately one mile of Prosper Ridge Road in the King Range National Conservation Area near Petrolia, California. Key tasks include installing new culverts, constructing rolling dips and critical dips, placing aggregate base, and armoring fill slopes. The contractor must provide culverts, rock, and water, while the government will provide one 24-inch culvert. The period of performance is 60 days, to be completed by October 31, 2024. Optional additive items include installing additional rolling dips and enhancing the road outslope. Contractor safety, security, and contingency planning requirements are also specified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B09_Prosper_Ridge_Culvert_site_visit_sign_in_0001.pdf | ||
| B09_Prosper_Ridge_Rd_Questions_Recieved_080624_0001.docx | DOCX document | |
| B09_REVISED_B08_Attachment_1_Prosper_Road_SOW_0001.docx | DOCX document | |
| Sol_140L1224R0003_Amd_0001.pdf | ||
| B08_Attachment_3_-_Price_Table.xlsx | XLSX spreadsheet | |
| B03_Attachment_2_-_Davis-Bacon_Act_WD___CA20240004v5.pdf | ||
| Sol_140L1224R0003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
| 1.0 - Background on the Government’s Requirement | 2 |
| 2.0 - General Scope of Work | 2 |
| 3.0 - Overall Objective(s) | 4 |
| 4.0 - Specific Tasks | 4 |
| 5.0 - Delivery / Performance Schedule | 7 |
| 6.0 - Government-Furnished Property, Materials, Services | 7 |
| 7.0 - Security and Administrative Matters | 8 |
| 8.0 - Technical Exhibits and Definitions | 10 |
1.0 - Background on the Government’s Requirement
The Bureau of Land Management (BLM) Arcata Field Office requires roads-related construction services to replace deteriorated culverts along Prosper Ridge Road in the King Range National Conservation Area (Map 1). The project will install new culverts and upgrade associated surface drainage conditions along approximately one mile of rural dirt and aggregate-surface road in Humboldt County near the community of Petrolia. The road provides access to both public and private lands. Specific actions include culvert replacements, rolling dip construction, aggregate base installation, road reshaping, and rock armoring of vulnerable fill slopes. The contractor will have to supply culverts, rock and water for compaction purposes at each of the treatment sites. The government will provide culvert pipe for one of the sites as detailed below. The work will be in a relatively remote setting with poor to nonexistent cell phone coverage.
2.0 - General Scope of Work
Services include the removal and installation of culverts at three sites along Prosper Ridge Road. The site locations are shown on the map in Figure 1 and the table below lists the general scope of work entailed for each site. Culvert replacement sites will be accompanied by installation of rolling dips, critical dips and rock armoring on the approaches. Specifications for rolling dips and critical dips are provided in Appendix A and contractor will be required to adhere to these in order to provide all season vehicle passage. Prior to the start of work, the BLM will stake and/or flag individual treatment sites.
Required Treatment Sites:
| Site # |
| Milepost |
| Treatment |
| 1 |
| 2.15 |
| Remove 2 deteriorated culverts, |
Install 54” culvert on new alignment, Install rock armor along fillslope and at inlet, Install one rock-armored rolling dip, Install and compact 3” class II base rock 40’x20’
| 2 |
| 2.0 |
| Remove 2 deteriorated culverts, |
Replace with 36” culvert, Install rock armor along fillslope and at inlet, Install one rock-armored rolling dip, Install and compact 3” class II base rock 60’x20’
| 3 |
| 1.75 |
| Remove 1 deteriorated culvert, |
Replace with 24”x33’ culvert provided by government Install two rock-armored rolling dips, Install one rock-armored critical dip, Install and compact 3” class II base rock 70’x 20’ though crossing
Additive Items:
Depending on funding availability, two additional treatments will be performed as defined below. The possible locations are also shown on Figure 1:
Additive Item A – Add Rolling Dip (cost per site)
· Install additional rocked, rolling dip along the road. Rolling dip installation shall be consistent with specifications in Appendix A. Rock shall consist of 3” ballast rock placed through the axis of the dip and then surfaced with Class II base or suitable substitute along the entire disturbed length.
· Cost for Additive Item A shall be for a single rolling dip, added at any location along the road. Two potential sites are shown in the attached map. Specific locations along Prosper Ridge Road will be identified by the COR depending on the quantity awarded and funding availability.
Additive Item B – Enhance Outslope along 125-feet of Road
· Enhance outslope along 125 feet at the point indicated in attached map adjacent to site #1. Contractor will make efforts to salvage existing rock on the road tread and apply additional 3” subbase to achieve a minimum of 6” depth. Treated segment will then be surfaced with a minimum of 3” Class II base or equivalent.
General Specifications:
· New culverts shall be Aluminized, Type 2 corrugated metal pipe for all culvert sites. Culverts 42" or smaller shall be 12 gauge aluminized corrugated metal pipe. Culverts 48" and larger shall be 10 gauge aluminized corrugated metal pipe.
· Culvert coupling bands shall be made of the same material as the culvert.
· Culverts shall be set into prepared native material free of visible organic debris and rock particles >3”. Compaction shall conform to requitements in Appendix A.
· Contractor shall provide sufficient water to achieve compaction at all treatment sites.
· Ballast rock and Class II base rock shall be angular, crushed particles. Substitutions may be proposed for road base materials to meet the Class II base rock objective of providing a durable all-season running surface.
· Ballast rock shall be 3” max and shall be placed through the axis of the rolling dip / critical dip and then surfaced with Class II base or suitable substitute along the entire disturbed length.
· Rolling Dip/Critical Dip: Assume a 20-foot wide, 80-foot long, 3-inch thick course of Class II base, and one full dump truck load (8yards or x-tons) of 3” ballast rock placed in the center. Install in accordance with the standard typical drawings (Appendix A).
Local Quarries for rock material supplies:
· Billy Eddars in Honeydew, California
· Bear Butte Rock Quarry in Miranda, California
Place of Performance:
Work will be performed along Prosper Ridge Road, located approximately 6 miles SW of the community of Petrolia, California in Humboldt County. One map is provided showing the treatment locations.
For general orientation purposes, Site # 1 is located at the following coordinates:
Latitude: 40.27369 Longitude: -124.34514
Period of Performance:
The period of performance shall be 60 days, commencing at the time of award and completed no later than October 31, 2024.
3.0 - Overall Objective(s) The objectives of this work are:
(1) Replace deteriorated culverts along Prosper Ridge Road to maintain road-stream crossing functions; and
(2) Install rocked, rolling dips on relevant road sections to minimize road surface erosion, disperse runoff and provide for safe vehicle passage conditions that includes trailers and logging trucks.
4.0 - Specific Tasks
Task 1 – Treatment Site #1
a. Remove and dispose of existing pipes offsite at disposal facility. Replace, add, and compact fill through abandoned pipe alignment to restore road running surface. Import new fill as needed or lower road fill accordingly.
b. Install 54” x 60’ corrugated metal pipe along axis of channel as flagged by the BLM. Contractor shall utilize Aluminized, Type 2, 10-gauge corrugated metal pipe. Culvert outlet elevation will be located by BLM staff that maintains a channel slope through the site. The inlet may be countersunk on the order of 1-2’ in order to provide for a minimum of 24” of overhead fill. Cutting of pipe end(s) may be required to meet road dimensions.
c. Reconstructed outlet fill slope will be rock armored with 6”-24” boulders with the following dimensions (facing downstream):
· Right bank fill slope: 30’ wide x 15’ slope length
· Left bank: 50’ wide x 15’ slope length
· Finished depth shall be a minimum of 18”
d. Newly installed culvert inlet shall be armored with 12-24” boulders to create a “vee-shaped” inlet configuration.
e. Install one rocked rolling dip on right approach to crossing. Specific location will be identified during project construction.
f. Install Class II base through the site at a minimum depth of 3” and approximate area of 20’ wide x 40’ long,
g. Use excess fill or in-stream excavations to fill in old channel where pipes were removed from in order to ensure all stream flows are directed into new culvert.
h. Substitutions may be made for the class II base if the COR determines they meet the requirements for road armoring and vehicle passage. Rounded, river-run rock shall not be used as a substitute.
Task 2 – Treatment Site #2
a. Remove and dispose of existing pipes offsite at disposal facility.
b. Install 36” x 40’ corrugated metal pipe to match stream grade through site. 40’ length may minor reductions in road width to maintain pipe slope. Contractor shall utilize Aluminized, Type 2, 12-gauge corrugated metal pipe. Cutting of pipe end(s) may be required to match road dimensions.
c. Reconstructed outlet fill slope will be rock armored with 6”-24” boulders with the following dimensions (facing downstream):
· Right bank fill slope: 15’ wide x 12’ slope length
· Left bank: 15’ wide x 12’ slope length
· Culvert outfall shall also be armored for a minimum distance of 10’ downstream.
· Finished depth shall be a minimum of 18” deep.
d. Newly installed culvert inlet shall be armored with 12-24” boulders to create a “vee-shaped” inlet configuration.
e. Install one rocked rolling dip on left approach to crossing approximately 115’ from culvert centerline. Specific location will be identified during project construction. Minimum rock depth shall be 3” through the constructed site.
f. Install Class II base through the site at a minimum depth of 3” and approximate area of 20’ wide x 60’ long.
g. Substitutions may be made for the class II base if the COR determines they meet the requirements for road armoring and vehicle passage. Rounded, river-run rock shall not be used as a substitute.
Task 3 – Treatment Site #3
a. Remove and dispose of existing pipe offsite at disposal facility.
b. Install 24” x 33’ corrugated metal pipe to match stream grade through site. Pipe is onsite and will be provided by the government. Cutting of pipe end(s) will be needed to match road dimensions.
c. Install one rocked rolling dip on left approach to crossing approximately 100’ from culvert centerline. Specific location will be identified during project construction.
d. Install one rocked rolling dip on right approach to crossing approximately 170’ from culvert centerline. Specific location will be identified during project construction.
e. Install critical dip 25’ below right approach to ensure overtopping flows re-enter channel.
f. Install Class II base through the site at a minimum depth of 3” and approximate area of 20’ wide x 70’ long.
g. Substitutions may be made for the class II base if the COR determines they meet the requirements for road armoring and vehicle passage. Rounded, river-run rock shall not be used as a substitute.
Task 4 – Additive Item A – Additional Rolling Dips
a. This task will only be selected if funding is available at time of award.
b. Cost is per Rolling Dip
c. Two possible locations are shown on Figure 1.
d. Rolling Dip will be constructed as specified in this SOW and Appendix A.
Task 5 – Additive Item B – Enhance 125-feet of Road Outslope
a. This task will only be selected if funding is available at time of award.
b. Location of enhanced outslope is shown on Figure 1.
c. Perform grading to define the outslope along this 125 foot section of road.
d. Road width is 20 feet.
e. Grade the existing 20-ft wide 125-ft long road section to shape and contour the outslope.
f. Furnish additional 3-inch deep course of sub-base material an add to the existing sub-base. Total sub-base thickness shall be 6-inches including existing and new material. The new material shall be 3-inch thick compacted section along the entire 20-ft wide 125-ft long road section. Compaction shall be 90-percent relative compaction.
g. Furnish Class II aggregate base placed on top of the sub-base layer. Place, spread, and compact a 3-inch thick section of compacted Class II aggregate base section along the entire 20-ft wide 125-ft long road section. Compaction shall be 90-percent relative compaction.
5.0 - Delivery / Performance Schedule The Contractor shall complete all road treatments and any awarded additive items within 60 calendar days after notice to proceed. All work must be completed by October 31.
Final Inspection and Acceptance. The Contracting Officer’s Representative will review all work. At the conclusion of the work, the Contracting Officer, or their representative, will inspect all sites for conformance with the specifications and requirements. The contractor will be asked to demonstrate dimensions for compliance with specifications such as those described in Appendix A. Any deficiencies noted during the inspection will require correction prior to release of final payment. Prior to final payment the Contractor will have properly disposed of all waste materials including culverts.
Any staging and storage areas will be restored to pre-disturbance topography and left in a free draining condition.
6.0 - Government-Furnished Property, Materials, Services
General:
The Contractor shall furnish all personnel, materials, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the work tasks defined in this Performance Work Statement, except for those items specified as government furnished.
Materials:
The Government shall furnish the below materials to assist the Contractor in meeting the requirement of this contract:
a. Corrugated metal pipe, 40’x24” for installation at Prosper Site #3. Pipe is located on site.
Equipment:
The Government will not be furnishing any equipment to assist the Contractor in meeting the requirement of this contract.
Applicable Publications (Current Editions) Contractor will abide by all stream crossing and rolling dip specifications outlined in the “Handbook for Forest, Ranch & Rural Roads”(Pacific Watershed Associates 2014) and available online at:
https://www.pacificwatershed.com/roadshandbook
These specifications are provided in Appendix A and shall be incorporated into the treatments.
7.0 - Security and Administrative Matters
No special surety arrangements are required for this project. The road is located on an all-season public road.
Security:
The Contractor shall be responsible for safeguarding all Government property provided for Contractor use or under their control, including securing all facilities the Contractor may access after normal business hours.
Contractor shall coordinate work schedule with Contracting Officers Representative to minimize public and employee ingress/egress to the building.
Safety:
The Contractor shall not require, or allow any employee, engaged in the performance of this Contract to work under conditions which are unsanitary, hazardous, or dangerous to his/her health or safety, as determined under safety and health standards promulgated by the Secretary of Labor under Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C. 327 et seq.) as amended and other Federal, State and applicable local government safety standards.
Department of Labor Code of Federal Regulations Title 29 and other Federal, State and local government safety standards will apply in its entirety to the Contractor.
Examples of applicable safety standards are OSHA 29 CFR 1910, OSHA 29 CFR 1926, California Title 19, "Public Safety", California Title 8, "General Industry Safety Orders", and 41 CFR, Subpart B, "Public Contracts, General Safety and Health Standards."
The contractor shall also use the “BLM SAFETY AND HEALTH STANDARDS” (The Yellow Book) for reference.
Should the contractor fail to comply with any of these standards and regulations, the contractor shall be found to have defaulted on the terms of the contract.
Contingency Plan:
Sudden or unusual events could result in a negative impact to the delivery / performance of these requirements.
As an aid to properly plan for such events, the Contractor shall prepare and submit for approval a Contingency Plan for each Place of Performance for these requirements.
The Contractor will outline in detail the method(s) that the Contractor shall use in meeting Contract requirements in the following circumstances:
· a natural disaster occurs which impacts upon the Contractor's ability to perform
· a labor strike occurs which impacts upon the Contractor's ability to perform.
· a hazardous materials spill which impacts the Contractor’s ability to perform or which may affects public safety
· an incident which causes major damage which impacts the Contractor's ability to perform
· other unforeseen circumstances
In all cases, the Contractor will assume that the government cannot provide supplemental forces, and continues to need the same or additional performance under the Contract, which the Contractor must meet.
This Contingency Plan shall be submitted as a part of the Contractor proposal.
Emergency Response:
Response to emergency service calls outside of the normal business hours shall not exceed four (4) hours regardless of the time during the day or night, weekends or holidays.
Response to emergency service during normal business hours shall not exceed two (2) hours.
Response is defined as having all personnel and equipment required to correct an emergency at the site of the emergency or at a pre-approved staging area, ready, willing, and able to perform the emergency work. The Contractor will provide a draft emergency response plan prior to Contract start date.
Emergency Services:
On occasion, services may be required to support an activation or exercise of contingency plans outside the normal business hours described above. The Contractor's responsibilities for emergency support will be in accordance with the contingency plan.
Hazardous Materials and Hazardous Response:
The Contractor will conform to all Bureau, Federal, State, and local regulations in the use and disposal of hazardous materials and hazardous waste. The Contractor will provide the appropriate response to any emergency involving hazardous materials at any of the facilities covered by this Contract. The Contractor will provide proof/certification of personnel qualified to work with hazardous materials and wastes to the Bureau. The Contractor will notify the Bureau immediately upon discovering a release of hazardous waste into the environment.
Public contact:
Contractor personnel may encounter adjacent landowners or members of the public during the performance of their work.
Contractor personnel will present a professional appearance and be able to provide appropriate identification, including display of proper identification by each employee.
All Contractor and subcontractor personnel shall comply with all Federal and State laws relative to citizenship.
Contractor personnel shall inform any trespassers along the right of way of hazards and, as necessary and appropriate, ask trespassers to leave fenced off or restricted areas.
If Contractor personnel may encounter emergency personnel, policemen, or firemen along the right of way, the Contractor personnel shall notify the On-Site Foreman.
If Contractor personnel encounter the news media, they should refer all questions to the On-Site Foreman, who shall keep the COR informed of all news media contacts.
Government Observations:
Government personnel other than COR may from time to time observe, photograph, or otherwise record Contract operations.
However, these personnel will not interfere with Contractor performance.
Communications:
“Time” for communications received after 3:00pm, after 12:00 pm locally on Fridays, or after 12:00 pm locally prior to a holiday will not start until the next business day. All times are local Pacific Standard Time.
8.0 - Technical Exhibits and Definitions
Standard Definitions:
Physical Condition The Physical appearance of Federal equipment or facilities that considers cracks, chips, dents, abrasions, rust, corrosion, general cleanliness, vibration, operating temperature, and discoloration and other items as identified by the COR. Physical condition may be determined by visual as well as diagnostic means.
Contracting Officer (CO) The Secretary of the Interior or designated authorized representative who is the only agent capable of signing a federal award or obligating funds.
Contracting Officer’s Representative (COR) The Contracting Officer’s designated representative as indicated in a delegation of authority letter.
Quality Assurance (QA) Surveillance of Contractor performance to determine performance requirements are met.
Performance Requirements Summary (PRS) (see Technical Exhibit below) The PRS identifies the key performance indicators of the Contract that will be evaluated by the Government to assure Contract performance standards are met by the Contractor.
Quality Control Those actions taken by the Contractor to control the production of goods or services so that they meet the requirements of the performance work statement.
Technical Definitions:
Refer to Appendix A for definitions and specifications for various roads treatments.
Figure 1: Prosper Ridge Road Treatment Sites Statement of Work Prosper Ridge Road Culvert Replacement Project
SOW Page 5
Appendix A
STANDARD DETAILS AND SPECIFICATIONS
Schematics for Typical Treatments Specified in the Scope of Work
From:
Handbook for Forest, Ranch & Rural Roads Pacific Watershed Associates 2014
Available online at:
https://www.pacificwatershed.com/roadshandbook image1.jpeg image2.emf image3.emf image4.emf image5.emf image6.emf image7.emf image8.emf image9.emf image10.emf image11.emf image12.emf image13.emf