B08__A2_Specifications.pdf

PDF 5 MB Posted

Attached to
Menagers Dam Construction Federal contract opportunity
Solicitation number
140A1624R0014
Issued by
Department of the Interior Bureau of Indian Affairs Central Office

About this file

This document contains the specifications and payment details for the Menager's Dam Modification Design project, which is being solicited by the Department of the Interior Bureau of Indian Affairs.

The project includes installing a cofferdam to protect the work, procuring and storing construction water, excavating and demolishing existing structures, abandoning an existing tunnel, constructing access roads, performing a geotechnical investigation, developing a rockfill borrow area, constructing a zoned rockfill embankment, a new outlet works, an early warning system building, and other incidental work. The specifications provide details on the general construction sequence, project milestones, project management requirements, and quality control and quality assurance testing. The payment provisions outline the lump sum and unit price pay items, the schedule of values, and procedures for progress payments and final payment.

View the file

Other files for this federal contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MENAGER’S DAM MODIFICATION DESIGN

PROJECT SPECIFICATIONS

ISSUED FOR BID

ALI CHUK, TOHONO O’ODHAM NATION, ARIZONA

BY: _______________________________

ENGINEER: ERIC M. HAHN, P.E.

RJH CONSULTANTS, INC.

9800 MT. PYRAMID COURT, SUITE 330

ENGLEWOOD, COLORADO 80112

THIS PAGE LEFT INTENTIONALLY BLANK

1 TABLE OF CONTENTS

MENAGER’S DAM MODIFICATION DESIGN PROJECT

ISSUED FOR BID

OCTOBER 2023

SPECIFICATION INDEX

Section Title Number of Pages

DIVISION 0 – CONTRACT

DIVISION 1 – GENERAL REQUIREMENTS

01 11 00 Summary of Work 1 01 29 00 Payment Procedures 10 01 31 00 Project Management and Coordination 5 01 32 00 Construction Progress Documentation 5 01 33 00 Submittal Procedures 7 01 42 00 References 3 01 45 00 Quality Control 5 01 50 00 Temporary Facilities and Controls 7 01 53 00 Reservoir Control 3 01 55 26 Traffic Control 2 01 57 50 Project Permits and Environmental Controls 4 01 71 23 Layout of Work and Quantity Surveys 3 01 77 00 Project Closeout 2

DIVISION 2 – EXISTING CONDITIONS

02 32 00 Geotechnical Investigation 5 02 41 00 Demolition 1

DIVISION 3 – CONCRETE

03 01 30 Maintenance of Concrete 3 03 11 00 Concrete Forming 3 03 15 00 Concrete Accessories 3 03 20 00 Concrete Reinforcing 3 03 30 00 Cast-In-Place Concrete 7 03 30 50 Basic Concrete Materials 9 03 35 00 Concrete Finishing 4 03 62 00 Non-Shrink Grout 5

DIVISION 4 – MASONRY

DIVISION NOT USED

DIVISION 5 – METALS

05 12 00 Structural Steel and Miscellaneous 8 05 51 33 Metal Stairs and Ladders 1 05 52 50 Handrail 3 05 53 00 Metal Gratings 3

DIVISION 6 – WOOD, PLASTICS, AND COMPOSITES

DIVISION NOT USED

2 TABLE OF CONTENTS

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

DIVISION 8 – OPENINGS

08 11 00 Metal Doors and Frames 2 08 31 00 Access Doors and Panels 3 08 90 00 Louvers and Vents 5

DIVISION 9 – FINISHES

09 90 00 Painting and Coating 8

DIVISION 10 – SPECIALTIES

DIVISION NOT USED

DIVISION 13 – SPECIAL CONSTRUCTION

13 50 00 Measurements and Control Instrumentation 3

DIVISION 22 – PLUMBING

DIVISION NOT USED

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

DIVISION NOT USED

DIVISION 26 – ELECTRICAL

DIVISION NOT USED

DIVISION 31 – EARTHWORK

31 01 01 Site Restoration and Cleanup 2 31 05 19 Geosynthetics 7 31 11 00 Site Preparation 2 31 23 13 Subgrade Preparation 5 31 23 16 Excavation 22 31 23 19 Dewatering 4 31 23 23 Fill 20 31 25 00 Erosion and Sedimentation Controls 3 31 37 00 Riprap 3

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 15 00 Aggregate Surfacing 2 32 31 13 Chain Link Fences and Gates 4 32 34 00 Fabricated Bridges 4 32 96 33 Transplanting 2

3 TABLE OF CONTENTS

DIVISION 33 – UTILITIES

33 11 01 Welded Steel Pipe and Fittings 10 33 11 03 Polyvinyl Chloride (PVC) Pipe 2

DIVISION 34 – TRANSPORTATION

DIVISION NOT USED

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

35 20 13 Hydraulic Fabrications 5 35 20 16 Water Control Gates 5

DIVISION 41 – MATERIAL PROCESSING AND HANDLING EQUIPMENT

20113/MENAGER’S DAM MODIFICATION ISSUED FOR BID

01 11 00 1 SUMMARY OF WORK

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 GENERAL

A. The work described in these specifications includes the following general items:

1. Installing a cofferdam to protect the work.

2. Procuring construction water and storing construction water on-site.

3. Excavating the existing dam and alluvial materials and stockpiling materials for reuse.

4. Demolishing existing concrete structures.

5. Abandoning the existing tunnel by grouting the outlet.

6. Constructing temporary and permanent access roads.

7. Performing a geotechnical investigation of the rockfill borrow area.

8. Performing excavation, blasting, and processing to produce rockfill materials.

9. Installing and testing a rockfill test section.

10. Importing filler and drain materials.

11. Constructing a zoned rockfill embankment with earthfill core. The embankment will include internal transition and drainage zones, geotextiles, and instrumentation.

12. Constructing a new outlet works along the right side of the dam. The outlet works will include an intake structure, discharge pipe, and impact basin.

13. Constructing an early warning system building.

14. Relocating cacti to accommodate construction of the work.

15. Complying with environmental and other required permits.

16. Removing the cofferdam and reclaiming the site.

17. Implementing a two-week work shutdown in July and/or August for Tribal holiday.

18. Other incidentals not listed above.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

NOT USED

END OF SECTION

01 29 00 1 PAYMENT PROCEDURES

SECTION 01 29 00

PAYMENT PROCEDURES

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Measurement and payment criteria applicable to portions of the Work performed under a unit price payment method.

B. Measurement and payment criteria applicable to portions of the Work performed under a lump sum payment method.

1.2 SUBMITTALS

A. Administrative Submittals

1. Schedule of Values.

2. Monthly Payment Application.

3. Final Payment Application.

1.3 MEASUREMENT OF QUANTITIES

A. Measurement by Volume - Measured by cubic dimension using mean length, width, and height or thickness. Unless specified otherwise, volumes shall be computed using the average-end-area method with cross sections surveyed at maximum 25-foot spacing. On curved alignments, volume computations shall utilize the length between the centroid of each area at adjacent cross sections rather than the nominal cross section spacing along the alignment.

1. Measurement for placement, installation, and backfilling of materials will be in place after Work. Measurement will be made from the limit of the neat lines shown on the Drawings or to the approved limits of excavation.

B. Measurement by Area - Measured by square dimension using mean length and width or radius.

C. Linear Measurement - Measured by linear dimension at the item centerline or mean chord, and shall be based on a horizontal projection of the actual area installed except where specified as a vertical measurement.

D. Surveys for measurement shall be in accordance with the requirements of Section 01 71

23: LAYOUT OF WORK AND QUANTITY SURVEYS.

E. Round to the nearest whole unit for pay quantities.

1.4 GENERAL PAYMENT

A. Payment under the lump sum work line item shall cover all Work not included in the unit price items of Work.

B. Separate payment will not be made for excavation except where specifically included as pay items. All other excavation is considered incidental to other items of Work.

01 29 00 2 PAYMENT PROCEDURES

C. Separate payment will not be made for preparation of foundation or subgrade surfaces except where specifically included as pay item. All other foundation preparation is considered incidental to other items of Work.

D. No payment will be made because of foundation or embankment settlement.

E. CONTRACTOR shall furnish all submittals, equipment, labor, and material required for complete construction of pay items. Including any incidental items.

F. Separate payment will not be made for procuring construction water or on-site storage of construction water. Procuring and storing construction water is considered incidental to other items of the Work.

G. Separate payment will not be made for installation of an on-site concrete batch plant. This is considered incidental to other items of work.

1.5 PAYMENT FOR UNIT PRICE ITEMS

A. Unit Price Work:

1. Reflect unit price quantity and price breakdown from the Bid Form.

2. Estimated quantities shown on the Bid Form are approximate and are given only for a comparison of bids. CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE does not either expressly or by implication warrant that the actual quantities will correspond to the estimated quantities.

CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE reserves the right to increase or decrease the amount of work performed under unit price items, or to omit work altogether. No adjustments in contract unit prices will be made.

B. Final payment for Work governed by unit prices will be made on the basis of the actual measurements and quantities accepted by the CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE, multiplied by the unit price for Work that is incorporated in or made necessary by the Work.

1.6 PAYMENT FOR LUMP SUM ITEMS

A. Payment for lump sum Work shall be made in accordance with the accepted schedule of values.

B. An unbalanced or front-end loaded schedule will not be acceptable.

C. Mobilization and demobilization shall not exceed 7 percent of the total original contract amount (at the time of award). Payment for mobilization and demobilization shall be made as follows:

1. When 5 percent of the total original contract amount is earned from other pay items, 50 percent of the amount bid for mobilization and demobilization will be paid.

2. When 10 percent of the total original contract amount is earned from other pay items, 90 percent of the amount bid for mobilization and demobilization will be paid, exclusive of any amount already paid for previous progress payment.

3. When the CONTRACTOR has demobilized from the site, the balance of the amount bid for mobilization and demobilization will be paid.

1.7 SCHEDULE OF VALUES

A. Provide breakdown of the lump sum pay item to facilitate review of progress payments.

01 29 00 3 PAYMENT PROCEDURES

1. List Bonds and insurance premiums, mobilization, demobilization, facility startup, and contract closeout separately.

2. As a minimum, break down into the following separate pay items:

a. Mobilization and Demobilization

1) Mobilization

2) Demobilization

b. Surveying

1) Pre-Construction Survey

2) Quantity Surveys

3) As-Built Survey

c. Ancillary Work, Bonds and Insurance, and Contract Administration

1) Bonds and Insurance

2) Submittals

3) Contract Administration

4) Quality Control

5) Project closeout

6) Construction water storage facilities

7) All other items that the CONTRACTOR deems appropriate.

d. Demolition and Abandonment

1) Demolition

2) Abandonment of existing tunnel

e. Reservoir Control

1) Design and Installation

2) Operation

3) Removal

f. Geotechnical Investigation – Rockfill Borrow Area

1) Drilling Plan

2) Drilling and Geophysical Survey

3) Laboratory Testing

4) Geotechnical Data Report

g. Rockfill Test Section

1) Rockfill Test Plan

2) Installation and surveying

3) Removal

h. Site Access Road

1) Excavation and grading

2) Aggregate surfacing

3) Low-level concrete crossing

i. Dam Crest Access Road

1) Excavation and grading

01 29 00 4 PAYMENT PROCEDURES

2) Aggregate surfacing

3) Water bars

j. Outlet Works Intake Structure

1) Excavation

2) Reinforced Concrete

3) Trashracks

4) Miscellaneous metals

k. Concrete encased 36-inch diameter steel pipe

1) Excavation

2) Reinforced Concrete

3) Steel pipe

l. Outlet Works Impact Basin and Riprap Apron

1) Excavation

2) Reinforced Concrete

3) Riprap and geotextile

m. Instrumentation

1) Concrete building

2) Staff gage

3) EWS conduits

4) Survey monuments

B. Submit on CONTRACTOR’s standard form.

1.8 PROGRESS PAYMENTS

A. Progress payments will be made monthly.

B. Include accepted schedule of values for each portion of Work and the unit price breakdown for Work to be paid on unit price basis, and allowances.

C. Preparation:

1. Round values to the nearest dollar.

2. List each Change Order and Written Amendment executed prior to date of payment request as separate line items.

1.9 PARTIAL PAYMENT FOR UNDELIVERED, PROJECT-SPECIFIC MANUFACTURED OR

FABRICATED EQUIPMENT

A. Notwithstanding the above provisions, partial payments for undelivered (not delivered to the site or stored on the vicinity of the site) equipment or products specifically manufactured for this Project, excluding off the shelf or catalog items, will be made when the following conditions are met:

1. Partial payment request is supported by written acknowledgment from Suppliers that invoice requirements have been met.

2. Equipment or product is adequately insured, maintained, stored, and protected.

3. Each equipment or product item is clearly marked and segregated from other items to permit inventory and accountability.

01 29 00 5 PAYMENT PROCEDURES

4. Authorization has been provided for access to storage site for CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE.

5. Equipment or product meets applicable Specifications requirements.

1.10 NONPAYMENT FOR REJECTED OR UNUSED PRODUCTS

A. Payment will not be made for the following:

1. Loading, hauling, and disposing of rejected material.

2. Quantities of material wasted or disposed of in a manner not called for under the

Contract Documents.

3. Rejected loads of material, including material rejected after it has been placed for failure to conform to provisions of the Contract Documents.

4. Material not unloaded from the transporting vehicle.

5. Defective Work not accepted by the CONTRACTING OFFICER or

CONTRACTING OFFICER’S REPRESENTATIVE.

6. Material remaining on hand after completion of the Work.

20113/MENAGER’S DAM MODIFICATION 90 PERCENT DESIGN

01 29 00 6 PAYMENT PROCEDURES

Listing of Pay Items

Item

Unit of Measure

General Description of Work Included Measurement and Payment Terms

1 Mobilization and Demobilization

Lump Sum

Preparatory work and operations including but not limited to obtaining permits; moving equipment, supplies, and incidentals to the site;

establishing field offices; installing temporary utilities; and having superintendent at Site fulltime. Demobilization including removal of all equipment, materials, field offices, and temporary works.

Measurement will be based on procedures described in Paragraph 1.6.

2 Surveying Lump Sum

All required surveys including: pre-construction survey, quantity surveys for progress payments, as-built survey and others required in these specifications.

Measurement will be lump sum prorated over duration of this item of Work based on the accepted schedule of values.

3 Erosion and Sediment Control

Lump Sum

Furnishing, installing, and maintaining erosion control protection facilities in accordance with the drawings and applicable permit requirements.

Measurement will be lump sum prorated over duration of this item of Work based on the accepted schedule of values.

4 Clearing and Grubbing

Lump Sum

Removing and disposing vegetation and debris from the Work area. Measurement will be lump sum complete in-place.

5 Demolition Lump Sum

Demolishing the existing concrete intake structure, concrete diversion structure, concrete stilling basin, and 8-inch diameter corrugated metal pipe. Disposing demolished materials at an off-site disposal area or landfill.

Measurement will be lump sum complete in-place.

6 Abandonment Lump Sum

Procuring and installing grout and PVC drain pipe at existing tunnel. Measurement will be lump sum complete in place.

7 Construction Dewatering

Lump Sum

Designing, furnishing, installing, and maintaining dewatering facilities to control the water in required excavations.

Measurement will be lump sum prorated over duration of this item of Work based on the accepted schedule of values.

8 Reservoir Control

Lump Sum

Designing, furnishing, installing, maintaining, and removing necessary facilities including cofferdam, pipes, and pumps as needed to manage reservoir levels.

Measurement will be lump sum prorated over duration of this item of Work based on the accepted schedule of values.

9 Excavation Unclassified

Cubic Yard

Excavating the existing embankment and alluvium, segregating and stockpiling excavated materials for reuse, and disposing excess excavated materials in reservoir basin. No payment will be made for backfilling over-excavations.

Measurement will be based on the volume between the pre-construction survey and the surveyed bottom of excavation before core trench excavation.

01 29 00 7 PAYMENT PROCEDURES

Measure

General Description of Work Included Measurement and Payment Terms

10 Excavation Bedrock

Cubic Yard

Excavating bedrock materials for the core trench, embankment, and outlet works, and disposing excavated materials. No payment will be made for backfilling over-excavations.

Measurement will be based on the volume between the surveyed bottom of excavation before core trench excavation and the surveyed bottom of the core trench excavation.

11 Foundation Preparation - Core Trench

Lump Sum

Cleaning the limit of core trench excavation to remove all loose material and using mechanical brooms, hand shovels and brooms, or pressurized air or water. Furnishing and placing slush grout and dental concrete.

Measurement will be lump sum complete in-place.

12 Geotechnical Investigation - Rockfill Borrow Area

Lump Sum

Perform and submit the preconstruction geotechnical investigation of the rockfill borrow area.

Measurement will be lump sum based on the accepted schedule of values.

13 Rockfill Test Section

Lump Sum

Excavating materials from rockfill borrow area, processing, hauling, constructing test section, compacting, surveying, and demolishing.

Measurement will be lump sum based on the accepted schedule of values.

14 Zone 1 - Earthfill Cubic Yard

Hauling from stockpiles, placing, spreading, compacting, and quality control.

Measurement will be based on the volume in-place after compaction between the neat lines.

15 Zone 2A - Rockfill

Cubic Yard

Blasting and excavating from rockfill borrow area, processing, hauling, stockpiling, subgrade preparation, conditioning, placing, spreading, compacting, and quality control.

Measurement will be based on the volume in-place after compaction between the neat lines.

16 Zone 2B - Rockfill

Cubic Yard

Importing materials or blasting and excavating from rockfill borrow area, processing, hauling, stockpiling, subgrade preparation, conditioning, placing, compacting, and quality control.

Measurement will be based on the volume in-place after compaction between the neat lines.

17 Zone 2C - Rockfill

Cubic Yard

Importing materials or blasting and excavating from rockfill borrow area, processing, hauling, stockpiling, subgrade preparation, conditioning, placing, compacting, and quality control.

Measurement will be based on the volume in-place after compaction between the neat lines.

18 Zone 3 - Fine Filter

Cubic Yard

Importing, hauling, subgrade preparation, conditioning, placing, compacting, and quality control.

Measurement will be based on the volume in-place after compaction between the neat lines.

19 Zone 4 - Coarse Filter

Cubic Yard

Importing or blasting and excavating from rockfill borrow area and processing, hauling, subgrade preparation, conditioning, placing, compacting, and quality control. This material can either be imported or produced from the rockfill borrow area.

Measurement will be based on the volume in-place after compaction between the neat lines.

01 29 00 8 PAYMENT PROCEDURES

Measure

General Description of Work Included Measurement and Payment Terms

20 Random Fill Cubic Yard

Hauling from stockpiles, blending, subgrade preparation, placing, conditioning, compacting, and quality control.

Measurement will be based on the volume in-place after compaction between the neat lines.

21 Geotextile - Embankment

Square Yard

Furnishing, placing, and seaming geotextile in the embankment. Measurement will be based on the slope area of geotextile in place. No extra payment will be made of seamed or overlap areas.

22 Site Access Road

Lump Sum

Excavating, grading, placing aggregate surfacing, maintaining during construction; and placing and grading aggregate base as needed at the end of construction.

Measurement will be lump sum based on the accepted schedule of values and paid at 80 percent and 20 percent when construction complete.

23 Dam Crest Access Road

Lump Sum

Excavating, grading, placing aggregate surfacing, installing concrete water bars, maintaining during construction; and placing and grading aggregate base as needed at the end of construction. Includes aggregate surfacing along dam crest.

Measurement will be lump sum based on the accepted schedule of values and paid at 80 percent and 20 percent when construction complete.

24 Chain Link Fence and Gate

Lump Sum

Installing chain link gate and fence, concrete, and all required components.

Measurement will be lump sum complete in-place.

25 Outlet Works Intake Structure

Lump Sum

Subgrade preparation, grading, concrete, reinforcing steel, formwork, curing, embeds, backfill concrete, steel grating, wall thimbles, access hatch, steel bulkheads and accessories, trashracks, miscellaneous metals, concrete finishing, all appurtenances and incidental items necessary for the complete construction, and quality control.

Measurement will be lump sum based on the accepted schedule of values.

26 Access Bridge and Abutment

Lump Sum

Excavation, excavation support, subgrade preparation, grading, concrete, reinforcing steel, formwork, curing, embeds, engineering design, prefabricated bridge, steel bridge deck, ancillary equipment, all appurtenances and incidental items necessary for the complete construction, and quality control.

Measurement will be lump sum based on the accepted schedule of values.

27 Water Control Gates

Lump Sum

Procuring, furnishing, and installing the slide gates in the intake structure.

Measurement will be lump sum based on the accepted schedule of values.

28 Concrete Encased 36-inch Steel Pipe

Lump Sum

Subgrade preparation, grading, steel pipe, coatings, linings, specials, welding, testing, reinforcing steel, formwork, curing, concrete, concrete finishing, air vent and all appurtenances and incidental items necessary for the complete construction.

Measurement will be lump sum based on the accepted schedule of values.

01 29 00 9 PAYMENT PROCEDURES

Measure

General Description of Work Included Measurement and Payment Terms

29 Outlet Works Impact Basin and Riprap Apron

Lump Sum

Subgrade preparation, grading, concrete, reinforcing steel, formwork, curing, embeds, concrete finishing, grating, riprap, geotextile, all incidental items necessary for the complete construction, and quality control.

Measurement will be lump sum based on the accepted schedule of values.

30 Instrumentation Lump Sum

Embankment monitoring points, structural monitoring points, staff gage, stilling well, conduits for Early Warning System instrumentation, and reinforced concrete Early Warning System building.

Measurement will be lump sum based on the accepted schedule of values.

31 Cacti Transplanting

Lump Sum

Transplanting existing cacti and maintaining transplanted cacti until substantial completion.

Measurement will be lump sum complete and prorated over duration of project based on the accepted construction schedule.

32 Site Reclamation

Lump Sum

Finish grading. Measurement will be lump sum complete in-place.

33 Ancillary Work, Bonds and Insurance, Contract Administration

Lump Sum

Ancillary project work not included in other pay items; contract administrative tasks including but not limited to project management and accounting; securing bonds and insurance; preparation of submittals; resubmittals as necessary; site security; and implementing a two-week shutdown.

Measurement will be lump sum complete and prorated over duration of project based on the accepted construction schedule.

01 29-00 10 PAYMENT PROCEDURES

PART 2 PRODUCTS

PART 3 EXECUTION

01 31 00 1 PROJECT MANAGEMENT

AND COORDINATION

SECTION 01 31 00

PROJECT MANAGEMENT AND COORDINATION

PART 1 GENERAL

1.1 WORK INCLUDES

A. Project Management

B. Project Meetings

C. Coordination

D. Requests for Information

1.2 SUBMITTALS

A. Administrative:

1. CONTRACTOR’s water usage plan. Indicate CONTRACTOR’s source, storage, and peak daily water demands for the Work.

2. Complete list of subconsultants and contact information.

1.3 CONTRACTOR FURNISHED ITEMS

A. Construction Water

1. Non-potable water for construction of the Work can be obtained from the following sources:

a. Reservoir if available.

b. Kerwo Intertie water system well No. 3 located 15 miles north of site.

c. Off-site source identified by the CONTRACTOR.

B. Utilities

1. CONTRACTOR is responsible for electrical, telephone, and high-speed internet services for the CONTRACTOR’s and CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE’s use.

1.4 PROJECT MEETINGS

A. CONTRACTOR will schedule project meetings, prepare meeting agenda with participant input, preside at meetings, record meeting minutes to include significant proceedings and decisions, and distribute meeting minutes within 5 business days after meeting.

B. Preconstruction Conference

1. Prior to starting Work at the site, meet with CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE to discuss the following items:

a. Project schedule.

b. Bonds and insurance.

c. Project permits.

d. Administrative procedures.

01 31 00 2 PROJECT MANAGEMENT

1) Submittals

2) Progress payments

3) Changes in the Work

4) Weekly progress meetings

e. Construction sequence.

f. Quality control and testing.

g. Site safety.

h. Site access, security, and temporary facilities.

i. CONTRACTING OFFICER OR CONTRACTING OFFICER’S

REPRESENTATIVE authority and responsibilities.

j. CONTRACTOR authority and responsibilities.

2. The Preconstruction conference shall be attended by the following people:

a. CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE (attendance mandatory).

b. CONTRACTOR’s office representative (attendance mandatory).

c. CONTRACTOR’s resident superintendent (attendance mandatory).

d. CONTRACTOR’s safety representative (attendance mandatory).

e. Subcontractors whom CONTRACTOR, CONTRACTING OFFICER or

CONTRACTING OFFICER’S REPRESENTATIVE request to attend.

f. Others as appropriate.

C. Progress Meetings

1. Meet with CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE at the job site once a week during construction to discuss Work progress. Location and time of meeting shall be coordinated at the preconstruction conference. CONTRACTOR shall give verbal reports of the following items:

a. Progress of construction.

b. Project schedule, including a detailed projection of activities for the next 2 weeks.

c. Status of submittals.

d. Status of progress payments.

e. Any conflicts, discrepancies, or other difficulties requiring resolution.

2. The progress meetings shall be attended by the following people:

a. CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE (attendance mandatory).

b. CONTRACTOR’s resident superintendent (attendance mandatory).

c. Subcontractors whom CONTRACTOR, CONTRACTING OFFICER or

CONTRACTING OFFICER’S REPRESENTATIVE request to attend.

d. Others as appropriate.

D. Special Meetings

1. Meet with CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE, when requested, to discuss technical issues, construction planning, construction schedule, and contract administration. Meetings shall be scheduled at least 2 weeks before the scheduled start of the activity. At a minimum special meetings shall be held prior to the following activities:

a. Dam foundation excavation and foundation preparation

01 31 00 3 PROJECT MANAGEMENT

b. Geotechnical investigation for rockfill borrow area

c. Development of rockfill borrow area

d. Rockfill test section

e. Concrete placement

f. Embankment construction

2. Special meetings shall be attended by the following people:

a. CONTRACTOR’s resident superintendent (attendance mandatory).

b. CONTRACTING OFFICER or CONTRACTING OFFICER’S

REPRESENTATIVE (attendance mandatory).

c. Others as appropriate.

1.5 CONSTRUCTION SEQUENCE

A. General construction sequence for key project components:

1. Mobilize to the site.

2. Construct the site access road.

3. Construct on-site water storage facility for construction water.

4. Procure construction water and store water on-site.

5. Design and construct the cofferdam and other reservoir control facilities.

6. Perform cacti mitigation.

7. Perform a geotechnical investigation of the rockfill borrow area. CONTRACTING

OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE will evaluate if engineering properties are acceptable.

8. Quarry, process, and stockpile the rockfill material.

9. Perform excavation required for outlet works.

10. Construct the outlet works.

11. Perform excavation required for embankment. Stockpile material for reuse.

12. Construct test section for rockfill.

13. Construct the embankment.

14. Construct the dam crest access road.

15. Remove cofferdam and ancillary facilities.

16. Perform site reclamation activities.

17. Demobilize from the site.

1.6 PROJECT MILESTONES

A. Geotechnical investigation for rockfill borrow area.

B. Construction of outlet works

C. Construction of embankment

D. Substantial completion

E. Final completion

1.7 UTILITY NOTIFICATION

A. Coordinate Work with Tohono O’odham Nation utility authority. Notify prior to commencing Work, if damage occurs, or if conflicts or emergencies arise during Work.

01 31 00 4 PROJECT MANAGEMENT

1.8 REGULATORY

A. Approved Plans and Specifications shall not be materially changed without the prior written approval of the CONTRACTING OFFICER or CONTRACTING OFFICER’S

REPRESENTATIVE.

1.9 REQUEST FOR INFORMATION

A. Submit questions and requests for clarifications to CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE using the Request for Information (RFI) form attached at the end of this Section. RFIs shall be used for clarification of information provided in the Specifications or shown on the Drawings, and to request substitutions for materials or methods.

1.10 WORK SHUTDOWN

A. Work will be halted for a two-week period in July and/or August for Tribal holiday.

Coordinate dates with CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE. No CONTRACTOR personnel will be allowed on site during this period. CONTRACTOR may leave equipment on site.

1.11 TRIBAL MONITORS

A. CONTRACTOR shall hire two monitors from the Tribal Historical Preservation Office to observe all construction activities. All associated coordination and payment is the responsibility of the CONTRACTOR. Point of contact is Peter Steere: 520-383-3622.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

01 31 00 5 PROJECT MANAGEMENT

Project Name RFI Number:

Date:

To: ________________________________ From: _____________________________

SUBJECT:

SPECIFICATION SECTION:

DRAWING NUMBER:

QUESTION:

WRITTEN BY: _____________________________ DATE: _________________________

ATTACHMENTS: __________________________________________________________________

RESPONSE:

WRITTEN BY: _____________________________ DATE: _________________________

ATTACHMENTS: __________________________________________________________________

CONTRACTOR ACCEPTANCE: ________________________________________________________

TITLE: ________________________________________ DATE: _________________________

01 32 00 1 CONSTRUCTION PROGRESS

DOCUMENTATION

SECTION 01 32 00

CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 GENERAL

1.1 DEFINITIONS

A. Critical Path Method – Critical path method (CPM) shall be interpreted to be generally as outlined in the Association of General Contractors (AGC) publication. “The Use of CPM in Construction.” except that either “i-j” arrow diagrams or precedence diagramming format may be utilized.

B. Construction Schedules – Construction schedules shall include a bar chart, graphic network diagrams, and computerized construction schedule reports.

C. CPM Network – CPM network shall be in a form of a time scaled “i-j” activity-on-arrow or precedence type diagram and may be divided into a number of separate sheets with suitable match lines relating the interface points among the sheets. Individual sheets shall not exceed 22- by 34-inch.

D. Duration Estimates – The duration estimate indicated for each activity shall be computed in days and shall represent the single best estimate considering the scope of the activity work and resources planned for the activity. Except for certain non-labor activities such as curing of concrete or delivery of materials, activity duration shall not exceed 30 days nor less than one day unless otherwise accepted by CONTRACTING OFFICER or

CONTRACTING OFFICER’S REPRESENTATIVE.

E. Float – Unless otherwise provided herein, float as referenced in these documents is total float. Total float is a period of time measured by the number of days each non-critical path activity may be delayed before it and its succeeding activities become part of the critical path. If a non-critical path activity is delayed beyond its float period, that activity then becomes part of the critical path and controls the end date of the project.

F. Float Ownership – Neither CONTRACTING OFFICER nor CONTRACTOR owns the float time. The project owns the float time. As such, liability for delay of the project completion date rests with the party actually causing delay to the project completion date. For example, if Party A uses some, but not all, of the float time and Party B later uses the remainder of the float time as well as additional time beyond the float time, Party B shall be liable for the costs associated with the time that represents delay to the project’s completion date. Party A would not be responsible for any costs since it did not consume all of the float time and additional float time remained; therefore, the project’s completion date was unaffected.

1.2 SUBMITTALS

A. Administrative:

1. Preliminary Progress Schedule.

2. CPM Schedule.

3. Updated CPM Schedules.

4. Final CPM Schedule.

5. Construction Photographs.

6. Video Recordings.

01 32 00 2 CONSTRUCTION PROGRESS

1.3 CPM SCHEDULE

A. A time-scaled network diagram of the “i-j” activity-on-arrow or precedence type. The network diagram shall describe the activities to be accomplished and their logical relationships and show the critical path. The schedule shall include, as a minimum, the following items:

1. Mobilization

2. Submittals

3. Initial site work.

4. Temporary facilities and erosion control.

5. Cacti mitigation.

6. Cofferdam and stream diversion.

7. Demolition of concrete structures.

8. Excavation of existing embankment and alluvial materials.

9. Site access road.

10. Dam crest access road.

11. Rockfill borrow area geotechnical investigation.

12. Outlet works excavation.

13. Intake structure construction.

14. Dam foundation excavation.

15. Foundation preparation of core trench.

16. Rockfill materials development.

17. Rockfill test section.

18. Embankment construction.

19. Access bridge installation.

20. Concrete encased steel pipe installation.

21. Impact basin construction.

22. Slide gate installation.

23. Early warning system building.

24. Site reclamation and closeout.

25. Demobilization.

B. The schedule shall contain sufficient detail and information to cost load the CPM schedule in accordance with the schedule of values. Each construction activity shall have been cost loaded as specified.

C. The schedule shall include the number of shifts, length of shift, production rates for concrete conduits and embankment placement, and number of days worked per week.

D. Submission of CONTRACTOR’s CPM schedule to CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE shall not relieve CONTRACTOR of total responsibility for scheduling and sequencing the Work.

1.4 UPDATED CPM SCHEDULE

A. A revised CPM schedule shall be submitted monthly with the payment request. Failure to include the updated schedule will cause CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE to withhold the monthly progress payment.

B. Each schedule update submitted must be complete, including all information requested in the original CPM schedule submittal. In addition, the updated submittal shall include the following information:

1. Delays in submittals, resubmittals, or deliveries.

2. Changes in the sequences of Work.

3. Revisions to durations and completion dates.

01 32 00 3 CONSTRUCTION PROGRESS

4. Changes in the number or length of shifts, or changes in the number of days worked per week.

C. Each update shall continue to show all Work activities including those already completed.

These completed activities shall reflect the “as built” information by indicating when the Work was actually started and completed. The updated schedule should reflect actual construction progress, changes to the schedule as a result of Change Orders, construction delays, and other schedule impacts.

D. Changes or delays that do not affect the controlling operator or operations of the critical path will not be considered as a basis for a time adjustment. Changes or delays that do not affect the controlling operations or the critical path will be considered in granting an extension of time for completion of the contract only if the total float is absorbed by the delay.

E. If CONTRACTOR fails to complete activities that are on the critical path, then CONTRACTOR shall submit in writing a statement as to how CONTRACTOR intends to correct the deficiency and return the Work to an acceptable schedule.

1.5 FINAL CPM SCHEDULE

A. Submit a final CPM schedule that updates the CPM schedule to reflect actual construction progress.

1.6 SCHEDULE REPORTS (FORMAT)

A. Plot or print the schedule on 22- by 34-inch paper.

B. Project Information - Each Schedule Report shall be prefaced with the following summary data:

1. Project Name

2. CONTRACTOR

3. Type of Tabulation

4. Project Duration

5. Contract Completion Date (revised to reflect time extensions)

6. The Commencement Date Stated in the Notice to Proceed

7. The Data Date and Plot Date of the Network Diagram

8. If an update, cite the new schedule completion date

C. Schedule Reports - Schedule Reports shall be prepared based on the Construction Schedule, and shall include the following minimum data for each activity:

1. Activity Numbers and Responsibility Codes

2. Estimated Activity Duration

3. Activity Description

4. Activity’s Percent Completion

5. Early Start Date (Calendar Dated)

6. Early Finish Date (Calendar Dated)

7. Late Start Date (Calendar Dated)

8. Late Finish Date (Calendar Dated)

9. Status (Whether Critical)

10. Total Float for Each Activity

11. Free Float for Each Activity

12. Cost Value for Each Activity

01 32 00 4 CONSTRUCTION PROGRESS

1.7 PROJECT STATUS REPORTING

A. Provide monthly project status reports in the form of a written narrative report to be submitted in conjunction with the revised CPM Schedules.

B. Prepare monthly written narrative reports of the status of the project. Written status reports shall include:

1. Number of days worked, construction force, weather conditions, and list of equipment on site.

2. The status of major project components (percent complete, amount of time ahead or behind schedule).

3. The progress made on critical activities indicated on the CPM schedule.

4. The status of major material and equipment procurement.

5. Any delays encountered during the reporting period.

6. An assessment of delays encountered and impacts to the progress of the Work.

7. Changes in the Contract.

8. CONTRACTOR may include any other information pertinent to the status of the project. CONTRACTOR shall include additional status information requested by CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE.

1.8 CONSTRUCTION PHOTOGRAPHS

A. Photographically document all phases of construction including preconstruction, construction progress, and post construction.

B. CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE shall have the right to select the subject matter and vantage point from which photographs are to be taken.

C. Preconstruction and post construction:

1. Preconstruction photos shall be after the Effective Date of the Agreement but before Work begins at the site. Post construction photos shall be at the issuance of Substantial Completion.

2. Take a minimum of 72 exposures of the site and properties adjacent to the site and limits of disturbance. Photos for post construction shall be taken at the same vantage points as the Preconstruction photos.

D. Construction progress photos:

1. Demonstrate progress on construction.

2. Weekly: minimum of 24 exposures.

E. Format:

1. Digital Images

a. Submit on DVD or flash drive or as agreed to by CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE

b. Date stamp on all photos

2. Label each photo with the following:

a. Project name

b. Date

c. Description of photo

01 32 00 5 CONSTRUCTION PROGRESS

1.9 VIDEO RECORDINGS

A. Video recording of the existing condition of all areas within limits of site disturbance, properties adjacent to the limits of disturbance, and along BIA Route 1 near the turnoff to the site access road.

1.10 RECORD DRAWINGS

A. Provide and maintain at the project site, one complete set of prints of the project Drawings.

Keep the Drawings in good, clean, and readable condition.

B. Neatly inscribe on the project Drawings all changes in Work including relocation of lines, change in type of materials, etc. Note changes with red pencil or red ink. Note date of change. Note all data and changes on these record drawings in sufficient detail and clarity and provide information necessary for preparation of record drawings. Project Drawings shall be kept current and shall be updated weekly.

C. Review changes with CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE at monthly pay request submittal.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

01 33 00 1 SUBMITTAL PROCEDURES

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUBMITTAL PROCEDURES

A. The word "submittals" shall be interpreted to include Work plans or procedures, Drawings, shop drawings, schedules, data, manuals, certifications, test reports, curves, samples, brochures, and other items furnished by CONTRACTOR for approval, information, or other purposes.

B. Each submittal will be returned within fourteen (14) calendar days following receipt of submittal, unless otherwise indicated in the Specification section. Resubmittals shall be subject to the same review time.

C. Do not perform Work related to submittals prior to obtaining the required approval from

CONTRACTING OFFICER OR CONTRACTING OFFICER’S REPRESENTATIVE.

D. Utilize a 9-character submittal identification numbering system in the following manner:

1. The first five digits shall be the applicable Specification section number.

2. The next three digits shall be the numbers 001 to 999 to sequentially number each initial separate item or submittal under each specific section number.

3. The last character shall be a letter (A to Z) indicating the submission, or resubmission of the same Submittal, i.e., “A = 1st submission, B = 2nd submission (first resubmission), C = 3rd submission, etc. A typical submittal number would be as follows: 02617 - 008 - B.

E. Submittals will be reviewed no more than twice at CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE expense. Subsequent reviews will be performed by CONTRACTING OFFICER OR CONTRACTING OFFICER’S REPRESENTATIVE at CONTRACTOR’s expense. CONTRACTOR will be invoiced on a time and materials basis using the same hourly rates that are being charged to CONTRACTING OFFICER for engineering services. Invoice amounts will be deducted from amounts due, or to become due, to CONTRACTOR. Submittals are required until approved. Delays resulting from resubmittals will not entitle CONTRACTOR to a Contract Time extension or change in Contract Price.

F. If the items as submitted describe variations and show a departure from the Contract requirements which CONTRACTING OFFICER OR CONTRACTING OFFICER’S REPRESENTATIVE finds to be in the interest of CONTRACTING OFFICER and to be so minor as not to involve a change in Contract Price or Contract Time, CONTRACTING OFFICER OR CONTRACTING OFFICER’S REPRESENTATIVE may return the reviewed submittals without noting an exception.

G. Complete and submit a transmittal form with each submittal package. A copy of the form is attached at the end of this Section.

1.2 SUBMITTALS

A. Administrative:

1. Schedule of Submittal Submission: Submit 14 days after Notice to Proceed.

Include the following information:

01 33 00 2 SUBMITTAL PROCEDURES

a. List of submittals (group by Specification number)

b. Estimated submission date

c. Estimated start date for corresponding items of Work

1.3 SHOP DRAWINGS

A. Copies: Submit one electronic copy of shop drawings and product data.

B. Shop drawings are those submittals that reflect processes, layout, or method of construction. All shop drawing submittals shall contain the following information:

1. The date of submission and the dates of any previous submissions.

2. The project title and number.

3. The name of CONTRACTOR (and Subcontractor where applicable).

4. Identification of the items/submittal/product, with the Specification section number, page, and paragraph(s), and Drawing reference, if any.

5. Field dimensions, clearly identified as such.

6. Relation to adjacent or critical features of the Work or materials.

7. Design Data: show calculations, dimensions, logic, and assumptions upon which the design is based.

8. Applicable standards, such as ASTM, ANSI, or Federal Specification numbers.

9. Identification of deviations from Contract Documents.

10. Identification of revisions on resubmittals.

11. A blank space suitably sized for CONTRACTOR and CONTRACTOR’s engineer

(if necessary) stamps.

C. Prepare the submittal as follows:

1. Present in a clear and thorough manner. Include sufficient detail to show the kind, size, arrangement, and function of components or materials and compliance with the Contract Documents.

2. Include drawings that are to scale.

3. Mark pertinent products or models and show performance characteristics, capacities, dimensions, clearances, anchorages, external connections, or supports required.

4. Submit on 8-1/2- by 11-inch or 11- by 17-inch paper. If paper larger than 11- by 17-inch is required, use 22- by 34-inch paper.

D. Disposition: CONTRACTING OFFICER OR CONTRACTING OFFICER’S REPRESENTATIVE will review and mark up submittals and distribute marked-up copies as described below.

1. Approved:

a. One copy to CONTRACTING OFFICER or CONTRACTING OFFICER’S

REPRESENTATIVE

b. One copy returned to CONTRACTOR

c. CONTRACTOR may begin Work described in the submittal

2. Approved as Noted:

a. One copy to CONTRACTING OFFICER or CONTRACTING OFFICER’S

REPRESENTATIVE

b. One copy returned to CONTRACTOR appropriately annotated.

c. CONTRACTOR may begin Work described in submittal in accordance with CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE notations, subject to CONTRACTOR’s written

01 33 00 3 SUBMITTAL PROCEDURES

verification and acceptance of CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE notations.

3. Disapproved:

a. One copy retained by CONTRACTING OFFICER OR CONTRACTING

OFFICER’S REPRESENTATIVE.

b. One copy returned to CONTRACTOR appropriately annotated.

c. CONTRACTOR shall make corrections or develop a replacement submittal and resubmit.

4. Incomplete:

a. One copy retained by CONSTRUCTION MANAGER.

b. One copy returned to CONTRACTOR appropriately annotated.

c. CONTRACTOR shall complete and resubmit or submit missing portions of the submittal.

1.4 SAMPLES

A. Unless otherwise noted, submit three samples for each required submittal.

B. Sample submittals are those submittals that reflect type or quality of product. All sample submittals shall contain the following information:

1. The date of submission and the dates of any previous submissions.

2. The project title and number.

3. The name of CONTRACTOR (and Subcontractor where applicable).

4. Identification of the items/submittal/product, with the Specification section number, page, and paragraph(s), and Drawing reference, if any.

5. Applicable standards, such as American Society for Testing and Materials

International (ASTM), American National Standards Institute (ANSI), or Federal Specification numbers.

6. Identification of deviations from Contract Documents.

7. Identification of revisions on resubmittals.

8. Source, location, date obtained, and who obtained the sample.

C. Prepare the sample submittal as follows:

1. Present in a clear and thorough manner. Include sufficient detail to show the kind, size, arrangement, and function of components or materials, and compliance with the Contract Documents.

2. Mark pertinent products or models and show performance characteristics, capacities, dimensions, clearances, anchorages, external connections, or supports required.

D. Disposition: CONTRACTING OFFICER OR CONTRACTING OFFICER’S REPRESENTATIVE will review and mark up submittals and distribute marked-up copies as described below.

1. Approved:

a. One copy of transmittal and one sample to CONTRACTING OFFICER or

CONTRACTING OFFICER’S REPRESENTATIVE.

b. One copy of transmittal and one sample to CONTRACTOR.

c. CONTRACTOR may begin Work described in the submittal.

2. Approved as Noted:

01 33 00 4 SUBMITTAL PROCEDURES

a. One copy of transmittal, with annotations, and one sample to CONTRACTING OFFICER or CONTRACTING OFFICER’S

REPRESENTATIVE.

b. One copy of transmittal, with annotations, and one sample to

CONTRACTOR.

c. CONTRACTOR may begin Work described in submittal in accordance with CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE notations, subject to CONTRACTOR’s written verification and acceptance of CONTRACTING OFFICER or CONTRACTING OFFICER’S REPRESENTATIVE notations.

3. Disapproved:

a. One copy of transmittal and one sample retained by CONTRACTING

OFFICER OR CONTRACTING OFFICER’S REPRESENTATIVE.

b. Remaining samples returned to CONTRACTOR appropriately annotated.

c. CONTRACTOR shall make corrections or develop a replacement submittal and resubmit.

4. Incomplete:

a. One copy of transmittal, with annotations, and one sample retained by

CONTRACTING OFFICER OR CONTRACTING OFFICER’S

REPRESENTATIVE.

b. Remaining samples returned to CONTRACTOR appropriately annotated.

c. CONTRACTOR shall complete and resubmit or submit missing portions of the submittal.

1.5 ADMINISTRATIVE SUBMITTALS

A. Copies: Submit one electronic copy of administrative submittals.

B. Administrative submittals are those submittals that do not reflect quality of product or method of construction. Administrative submittals include, but are not limited to, the following items:

1. Submittals Required By Law, Regulations Or Governing Agencies.

C. All administrative submittals shall contain the following information:

1. The date of submission and the dates of any previous submissions.

2. The project title and number.

3. The name of CONTRACTOR (and Subcontractor where applicable).

4. Identification of the items/submittal/product, with the Specification section number, page, and paragraph(s), and Drawing reference, if any.

5. Identification of deviations from Contract Documents.

6. Identification of revisions on resubmittals.

D. Prepare the administrative submittal as follows:

1. Present in a clear and thorough manner. Include sufficient detail to show compliance with the Contract Documents.

2. Include drawings that are to scale.

3. Prepare schedules in accordance with the applicable…