Bid Schedule Lower Suwanee TOWER DESIGN- BUILD 2021
| 1 | DESIGN | Hourly rate | Hours | Total | |
| PROJECT MANAGEMENT | |||||
| Principal | $0.00 | 0 | $0.00 | ||
| Clerical | $0.00 | 0 | $0.00 | ||
| Project Manager | $0.00 | 0 | $0.00 | $0.00 | |
| SITE ASSESSMENT | |||||
| Project Manager | $0.00 | 0 | $0.00 | ||
| Engineer | $0.00 | 0 | $0.00 | ||
| TRAVEL | $0.00 | $0.00 | |||
| GEOTECHNICAL REVIEW | |||||
| Project Manager | $0.00 | 0 | $0.00 | ||
| Soils Engineer | $0.00 | 0 | $0.00 | $0.00 | |
| ANALYSIS AND REPORT | |||||
| Project Manager | $0.00 | 0 | $0.00 | ||
| Sr. Structural Engineer | $0.00 | 0 | $0.00 | ||
| Soils Engineer | $0.00 | 0 | $0.00 | ||
| CAD/GIS | $0.00 | 0 | $0.00 | ||
| Clerical | $0.00 | 0 | $0.00 | $0.00 | |
| DRAWINGS & SPECIFICATIONS | |||||
| Project Manager | $0.00 | 0 | $0.00 | ||
| Sr. Structural Engineer | $0.00 | 0 | $0.00 | ||
| CAD Technician | $0.00 | 0 | $0.00 | ||
| Clerical | $0.00 | 0 | $0.00 | $0.00 |
| SUBTOTAL | $0.00 | |||
| Reimbursible costs | ||||
| DESIGN | TOTAL | $0.00 | ||
| BUILD | Lump Sum | |||
| Hardware, Structure, Anchors | $0.00 | |||
| Freight | $0.00 | |||
| Mobilization | $0.00 | |||
| Foundation | $0.00 | |||
| Bonding | $0.00 | |||
| Cabinet Installation | $0.00 | |||
| Ice Bridge Installation | $0.00 | |||
| Tower Installation | $0.00 | |||
| Site Conditions | $0.00 | |||
| Remove Existing Tower | $0.00 | |||
| 3% Bond | 3.00% | $0 | $0.00 | |
| Suwanee and State Tax Materials | 8.00% | $0 | $0.00 | |
| BUILD | TOTAL | $0.00 | ||
| TOTAL CONTRACT | $0.00 |